Ground 2 - Proper construction of clause 37.2
43Ground 2 of the notice of appeal alleges error in the finding that the Superintendent was not entitled pursuant to clause 37.2 to issue the January payment certificate. To the extent that it is predicated on error in relation to the construction of clause 37.1 (by the use of the words "and, accordingly" at the end of paragraph (a) of Ground 2), that has not been established and the ground would fail. Assuming, however, that what is in issue (under this ground or under Ground 4) is the proper construction of clause 37.2 even if the proper construction of clause 37.1 is as I consider it to be, is there an error in his Honour's finding?
44Mr Corsaro submits, in effect, that the fact that work under the contract has not been carried out during the relevant month is irrelevant because it nevertheless remains the case that Kingston has not issued a progress claim "in accordance with Item 28". In other words, the fact that Kingston may not have been required to do so, or that there was no occasion or basis that called for it to do so, is irrelevant; if it did not do so then the power of the Superintendent to issue one or both of the certificates provided for in clause 37.2 is enlivened. I consider that argument to be correct.
45The construction for which Dial D contends treats the words "in accordance with Item 28" in clause 37.2 as descriptive in the sense that they focus attention on whether the contractor has made a progress claim that meets the description in or is in conformity with Item 28 (i.e., "for WUC done to the 25th of the month") and is issued within the time specified in Item 28, such that the reason for it not having been issued is irrelevant.
46In Walker v Wilson (1991) 172 CLR 195 Deane, Toohey and McHugh JJ at 208 said "the words 'in accordance with' should be construed as meaning 'in conformity with' or 'consistently with'" (followed by this Court in Winn v Director General of National Parks and Wildlife and Ors [2001] NSWCA 17 at [250] per Stein JA).
47Relevantly, what clause 37.2 is addressing is not whether there was a requirement to issue a claim under clause 37.1 but whether a claim in conformity with ("in accordance with") Item 28 had been issued. With respect to his Honour, I consider that, on the ordinary meaning of the words in clause 37.2, all that is required to give rise to the entitlement, in the case of the 37.2(a) certificate, and the obligation, in the case of the 37.2(b) certificate, on the part of the Superintendent to issue the clause 37.2 certificates is that, as a matter of fact, the contractor has not, by the 25th of a month, made a progress claim for work under the contract, as defined, done to that month (i.e., up to and including that month). If no such progress claim has been issued then, whether or not the contractor was entitled or obliged to make such a claim, the fact is that there has been no such claim and the second paragraph of clause 37.2 is engaged. This is so whether or not the reason that no claim has been made by the contractor is that all work has been dealt with in previously certified progress claims.
48As adverted to above, Mr Corsaro relied, in support of his contended construction of the clause, on clause 37.2 being the only mechanism by which payment could be required for various amounts as certified by the Superintendent. I do not consider that to be a compelling argument in favour of his construction, though I think that is the better construction for the reasons set out above. The fact that other clauses refer to certification of amounts does not mean that clause 37.2 should be interpreted to provide a means for recovery of those amounts on an interim basis if it were not otherwise able to be so construed.
49The reasons for his Honour concluding to the contrary of Dial D's construction were, first, that this was consistent with the placement of the Superintendent's right to issue the certificates within clause 37.2 ([40]; CB 40R) and, second, that clause 37.2 incorporated a reference to Item 28 ([41]; CB 40U-V). I think there is little to be drawn from the first and his Honour did not place much weight on this. The first two paragraphs of clause 37.2 deal with alternative scenarios: one in which the contractor has made a progress claim and one in which it has not. There is thus an internal logic in them being grouped together.
50More important to his Honour's reasoning was the fact that clause 37.2 incorporated a reference to Item 28 and the latter referred to progress claims for work under the contract done to the relevant date of the particular month ([41]; CB 40U-V). However, whether or not the clause permitted the contractor to issue a claim relating to previously certified claims, the relevant fact is that no claim was made in the relevant period.
51Reliance was placed by Mr Corsaro on the decision of Rolfe J in Algons Engineering Pty Limited v Abigroup Contractors Pty Limited [1997] NSWSC 478, where his Honour noted, and summarily rejected, a submission for the party there in the position of Kingston that there was no entitlement on the part of the party in the position of the Superintendent (there referred to as the sub-contractor and main contractor's representative, respectively) to issue a payment certificate when the contractor had not made any claim for payment. However, his Honour rejected that submission by reference to the wording of the particular contract there before him, which was expressed in different words to clause 37.2, in that it provided that if the contractor failed to make a claim the main contractor's representative "may nevertheless issue a payment certificate" (my emphasis). Like his Honour, I do not see Algons as being of assistance in determining the construction of the relevant clause in the present case.
