Seventh issue: should Dial D have judgment?
75The conclusions that I have reached so far include that the final certificate contains an error, or erroneous computation, because it includes the value assigned by the superintendent to the deemed variation: $840,000.00.
76In addition, there are the unresolved issues that are the subject of the notice of dispute dated 7 February 2013. That notice of dispute effectively takes issue with the superintendent's determination of every claim made by Kingston in its progress claim 25. It is common ground that the superintendent's response to that is to be found in a document known as payment certificate 26.
The parties' submissions
77Mr Corsaro's comparison of progress claim 25 with payment certificate 26 shows that there were many hundreds of thousands of dollars claimed in respect of variations but not allowed. It is correct to say, as Mr Corsaro submitted, that the claims and the certifications were varied thereafter. Nonetheless, as Mr Corsaro's schedule shows, the unresolved issues on the variations alone exceed $900,000.00 in total. In addition, the backcharges for alleged defects and liquidated damages total about $370,000.00. Those backcharges too are the subject of the notice of dispute given on 7 February 2013, and thus form part of the "unresolved issues" that have been referred to arbitration.
78The conclusive effect of the final certificate (assuming that it is otherwise valid) is thus subject to the exceptions under para (c) - the erroneous inclusion of the value of the deemed variation in the computation of the balance due - and para (d) - the unresolved issues of about $910,000.00 in respect of variations and $370,000.00 in respect of backcharges.
79Mr Corsaro submitted that none of this mattered, because the effect of the exceptions was to detract from the conclusive effect of the final certificate, but not to qualify or negate the obligation to pay the amount that it stated as due and payable.
80Mr Corsaro submitted that the scheme of cl 37.4 was as follows:
(1) the contractor is required to give a final payment claim;
(2) thereafter, the superintendent is required to issue a final certificate "evidencing the moneys finally due and payable...";
(3) the amount so "certified as due and payable" is to be paid by the debtor to the creditor within seven days thereafter; and
(4) the final certificate is conclusive evidence of accord and satisfaction and the discharge of each party's obligations in connection with the contract except for matters falling within the four lettered subparagraphs.
81It followed, Mr Corsaro submitted, that the exceptions to the conclusive effect of the certificate were not exceptions to, or qualifications of, the obligation to pay the moneys certified by it as being due and payable.
82Mr Rudge relied on the decision of the Court of Appeal of the Supreme Court of Queensland in Martinek Holdings Pty Ltd v Reed Construction (Qld) Pty Ltd [2009] QCA 329. In that case, Keane JA (with whom de Jersey CJ and Holmes JA agreed) concluded at [20], having considered cl 37.4 of the GCC with which I am concerned, that "it is only the moneys certified as due and payable by a certificate unqualified in its effect by the fourth paragraph of cl 37.4 that give rise to a right to payment in accordance with the third paragraph of cl 37.4".
83Mr Rudge submitted that the reasoning of Keane JA leading to this conclusion was correct, as was the conclusion itself. In any event, he submitted, I should follow the decision, at least unless convinced that it is plainly wrong (and, he submitted, it was not).
84Mr Corsaro submitted that the conclusion was wrong, and that in any event both the conclusion (at [20] of the reasons) and the reasons leading to it were not essential to the actual decision in the case.
The decisions in Martinek
85To understand those submissions, it is necessary to give some close attention to the facts and to the reasons, both at first instance and on appeal. I should say however that I am doing so out of deference to the detailed arguments of counsel, not because I consider myself at liberty to take a different view of the operation of cl 37.4 in this case.
86The first instance decision is that of White J: [2009] QSC 328. As her Honour's reasons show, Martinek was the principal and Reed the contractor in respect of a construction project in Mackay. Their contract included the GCC which I am concerned, and cl 37.4 was relevantly unamended.
87The defects liability period expired on 4 July 2009. On 31 July 2009, Reed submitted its final progress claim. That progress claim was said to be also a payment claim for the purposes of the Building and Construction Industry Payments Act 2004 (Qld). That Act (the Payments Act) is in many respects similar to the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Security of Payment Act).
88Although the superintendent had not dealt with the claim for the purposes of cl 37.4, Martinek nonetheless served a payment schedule to protect its position under the Payments Act. Reed submitted that dispute to adjudication. The adjudicator determined that Reed was entitled to be paid an amount in excess of $919,000.00; the adjudicated amount, including fees and interest, exceeded $946,000.00.
