(1) A person referred to in section 8(1) who is or who claims to be entitled to a progress payment under a construction contract ( the claimant) may serve a payment claim on the person who , under the construction contract concerned, is or may be liable to make the payment."
30 The words (and commas) that I have underlined were inserted into the subsection by the Amendment Act. The words that I have shaded were deleted from the subsection by the same Act.
31 Before the commencement of the Amendment Act, Pt 2 of Schedule 2 to the Act (Schedule 2 contained Savings and Transitional Provisions, and was given effect by s 37) read as follows:
" 2 Certain construction contracts not affected
A provision of this Act does not apply to a construction contract entered into before the commencement of that provision."
32 The Amendment Act added the following Pt 3 to Schedule 2:
" 3 Application of amendments
An amendment made to this Act by the Building and Construction Industry Security of Payment Amendment Act 2002 does not apply to or in respect of a payment claim served before the commencement of the amendment and any such payment claim is to be dealt with in accordance with this Act as if the amendment had not been made."
Analysis: jurisdictional fact
33 As s 13(1) now stands, a person who is or who claims to be entitled to a progress payment ("the claimant") may serve a payment claim. The person on whom the claim is served ("the respondent") may reply by providing a payment schedule (s 14). If the parties remain in dispute then the claimant may apply for adjudication. The respondent may lodge an adjudication response (s 20). The adjudication response is not to include "any reasons for withholding payment unless those reasons have already been included in the payment schedule provided to the claimant" (s 20 (2B)). In determining the entitlement (if any) of the claimant, the adjudicator is to consider only the matters specified in s 22(2). Those include the payment claim, together with its supporting documents, and the payment schedule, together with its supporting documents.
34 It would follow that the adjudicator cannot determine the entitlement of the claimant by reference to any "defence" that is not contained in the payment schedule (or in any other "matter" to which the adjudicator can have regard under s 22(2)). Conversely, the adjudicator is required to determine only those matters that are raised in the material to which, under s 22(2), he or she can have regard.
35 It is a necessary consequence of the amendments effected by the Amendment Act that a person may make a payment claim without being, in fact or in law, entitled to be paid a progress payment. But the statutory mechanism must still be followed through. The respondent, should it wish to dispute the claim, must provide a payment schedule. If the matter goes to adjudication and the respondent still wishes to oppose the claim it must provide an adjudication response. If the relevant disentitling circumstance is not alleged in the payment schedule or in the adjudication response, then the likely, and perhaps inevitable, consequence is that the adjudicator will determine the claimant's entitlement without regard to that circumstance. Indeed, I think, s 22(2) of the Act effectively recognises that this may be so.
36 If the flaw in the claimant's entitlement is the absence of some factual circumstance, and if (as I think is the case) the adjudicator may nonetheless determine the application in the claimant's favour (because absence of that factual circumstance has not been relied upon as a ground of opposition), then it is hard to see how that factual circumstance could be characterised as a "jurisdictional fact".
37 It is one thing to say that s 8 of the Act specifies the entitlement to a progress payment as something existing "[o]n and from each reference date under a construction contract." It is quite something else to say that the reference date is thereby made a jurisdictional fact if the matter goes to adjudication. If the payment claim has no reference to a reference date, that may be a valid basis of opposition. But it does not mean that the claimant is anything other than "a person who … claims to be entitled to a progress payment". It does not mean that the adjudicator is required to make a positive finding as to a reference date, or that the adjudicator can rely on the absence of a reference date to find against the claimant where that point has not been raised by the respondent in its payment schedule or adjudication response.
38 If the existence of a reference date were regarded as a jurisdictional fact - something to be proved as a matter of fact before the adjudicator could proceed - then the adjudicator would be required to consider that matter explicitly. Further, it is at least arguable that it would not be a fact that could be established by the agreement, admission or concession of the parties. In other words, the parties could agree, for the purpose of the adjudication, that the claim was made by reference to a reference date under the contract: and yet, if this proved not to be the case, the respondent could later (subject to what I say in para [110] below as to discretionary considerations) take the point in proceedings to quash the determination.
39 The Act does not specify, expressly or by implication, that an adjudicator is required to be satisfied as to the relevant reference date before proceeding further with the adjudication. Instead, I think, it leaves it to the parties (in the usual case, the respondent) to raise the point if it is appropriate to do so. If the point is raised, then it is one that the adjudicator can determine. For the reasons given by Spigelman CJ in Timbarra at 65 [44], that would suggest that the existence of a relevant reference date is not a jurisdictional fact.