52His Honour considered that if the clause were construed as had been contended for by Dial D, namely, that the January certificate superseded the December progress claim (that was, by operation of the contract a deemed certificate), the Superintendent would be able to deprive the builder of an accrued right to payment ([36]; CB 39W-40B); that this would give to the Superintendent what would effectively amount to a "slip rule"; and that this would be an extraordinary result. His Honour recognised, nevertheless, that any such accrued rights were only on account of whatever might be determined to be the contractor's final entitlement to payment under the contract ([28]).
53Mr Hicks submits that the construction relied upon by Dial D would deprive clause 37 of substance and force; and would make the express obligation to pay effectively meaningless. It is submitted that if the obligation to pay could be superseded on a monthly basis there would be no reasonable opportunity to enforce the obligation. That, however, would be a consequence of the operation of the particular payment regime in question. In any event, the authorities that refer to later certificates "superseding" earlier ones do not suggest that the earlier progress certificates did not give rise to an accrued right - it is simply one that, in some circumstances might not be enforced by reference to other rights later accruing; or that might only be taken into account by way of set-off or by reference to interest payments.
54This raises the question whether the issue of a subsequent certificate by the Superintendent necessarily "supersedes" an earlier deemed certificate, as Mr Corsaro contends. I am not satisfied that a later valid certificate will necessarily have that effect but, even if it does, it does not seem to me to be inconsistent with the payment regime put in place under the contract by which successive payment claims and progress certificates may be issued and the value of the WUC may be progressively adjusted to take into account matters relating to the contract, including the possibility that the Superintendent may have failed to include in an earlier progress certificate a deduction, set-off or the like.
55The language of later progress certificates "superseding" earlier ones is drawn from a series of cases in which the effect of subsequent certificates after earlier invalid certificates (or no certificates) was considered.
56In Zauner Construction Pty Ltd v No 2 Pitt Street Pty Ltd [2001] VSC 154, on which reliance is placed by Mr Corsaro, Byrne J considered a claim for summary judgment for unpaid monthly progress claims in circumstances where the principal defaulted shortly after the building work commenced and work was suspended but the contractor continued to issue monthly progress clams including claims for delay and prolongation costs. The Superintendent issued valid certificates for some of the claims but issued no, or late, certificate for others.
57The contract in question was a different standard form contract from the present (AS 2124-1992) as modified by certain special conditions. The reasons indicated that the contract included a clause that required the principal to pay the amount of the claim within a prescribed time where the superintendent failed to issue a certificate or issued the certificate late, though the terms of that clause were not reproduced in his Honour's judgment. During the course of argument, the Court enquired as to whether a copy of the standard form contract there considered (AS 2124-1992) was available. After judgment was reserved, a copy of the contract was made available through enquiries made by Dial D's lawyers of the legal practitioners who had appeared in the Zauner case. It was received by this Court over the objection of Kingston, which submitted that if it were to be received there should also be put before the Court certain pages of the transcript of the proceedings before Stevenson J and sought leave to put on further submissions. Directions were made in chambers for that to occur.
58In the event, clause 42.1 of the contract considered in Zauner is in broadly similar terms to the corresponding provision extracted in 620 Collins Street Pty Ltd v Abigroup Contractors Pty Ltd (No 2) [2006] VSC 491, to which the Court was taken during submissions. In particular, it included provision that "[i]f the Contractor fails to make a claim for payment under Clause 42.1, the Superintendent may nevertheless issue a payment certificate".
59However, unlike the AS4000-1997 contract in the present case, clause 42.2 of the Zauner contract expressly permitted the Superintendent, at any time and from time to time, by a further certificate to correct any error discovered in any previous certificate, other than a Certificate of Practical Completion or Final Certificate.
