The alleged Progress Certificate
29On 31 January 2013, the Superintendent issued a progress certificate ("the Progress Certificate") which, far from requiring the Proprietor to pay the Builder any money (let alone the $1,170,695.09 in the Progress Claim), purportedly required the Builder to pay the Proprietor $1,067,571.53.
30The Progress Certificate dealt with each of the items in the Progress Claim and, in effect, purported to disallow many of them. The Progress Certificate thus, in terms, contradicted the Progress Claim.
31In issuing the Progress Certificate, the Superintendent evidently relied upon the provisions of clause 37.2 [2]; set out above.
32The Builder had not made a progress claim in January. That was because, the evidence revealed, the Builder had done no work under the Contract after service by it of the Progress Claim at the end of December 2012. The Proprietor submitted that as the Builder had not made a progress claim in January, it was open to the Superintendent to issue a progress certificate contradicting the Progress Claim in the manner I have outlined.
33This is notwithstanding the accrual to the Builder, on account of its ultimate entitlement under the Contract, of a right to payment by reason of the Superintendent's failure to respond to the Progress Claim in the time specified in the Contract.
34Mr Kalyk, who appeared for the Proprietor, submitted that the Progress Certificate had "superseded" the Progress Claim.
35That submission, if correct, would have the effect that in any month when the Builder did not make a progress claim (for example, as here, because it had completed the work) it would be open to the Superintendent to issue a progress certificate that deprived the Builder of its entitlements under any earlier unpaid progress claims.
36That would be an extraordinary result. It would repose in the hands of the Superintendent power to deprive the Builder of an accrued right to payment. It would also give the Superintendent what would effectively amount to a "slip rule", whereby the Superintendent would overcome the effect of its failure to respond to a progress claim in the time limits agreed by the parties by the simple expedient of waiting for a month in which the Builder did not make a progress claim and then issue the progress certificate under cl 37.2 [2].
37In my opinion, looking at the language used by the parties in the Contract, I do not think this is what they intended.
38First, the position of cl 37.2 [2] within the body of cl 37.2 points against the conclusion that this is what the parties intended.
39Clause 37.2 [2] appears before cl 37.2 [3] (which deals with the consequence of the Superintendent not issuing a progress certificate within 14 days of the receipt of a progress claim); before cl 37.2 [4] (which contains the Proprietor's obligation to pay) and before cl 37.2 [5] (which emphasises that a progress claim is "on account" only).
40That suggests to me that the parties did not intend cl 37.2 [2] to give power to the Superintendent to deprive the Builder of accrued rights arising from subsequent subparagraphs of cl 37.2.
41Second, and perhaps more importantly, cl 37.2 [2] must be read together with "Item 28" to which it refers. When those provisions are read together, cl 37.2 [2] reads:
"If the Contractor does not make a progress claim [by the 25th day of each month for work under the Contract done to the 25th day of that month], the Superintendent may issue the progress certificate with details of the calculations and shall issue the certificate in paragraph (b)." (emphasis added)
42This makes clear, in my opinion, that the parties intended that cl 37.2 [2] only be enlivened when the Builder did not make a progress claim, by the 25th of the month, for work the Builder had done in that month. In my opinion, the clause is not enlivened where, as here, the Builder made no progress claim during the month because it did no work.
43It follows, in my opinion, that the occasion for the Superintendent to issue a progress certificate under cl 37.2 [2] has not arisen. The purported Progress Certificate of 31 January 2012 is of no effect.
44In those circumstances, I do not consider that cl 46.2 of the Contract has any role to play. That clause is to the effect that a failure by the Superintendent to set out a relevant matter (for example a deduction) in one progress certificate does not affect its entitlement to do so in a later progress certificate. That clause does not, in my opinion, give the Superintendent an entitlement to issue a progress certificate which it does not otherwise have.
45Rolfe J, in Algons Engineering Pty Limited v Abigroup Contractors Pty Limited [1997] NSWSC 478, dealt with a similar provision to cl 37.2[2]. His Honour rejected a submission that the Superintendent was not entitled to issue a progress certificate in circumstances where the Builder had not made a claim for payment. It is not clear from the judgment that the argument before his Honour was developed as it has before me. His Honour dealt with the matter very briefly.
46In those circumstances, I do not see anything in his Honour's decision to deflect me from the conclusion to which I have come.
47I make these declarations and orders: -
(1)Declare that the purported progress certificate issued on or about 31 January 2013 was and is void and of no effect under the terms of the Contract made between the parties on 31 March 2010.
(2)Enter judgment for the plaintiff against the defendant in the sum of $1,170,695.09.
(3)Order that the defendant pay the plaintiff's costs of the proceedings.
(4)Order that the judgment in par 2 be stayed until 5pm on 8 March 2013.
(5)Order that the injunction granted by the McDougall J in the proceedings be extended until 5pm on 8 March 2013.
(6)Grant the parties liberty to apply to me on short notice.