The process for the issue of a FCC under the Contract is clear. It begins (under clause N11.1 of the Contract) with the contractor submitting a final claim to the architect when each of N11.1(a), (b) and (c) is satisfied; N11.1(b) provides that "the contractor has rectified all defects and finalised all incomplete works." Next, the architect must promptly assess the final claim, request any additional information required and then issue the final certificate to the contractor and the owner (clause N12.1). The FCC must (among other things) give written reasons for any differences between the amount certified and the amount claimed (clause N12.2).
None of those things occurred here. Instead, in an attempt to bring some finality to the escalating dispute between the parties, [the architect] purported unilaterally to assess amounts outstanding under the Contract and certify them for payment. The covering email from [the architect] described the revised FCC in the following terms: "So this Final Certificate (and it's [sic] supporting assessments)-is also the basis of a negotiation settlement which in our view is the fairest outcome".
In my view, the purported issue by [the architect] of a final certificate under clause N12 of the Contract in the absence of a final claim by [the contractor] under clause N11.1 (or, if relevant, in the absence of a written request by [the architect] to [the contractor] under clause 11.4 to submit such a claim), is a sufficient basis on which to find the revised FCC is invalid. The Contract clearly contemplates that the architect certifies "a claim", and thus it is the builder (not the architect) who sets the parameters of the issues that the architect must consider before issuing a certificate.
Further, that claim must be supported by a declaration made by the contractor that the contractor has performed its obligations under the Contract and all monies due to subcontractors at the date of the declaration have been paid (clause N11.2). In this case, the need for such a declaration would have required [the contractor] to confront during November 2014 at the latest, the impact of outstanding defects and incomplete work on its entitlement to be paid the retention sum.
... This is not a case of a minor or technical departure from the strict terms of the Contract. It involved a fundamental recasting of the roles and responsibilities of each of the owner, contractor and architect as provided for in the Contract.
We have received a Final Inspect (sic) report dated 18/10/13 from you and your final claim ...
As per clauses M11 & M12 of the Contract, we instructed and notified the builder on 5/7/2013 & 23/8/2013 to rectify these defects. Unfortunately, there are still a number of defects that have not been rectified by the builder. In accordance with the Contract, the builder has 7 days to attend to payment.
External paintwork - inadequate surface preparation, splashes
Windows - improper application of putty, sticking, weatherproofing
Timber floors and trim - front veranda unsupported, rear deck boards cut short and cracked
Ventilation boards - not repaired or replaced below bay window
Concrete driveway - 6m2 of surface removed by the Respondent and not reinstated
Conduit - encasing wiring on north side of the house, not fixed to external wall
Under sink recycling system (BLUM) - not installed in a pull-out drawer as per Contract Plans and Specifications, does not open and close properly
Internal paint finish - overpainting of windows, inadequate surface preparation, incomplete
Internal doors - missing fittings, bathroom sliding door not square
Failure to preserve space for water tank - rehang gate
Item 2: Windows - Improper Application of Putty, Sticking, Weatherproofing - $1,716
Item 5: Concrete Driveway on South Side of House- $550
Item 6: Conduit Not Fixed to External Wall - $82.50
Item 9: Kitchen Cupboards - Delaminated Melamine Lining - $99
Item 10: Internal Doors, Missing Fittings, Bedroom Sliding Door Not Square - (Costs Include Item 4) - $627
Items 11, 12, Water Tank: Rehanging of Gate - $550, and Toilets Not Connected for External Water Tank - $500
Item 13: Cracks in Plasterboard - Bedroom 3 North Wall - $670
External paintwork - inadequate surface preparation, splashes
Windows - improper application of putty, sticking, weatherproofing
Timber floors and trim - front veranda unsupported, rear deck boards cut short and cracked
Ventilation boards - not repaired or replaced below bay window (costs include item 10)
Concrete driveway - 6m2 of surface removed by the Respondent and not reinstated
Conduit - encasing wiring on north side of the house, not fixed to external wall
Under sink recycling system (BLUM) - not installed in a pull-out drawer as per Contract Plans and Specifications, does not open and close properly
Internal paint finish - overpainting of windows, inadequate surface preparation, incomplete
Internal doors - missing fittings, bathroom sliding door not square (costs included in item 4)
Failure to preserve space for water tank - rehang gate
[1] Progress Certificate No 5 dated 17 September 2012.
[2] BACV was a joint service conducted by Consumer Affairs Victoria and the Victorian Building Authority prior to 26 April 2017. It has now been replaced by Domestic Building Disputes Resolution Victoria.
[4] Interest calculations attached to the Applicant's written submissions dated 6 December 2019 state the amount owing by way of interest as at 29 February 2020 is $14,243.24.
[5] At the time of filing his Counterclaim the interest claimed totalled $7,462.68.
[6] This report is admissible in evidence in proceedings in this Tribunal pursuant to section 48T of the DBC Act.
[19] Clause A3.2 - warranties by the contractor.
[20] Robinson v Harman [1848] EngR 135; (1848) 1 Exch 850 at 855: Belgrove v Eldridge [1954] HCA 36; [1954] 90 CLR 613 at 617-618.
[22] Owner's written submissions - para 65 (a).
[25] A reference to Clause N14 of the Contract.
[26] Owner's written submissions - para 85.
[27] Owner's written submissions - para 67.
[28] Owner's written submissions - para 68.
[29] Owner's written submission - para 89.
[30] Consistent with this approach I note also that items which had been taken into account and considered by the Architect when issuing the Final Certificate, were not pursued by the Owner in this proceeding.
[32] As stipulated in Clause A8.2 of the Contract.