40 Kembla relied on the decision of Einstein J in Emag Constructions Pty Limited v High Rise Concrete Contractors (Aust) Pty Limited [2003] NSWSC 903. In that case, as appears from para [56], the adjudicator determined that the adjudication application had been served on 4 June 2003, whereas the court held that it was served no earlier than 12 June 2003. The time within which the respondent could lodge its adjudication response was, therefore, 19 June 2003. In fact, it was lodged on 16 June 2003. But the adjudicator held that it was out of time and did not consider it. Einstein J said that the adjudicator thereby misled and impeded the respondent as to its entitlement to lodge an adjudication response. More significantly, his Honour held that the determination was made before the end of the period within which the adjudication response might be lodged: and this was expressly forbidden by s 21(1) of the Act. As I read his Honour's reasons, it was this last circumstance that, as he said, "vitiates the validity of the adjudicator's determination". His Honour did not hold that the determination was vitiated because the adjudicator erroneously found, as a jurisdictional fact, that the adjudication application had been served on a particular date. It was vitiated because the adjudicator made his determination at a time when, by statute, he could not do so. I do not think that the decision in Emag provides any support for Kembla's position on this issue.
41 All of this assumes that the relevant transitional provision is that contained in Pt 3 of Schedule 2 to the Act rather than in Pt 2 of that schedule. In my judgment, it is Pt 3 that is relevant for present purposes. Part 2 was intended to ensure that, when the Act originally commenced, a provision of the Act would not apply to a construction contract entered into before the commencement of that provision. I do not think that it was intended, following the commencement of the Amendment Act, that Pt 2 would apply not just to what I might call the original provisions of the Act but also to the provisions introduced, or amended, by the Amendment Act. That was clearly the function of Pt 3. There can have been no other legislative purpose underlying Pt 3.
42 If, as I think is the case, it is Pt 3 that is relevant, then it is accepted that the relevant provisions are those as amended.
43 I therefore do not consider that the first and second challenges show that the adjudicator proceeded without jurisdiction, because of the absence of a necessary jurisdictional fact.
44 In case I am wrong in this analysis, I will consider the submissions of the parties based on the provisions of cl 37 of the contract, the Superintendent's direction given on 25 March 2004 and the consequence of the payment claim's including (as it did) an amount admitted but unpaid that was included in an earlier claim.
Analysis: clause 37; Final Payment Claim
45 Clause 42.7 provides that a "Final Payment Claim" is to be made "[w]ithin 28 days after the expiration of the Defects Liability Period or where there is more than one, the last to expire". The submission for Kembla was that a separate Defects Liability Period specified in a direction given under cl 37 was, therefore, to be considered in applying cl 42.7.
46 It will be noted that cl 37 refers to a Defects Liability Period commencing on the Date of Practical Completion. The expression "Defects Liability Period" is not otherwise defined in the contract. However, the contract and its annexure direct attention to "Separable Portions" of the Works.
47 It is agreed that there were three separable portions. Of those, separable portion 2 could not be commenced until after completion of separable portion 1, and separable portion 3 was "to be considered as Provisional and may be deleted from the Scope of Works of this Contract".
48 In the annexure to the contract, there was specified a defects liability period for separable portion No. 1 of "26 weeks from completion of Portion 2". There were specified for separable portions Nos. 2 and 3 defects liability periods of "26 weeks".
49 The reference in cl 42.7 to "more than one" Defects Liability Period is, therefore, capable of picking up the separate defects liability periods for the separable portions of the works. However, at least as to separable portions Nos. 1 and 2, it would appear that the defects liability periods are concurrent. The question is whether the reference in cl 42.7 to "more than one defects liability period" also includes any defects liability period arising as the result of a direction given by the Superintendent pursuant to clause 37. Kembla submits that it does. Select submits that it does not.
50 There is a practical problem with Kembla's submission. A claim under cl 42.7 is to be lodged "within 28 days after the expiration of" the relevant Defects Liability Period. A direction under cl 37 may be given up to 14 days after the expiration of the Defects Liability Period that commences on the Date of Practical Completion. Select could, in theory, lodge a Final Payment Claim under cl 42.7 on the day following the expiration of the Defects Liability Period (or the last of any several Defects Liability Periods). That would be a valid final payment claim under cl 42.7. However, the Superintendent could, within the next 12 or 13 days, give a direction under cl 37 that included a specified separate Defects Liability Period for works of rectification. On Kembla's argument, the effect of that direction would be retrospectively to deny to Select the ability to lodge a Final Payment Claim. The inevitable consequence of Kembla's submission is that a claim that was properly lodged as, and is properly to be regarded as, a Final Payment Claim could lose that character retrospectively because of a direction given under cl 37.
51 On balance, and notwithstanding that problem, I think that the expression "Defects Liability Period" in cl 42.7 should include not only one arising expressly under the contract or, where there are separate periods for separable portions of the works, each such period, but also one arising pursuant to a direction given by the Superintendent under cl 37. That seems to be confirmed by the statement in cl 37 that "Clause 37 shall apply in respect of the Work of Rectification and the Defects Liability Period for that Work of Rectification".
52 The construction is also consistent with the philosophy, clearly apparent in the contract, that no final accounting between the parties should take place until all work has been completed and all defects have been rectified. If they are not rectified by the Contractor then, as cl 37 makes clear, they may be rectified by the Principal at the Contractor's expense and the cost "shall be a debt due". It would be strange to enable the Contractor to ignore its obligations in respect of defects rectification (including under any extended Defects Liability Period arising from a direction of the Superintendent) but, at the same time, obtain final payment, without deduction, of all money owing to it by the Principal.