60In Zauner, Byrne J said (at [15]):
... The scheme of cl 42.1 is that payment should be made in accordance with the superintendent's certificate. Provided a valid certificate is issued, it matters not that the certificate is in error. It may be corrected by a further certificate issued pursuant to cl 42.2 or by a re-evaluation of the work in a subsequent payment certificate or, perhaps, by a determination pursuant to General Condition 47, as amended by Special Condition 21. An overpayment made pursuant to a certificate may be restored pursuant to cl 47.3. I reject the submission put on behalf of the principal that it is not obliged to pay where the uncertified claim or the sum certified for payment is based on a misapprehension or a misapplication of the contract. (my emphasis)
61His Honour then noted at [16] that:
The contractor is entitled to submit claims for payment including claims for "amounts then due to the Contractor arising out of or in connection with the Contract". These amounts include sums which might be due under cl 44.9 [dealing with damages incurred by suspension of the work] as well as sums under cl 36 [which related to payment for extra costs where an extension of time was granted]. The superintendent is entitled and required to form an opinion as to the amount of the payment which is to be made by the principal to the contractor and to include this in a payment certificate issued within 14 days of receipt of the claim pursuant to cl 42.1. This clause makes clear that certified sums are to be paid and that such payments are to be on account only without prejudice to the entitlement of the principal to dispute the certificate under cl 47 as amended by Special Condition 21. Indeed, the superintendent is entitled under cl 42.1 to issue a certificate notwithstanding that no claim has been made.
62His Honour accepted (at [17]) the contractor's submission that where the superintendent failed to issue a certificate or where the certificate was issued late, the effect of the clauses there under consideration was that the principal was obliged to pay the amount of the claim within the prescribed time. However, his Honour went on at [18] to say:
There is, however, a complication where, following the failure of the superintendent to issue a certificate timeously or at all, a valid certificate is subsequently issued. In the Daysea case a final certificate was issued after an invalid payment certificate. Having concluded that the contractor was entitled to payment of the sum claimed where the payment certificate was invalid because it was late, the Court of Appeal nevertheless refused to give judgment in that sum, for, if paid, it would have to be repaid in accordance with the valid final certificate. It follows, equally, that the obligation to pay which arises from a later valid payment certificate will supersede any entitlement for payment of the sum claimed where no valid certificate has issued. (my emphasis)
63His Honour concluded that various of the claims were cumulative, such that the amount payable in respect of those claims was the amount stated in the last of the series plus any prolongation costs claims which were not included in this sum. However, those claims were followed by a claim that was met with a valid nil certificate. His Honour said that "[t]his certificate supersedes the obligation to pay against the prior uncertified claims" (at [19]), though expressly putting to one side the principal's obligation to pay interest on those uncertified claims pursuant to clause 42.9 of the contract.
64The nil certificate was then followed by a further series of claims, again cumulative, in respect of which the certificates were issued late. His Honour said that, applying the principle in Daysea, the principal's obligation was then to pay the cumulative amount shown in the last of those claims, again putting to one side interest.
65That series of claims was followed by a claim in response to which there was a valid certificate issued, which his Honour noted had certified the value of work included in that claim at a particular amount. His Honour said that the determination of the value of the work performed superseded the contractor's valuation of the work included in the four previous claims (where certificates had been issued late).
66Relevantly, however, the series of progress claims on which summary judgment was sought appear simply to have added, to the value of the work, an amount presumably referable to the delay/suspension costs since no work was being undertaken during the suspension. It is therefore not surprising that each later valid payment claim would supersede the previous one since it, in effect, included that previous one in the new value of work and to allow both would result in double recovery. His Honour, though putting to one side the principal's obligation to pay interest on the claims pursuant to clause 42.9, appeared to accept that interest might be payable on the earlier valid claims. For present purposes, had each subsequent claim simply been a claim for payment of the month's interest/delay/suspension or prolongation costs, and not any earlier certified amounts, then it is difficult to see that it would have been treated as superseding the deemed certified amount for the value of work in the initial claim(s). Therefore, the sense in which the word "superseded" was there used must be borne in mind when considering the position in the present case.
67I consider the effect of the later valid certificate on the earlier deemed progress certificate in the present case in the context of Ground 4 of the notice of appeal.
68Finally, I note that Mr Hicks raised the spectre of a Superintendent in bad faith issuing subsequent certificates to frustrate the ability of the contractor in the interim to enforce a liability to pay under an earlier one. Such conduct would arguably be met by a challenge to the exercise by the Superintendent in such a case of the power in bad faith.
69Therefore, I consider that there was an entitlement on the part of the Superintendent to issue the January certificate and in the absence of any other challenge to its validity the declaration made by his Honour to the contrary should be set aside.