austlii:cth/FWCA/2019/8512
appellant. The Agreement was approved and will operate from 24 December 2019 with a nominal expiry date of 31 July 2021.
1 cited instrument linked from this judgment.
The Fair Work Commission approved an enterprise agreement for Kenshaw Electrical Pty Limited covering mechanical, electrical and store workers. The employer provided written undertakings to address concerns, which the Commission accepted after being satisfied they would not disadvantage employees or substantially change the agreement. The agreement will operate from 24 December 2019 until 31 July 2021.
AI-generated legal information, not legal advice. Zoe can make mistakes. Check the cited source, and for advice about your situation consult a qualified Australian lawyer.
s.185 - Enterprise agreement
KENSHAW ELECTRICAL PTY LTD MECHANICAL, ELECTRICAL & STORE WORKERS COLLECTIVE AGREEMENT 2019-2021
Application for approval of the Kenshaw Electrical Pty Ltd Mechanical, Electrical and Store Workers Enterprise Agreement 2019-2021.
[1] An application has been made for approval of an enterprise agreement known as the Kenshaw Electrical Pty Ltd Mechanical, Electrical and Store Workers Enterprise Agreement 2019-2021 (Agreement). The application was made pursuant to section 185 of the Fair Work Act 2009 (Act). The Agreement is a single enterprise agreement.
[2] The Employer has provided written undertakings (Undertakings). A copy of the Undertakings is attached in Annexure A to this decision. I am satisfied that the effect of accepting the Undertakings is not likely to:
(a) cause financial detriment to any employee covered by the Agreement; or
(b) result in substantial changes to the Agreement.
[3] The views of each person who the Fair Work Commission knows is a bargaining representative for the Agreement have been sought in relation to the Undertakings.
[4] Pursuant to subsection 190(3) of the Act, I accept the Undertakings. The Undertakings are taken to be a term of the Agreement.
[5] Subject to the Undertakings, I am satisfied that each of the requirements of sections 186, 187, 188 and 190 as are relevant to this application for approval have been met.
[6] The Agreement is approved and, in accordance with section 54 of the Act, will operate from 24 December 2019. The nominal expiry date of the Agreement is 31 July 2021.
Printed by authority of the Commonwealth Government Printer
The Agreement was approved and will operate from 24 December 2019 with a nominal expiry date of 31 July 2021.