Validity of the clause 37 notice: issues
53 That would therefore raise the question, whether the clause 37 notice was given in time. That turns on two things. Firstly, whether the Defects Liability Period commenced on the Date of Practical Completion (13 September 2003) so that it expired on 12 March 2004, or from the Date of Practical Completion, so that it expired on 13 March 2004. If the former date is correct, it will also require consideration of the question, whether the partially illegible direction sent by facsimile transmission on 25 March 2004 was effective as a direction under cl 37, or whether it was receipt of the completely legible copy on 26 March 2004 that constituted the effective direction.
Time commencing "on" a day
54 In Ex parte Toohey's Ltd: Re Butler (1934) 34 SR (NSW) 277, Jordan CJ at 285-286 said:
" The general rule is that in computing a period of time from the date, or the day of the date, of a deed, or any fixed day - that day is prima facie to be excluded, but the context or other admissible evidence may show that it is to be included; whereas in computing a period of time which commences on a fixed day, that day is included … ".
55 Similar views have been expressed in England: see Zoan v Rouamba [2000] 1 WLR 1509, 1516-1517 (Chadwick LJ); Trow v Ind Coope (West Midlands) Ltd [1967] 2 QB 899, 923, 925-926 (Salmon LJ); and Sidebotham v Holland [1895] 1 QB 378, 382 (Lindley LJ, with whom Lord Halsbury agreed). The effect of those decisions is summarised by what Salmon LJ said in Trow at 926:
" Sidebotham v Holland seems to me to re-affirm what has hitherto never been doubted, namely that when a period of time is required to be calculated as beginning on or with a certain date, that date must be included in the calculation."
56 Kembla relied upon statements in Norton on Deeds (Wm W Gaunt & Sons, Inc 1981) at 178-179 and Lewison, The Interpretation of Contracts (2nd Ed, Sweet and Maxwell, 1997) at 368-370. The passages from Norton relied upon do not deal in terms with the computation of a period of time that begins "on", rather than "from", a date. The passages relied upon from Lewison do, but in my opinion they misstate the effect of the authorities. Thus, at 370, Lewison relies on the judgment of Lindley LJ in Sidebotham, for the proposition "that it makes no difference whether the term is said to begin "from" or "at' or "on" a day. However, as Salmon LJ in Trow made clear, Lindley LJ was not seeking to displace the well settled principles of construction relating to the computation of periods of time running from a particular day. Further, as Lindley LJ made clear, the particular proposition was one relevant to the validity of a notice to quit; and I do not think that his Lordship intended it to be read any wider.
57 There is another problem with Lewison, in that it refers in a footnote to Trow, but only to the dissenting judgment of Lord Denning MR. It does not refer to the judgment of Salmon LJ (or to the short judgment of Harmon LJ, who with Salmon LJ constituted the majority); and, as I have shown, Salmon LJ clearly demonstrates that different considerations apply where the computation is expressed to commence "on", rather than "from", a particular day.
58 In any event, I think that the question is for present purposes effectively settled by what Jordan CJ said in Ex parte Toohey's; and, particularly where his Honour's analysis is consistent with subsequent authority, I should not be distracted from it by expressions of opinion in learned writings.
59 In the present case, the introductory words of cl 37 - specifying that the Defects Liability Period "shall commence on the Date of Practical Completion" are in clear contrast to other provisions of the contract where expressions such as "within [28 or 14 or 7] days after … " are used: see, by way of example only, cls 35.5, 38, 42.1, 42.5, 42.7 and 42.8 (this list is by no means comprehensive).
60 In context, I think that the drafting distinction must be taken to be deliberate, and that the parties must have intended to intend, by referring to a Defects Liability Period commencing on the Date of Practical Completion, that the date of commencement was included within that Defects Liability Period.
61 It follows that the relevant notice is the facsimile version, because the posted (and fully legible) version was not "given" to Select within the period allowed by cl 37. (I interpolate, in case it is not clear, that Kembla did not suggest that the posted version was "given" within time even if its submissions as to the proper construction of cl 37 were rejected.)
Validity of the notice - legibility etc
62 In my judgment, the version of the direction that was given by facsimile transmission on 25 March 2004 must be taken to be a valid direction to the extent that, read as a whole, it identified any particular omission or defect. If the identification of a particular defect depended upon the photographs - ie, if the defect could not be identified except by looking at the photographs - then the direction was not, in my judgment, effective. Where, however, identification of the defect did not require reference to a photograph (either because the document itself did not refer to a photograph or because, where it did, Select did not need to look at the photograph to identify the defect) then the direction was sufficient. I see no reason why the entirety of the direction should be struck down because part of it was inadequate. That would be so whether the inadequacy arose because identification of the defects necessarily required reference to the photographs, and the photographs were not legible, or because identification of the defect was, for any other reason, insufficient.
63 Further, I think, the matter is to be looked at objectively, by enquiring what the notice would convey (as to any particular alleged defect) to a reasonable and competent contractor in the position of Select.
64 The identification of the missing step irons was in the following terms: