18 Variation Claims V16, V23, V24, V25, V26, V28, V29, V31 and V35 all advance claims for payment consequent upon what the Claimant contends was an extension of time for completion. The Respondent advances a number of reasons why these claims should be disallowed, and it is convenient to consider each of them in turn.
19. The Respondent says (paragraph 24 of its submissions) that unless the delays are included in the value of a variation, such claims are claims for damages which are not properly claimable under the Act. It relies on Kembla Coal & Coke -v- Select Civil & Ors [2004] NSWSC 628 and Quasar Construction -v- Demtech Pty Ltd [2004] NSWSC 116, and seeks to distinguish de Martin & Gasparini -v- Energy Australia & Anor [2002] NSWCA 330, which is relied upon by the Claimant.
The crux of the matter is whether the amounts claimed are delay damages within the meaning of Clause 34.9 of AS 4903-2000 which provides:
"For every day the subject of an EOT for a compensable cause and for which the Subcontractor gives the Subcontract Superintendent a claim for delay damages pursuant to sub-clause 41.1, damages certified by the Subcontract Superintendent under clause 41.4, damages certified by the Subcontract Superintendent under clause 41.4 shall be due and payable to the Subcontractor. … "
The original date for practical completion was 30 March 2004 (see Item 11 of Annexure A to the subcontract). On or about 3 September 2004, the Respondent's Subcontract Superintendent notified the Claimant of altered dates for "practical completion". The final completion date specified in the attachment to this letter was 1 February 2005. In its response, apparently sent on 6 September 2004, this last date was stated by the Claimant to be "achievable". Not withstanding that the cautious language of its letter of 3 September avoided reference to an extension of time, the Respondent's letter is headed "Works Progress & Practical Completion". It contained an instruction to complete "your agreements for the nominated levels as the determined practical completion dates as listed in the attached schedule". Furthermore it referred to revised dates as having been assessed in accordance with Clause 34 and 34.5. It seems to me that thereby the Respondent brought about an extension of time under the subcontract, opening the door for the Claimant to proceed with a claim for delay costs under the contract. Resulting as they do from an extension of time for completion, these claims are variation claims and are properly included in progress claims.
11 The second defendant made the following additional relevant findings:
· The Contract Superintendent had directed an extension of time under clause 34.5 of the Contract which was "necessary" to enable the defendant to complete the work and to remain on site beyond the original contract period which contemplated completion by 30 March 2004 (par 22);
· The delay in question was a compensable cause within the meaning of clause 34.9 that entitled the defendant to claim damages (par 23);
· The tax invoices and the relevant progress claims satisfied the requirements of clause 41.2 (par 25);
· When a claim is made under clause 34.9, the circumstances on which the claim for "delay damages" or "delay costs" is based is the default of others which establishes the compensable claim, and the granting by the Contract Superintendent of the EOT, without which "delay damages would not be payable" (par 26);
· The defendant did as required by clause 41.3, giving notice in accordance with the requirements of clause 41.2 quantifying month by month the "monthly delay costs" (par 28);
· The legal basis for each claim is identified as being clause 34.9 of a Contract and the facts relied on clearly enough were the delay in time for completion month by month after 30 March 2004 (par 30); and
· The details provided in the attachments to the invoices are the basis of the claimed variations and on their face they seem to comprise proper components of "delay costs" which should be accepted as being incurred because of the delay occasioned by others so as to make them compensable costs (par 37).
The Act
12 Under s 8 of the Act a person who has undertaken to carry out construction under a construction contract or supply related goods and services under the contract is entitled to a progress payment. Other relevant sections of the Act are as follows:
13 Payment Claims
(1) A person referred to in section 8 (1) who is or who claims to be entitled to a progress payment (the claimant ) may serve a payment claim on the person who under the construction contract concerned, is or may be liable to make the payment.
(2) A payment claim:
(a) must identify the construction work (or related goods and services) to which the progress payment relates, and
(b) must indicate the amount of the progress payment that the claimant claims to be due (the claimed amount ), and
(c) must state that it is made under this Act.
5 Definition of "construction work"
(1) In this Act, construction work means any of the following work:
(a) the construction, alteration, repair, restoration, maintenance, extension, demolition or dismantling of buildings or structures forming, or to form, part of land (whether permanent or not),
(b) the construction, alteration, repair, restoration, maintenance, extension, demolition or dismantling of any works forming, or to form, part of land, including walls, roadworks, power-lines, telecommunication apparatus, aircraft runways, docks and harbours, railways, inland waterways, pipelines, reservoirs, water mains, wells, sewers, industrial plant and installations for purposes of land drainage or coast protection,
(c) the installation in any building, structure or works of fittings forming, or to form, part of land, including heating, lighting, air-conditioning, ventilation, power supply, drainage, sanitation, water supply, fire protection, security and communications systems,
(d) the external or internal cleaning of buildings, structures and works, so far as it is carried out in the course of their construction, alteration, repair, restoration, maintenance or extension,
(e) any operation which forms an integral part of, or is preparatory to or is for rendering complete, work of the kind referred to in paragraph (a), (b) or (c), including:
(i) site clearance, earth-moving, excavation, tunnelling and boring, and
(ii) the laying of foundations, and
(iii) the erection, maintenance or dismantling of scaffolding, and
(iv) the prefabrication of components to form part of any building, structure or works, whether carried out on-site or off-site, and
(v) site restoration, landscaping and the provision of roadways and other access works,
(f) the painting or decorating of the internal or external surfaces of any building, structure or works,
(g) any other work of a kind prescribed by the regulations for the purposes of this subsection.
(2) Despite subsection (1), construction work does not include any of the following work:
(a) the drilling for, or extraction of, oil or natural gas,
(b) the extraction (whether by underground or surface working) of minerals, including tunnelling or boring, or constructing underground works, for that purpose,
(c) any other work of a kind prescribed by the regulations for the purposes of this subsection.
6 Definition of "related goods and services"
(1) In this Act, related goods and services , in relation to construction work, means any of the following goods and services:
(a) goods of the following kind:
(i) materials and components to form part of any building, structure or work arising from construction work,
(ii) plant or materials (whether supplied by sale, hire or otherwise) for use in connection with the carrying out of construction work,
(b) services of the following kind:
(i) the provision of labour to carry out construction work,
(ii) architectural, design, surveying or quantity surveying services in relation to construction work,
(iii) building, engineering, interior or exterior decoration or landscape advisory services in relation to construction work,
(c) goods and services of a kind prescribed by the regulations for the purposes of this subsection.
(2) Despite subsection (1), related goods and services does not include any goods or services of a kind prescribed by the regulations for the purposes of this subsection.
(3) In this Act, a reference to related goods and services includes a reference to related goods or services.