89Thereafter, the superintendent issued his final certificate. That certificate assessed Reed's final payment entitlement at $665,000.00, and amounts due by Reed to Martinek exceeding $730,000.00, leading to an amount due by Reed to Martinek of, again in round figures, $65,000.00.
90Martinek, as White J recorded at [18]:
... conceded that the Final Certificate meant that Martinek had a contractual right to payment of the amount identified as due and payable by Reed to Martinek, ... but it was not final so as to bring about the accounting envisaged in s 100 of the Payments Act.
91I pause to note that s 100 of the Payments Act is, if not identical to, relevantly indistinguishable from, s 32 of the Security of Payment Act.
92Reed gave notice of dispute in respect of the superintendent's final certificate. Thus, as White J said at [30]:
.... it cannot be said that the Final Certificate has finality so as to bring into play the allowance provisions in s 100 of the Payments Act. The Adjudication Decision stands until the final position has been reached between the parties.
93Accordingly, her Honour dismissed Martinek's application for a stay of the adjudicator's determination which, as her Honour said at [1], was in effect "an order restraining [Reed] from proceeding... to seek an Adjudication Certificate and file a judgment in this court".
94The Court of Appeal dismissed the appeal from the decision of White J.
95Keane JA, having briefly summarised the facts, stated Martinek's position as follows, at [6]:
[6] Martinek commenced proceedings in the Trial Division of the Supreme Court contending that the final certificate issued by the superintendent under the contract trumps the adjudication decision by establishing the final position of the parties under the contract. On this basis Martinek argues that Reed may not pursue the inconsistent rights which would otherwise be available to Reed under the Payments Act. It was common ground between the parties at first instance and in this court that the resolution of this issue turns on the interpretation of cl 37.4 of the contract. Before turning to a discussion of the contract, it is desirable to give a brief summary of the relevant provisions of the Payments Act.
96His Honour, having dealt with relevant provisions of the Payments Act and the contract, turned to the decision of White J. He summarised the parties' positions as follows, at [11] (omitting citations):
[11] In the proceedings below, Martinek argued that the superintendent's final certificate operated to supersede the adjudication decision. Reed argued that the superintendent's final certificate gave Martinek a contractual right to payment of $72,027.27 but it did not produce a final settling of accounts which was apt to subsume or supersede the adjudication decision. In this regard, Reed relied particularly (though not exclusively) on the terms of cl 37.4(d) of the contract.
97At [14], Keane JA held that the notice of dispute given by Reed "engaged the terms of cl 37.4(d) to deny to the superintendent's certificate the effect for which Martinek's argument contends".
98His Honour reasoned at [15], [16] that the final settlement of accounts between a contractor and a principal could supersede the interim effect of adjudications under the Payments Act. But that would not happen, his Honour said, until the "accord and satisfaction" and "discharge of obligations" for which cl 37.4 provided took effect. And this had not happened, his Honour said, because of the notice of dispute. I set out those paragraphs:
[15] It may be accepted that the final settling of accounts between contractor and principal established under the terms of the contract may supersede the interim adjudications effected under the Payments Act, but in this case, the terms of cl 37.4(d) of the contract reflect an intention that the "accord and satisfaction" and the "discharge of obligations" between the parties not be effected by the superintendent's certificate while the issues the subject of Reed's notice of dispute remain "unresolved".
[16] It may be accepted that s 100(1)(a) of the Payments Act provides that the rights conferred by the Payments Act upon a party who has the benefit of an adjudication decision must ultimately yield to "any right that a party to a construction contract may have under the contract". But under the terms of cl 37.4(d) of the contract, the superintendent's certification has not yet come into effect to entitle Martinek to refuse payment of the adjudication amount, save insofar as the sum of $72,027.27 may properly be set off against the adjudication amount.
99At [17] his Honour dealt with an argument that "the second and third paragraphs of cl 37.4 are to be read separately from the fourth paragraph" (at the risk of stating the obvious, his Honour was referring to the unnumbered paragraphs within cl 37.4, not to the lettered subparagraphs). That argument was conceptually related, although not identical, to the submissions put by Mr Corsaro that I have noted at [80], [81] above.
100Keane JA rejected the argument. He said that the paragraphs should be construed to work harmoniously each with the other. It followed, in his Honour's view, that the fourth paragraphs both explained and qualified the effect of the second and third paragraphs. I set out [17]:
[17] On Martinek's behalf it is argued that the second and third paragraphs of cl 37.4 are to be read separately from the fourth paragraph. That argument is unpersuasive for two reasons. First, one must attempt to give all the paragraphs of cl 37.4 an operation by which each paragraph works in harmony with the others: the fourth paragraph should not be read as an operative stand alone provision; rather, its natural reading is as an explanation and qualification of the effect of the second and third paragraphs. Secondly, both the second and the fourth paragraphs of cl 37.4 speak in terms of the evidentiary effect of the superintendent's certificate: that is an express invitation to treat the fourth paragraph as an explanation and qualification of the effect of the superintendent's certificate as "evidencing the moneys finally due and payable between the Contractor and Principal on any account ... in connection with the subject matter of the contract."
101Then, after having referred to my decision in John Holland Pty Ltd v Roads and Traffic Authority of NSW, and the decision of the Court of Appeal therefrom (see respectively (2006) 66 NSWLR 624 and [2007] NSWCA 140), and having referred to the transfer of the risk of insolvency effected by the Payments Act, his Honour stated the conclusion at [20] that I have set out above.
Decision
102Mr Corsaro relied on the concession made by Reed, as recorded at [18] of the reasons of White J. This showed, he submitted, that the contractual entitlement to payment of the certified amount was not an issue in the litigation. That was confirmed, Mr Corsaro submitted, by the apparent repetition of the concession at [11] of the reasons of Keane JA.
103I accept that a close reading of the reasons shows that the precise issue in the litigation was whether the superintendent's final certificate was conclusive, as White J put it at [30], to bring into play the "allowance provisions" in s 100 of the Payments Act: "until the final position has been reached between the parties".
104That having been said, Keane JA directed attention to why it was that the certificate did not "entitle Martinek to refuse payment of the adjudication amount". It did not do so, his Honour said, because that certificate "has not yet come into effect" (both quotations come from [16] of his Honour's reasons).
105To my mind, the analysis that Keane JA gave, of the structure and operation of cl 37.4, at [17] of his reasons, is the explanation of why it is that the certificate "has not yet come into effect to entitle Martinek to refuse payment of the adjudication amount". It did not have that effect, his Honour said, because the "explanation and qualification" in the fourth paragraph applied to each of the second and third paragraphs. In particular, and again as his Honour said, it explained and qualified the second paragraph by depriving the superintendent's certificate of the evidentiary effect stated in that paragraph.
106Because the third paragraph takes as its subject "[t]hose moneys certified as due and payable" (i.e., as referred to in the second paragraph), it must follow that the qualifying effect that the fourth paragraph, if engaged, has on the second paragraph flows through to the third paragraph.
107That, as I understand it, is what Keane JA said far more succinctly and far more clearly at [17]. And, again as I understand it, that is why Keane JA concluded at [20] that "it is only the moneys certified as due and payable by a certificate unqualified in its effect by the fourth paragraph of cl 37.4 that give rise to a right to payment in accordance with the third paragraph of cl 37.4".
108Thus, I do not regard the critical reasoning on which Mr Corsaro focused his attention as being an incidental, rather than a necessary, step leading to the ultimate conclusion. But even if it were not essential to the conclusion, I would be bound to follow it, unless persuaded that it is plainly wrong. I do not regard it as plainly wrong. On the contrary, and if I may say so, it seems to me that his Honour provides a compelling and coherent account of the operation of cl 37.4.
109The effect of Mr Corsaro's submission is that the contractor (in this case, Kingston) would be required to pay the principal (in this case, Dial D) the full amount of the certification, even though there were (as there is in this case) a dispute as to the principal's entitlement, which dispute was in the throes of resolution in accordance with cl 42. Indeed, on Mr Corsaro's analysis, the same result would follow even if there were a clear (or arguable) "slip" within subpara (c).
110It may be accepted, as Keane JA observed in RJ Neller Building Pty Ltd v Ainsworth [2008] QCA 397 at [40], that the Payments Act transfers the risk of insolvency, at least until interim accounts are settled on a final basis. It may be accepted, also, that it would be open to parties to a contract to stipulate for the outcome for which Mr Corsaro contended. But clear words would be needed to achieve that outcome. To my mind, cl 37.4, considered as a whole, falls far short of the necessary degree of clarity.