[2025] QCAT 305
General information, not legal advice.
Queensland Civil and Administrative Tribunal
2025-08-11
Original judgment source is linked above.
Katiza v Murphy Builders Qld Pty Ltd t/as Murphy Homes [2025] QCAT 305
(a) Murphy Builders Qld Pty Ltd t/as Murphy Homes is responsible for carrying out and completing the rectification works in accordance with the contractual documents between the parties including the Geotechnical Report from Mr Andrew Middleton of 19 December 2022;
(b) Murphy Builders Qld Pty Ltd t/as Murphy Homes is to commence rectification work for the Geotechnical issues on the northern and southern batters and the architraves and windows within four (4) weeks of the date of these Orders and will complete all of those rectification works within a further period of four (4) weeks.
(c) Murphy Builders Qld Pty Ltd t/as Murphy Homes is to obtain and retain the services of Mr Andrew Middleton prior to commencement of the rectification work and also in accordance with these terms;
(i) the services provided by Mr Andrew Middleton are to supervise and to provide certification of compliance by Murphy Builders Qld Pty Ltd t/as Murphy Homes in undertaking and completing the rectification works in accordance with the contract between the parties including all relevant geotechnical and engineering requirements.
(ii) the services to be provided by Mr Andrew Middleton are at Murphy Builders Qld Pty Ltd t/as Murphy Homes sole cost. Murphy Builders Qld Pty Ltd t/as Murphy Homes is solely responsible for all costs, fees and charges of Mr Andrew Middleton relating to his engagement and performance of duties in carrying out and discharging the obligation to provide supervision and certification of compliance with the rectification work.
(iii) Murphy Builders Qld Pty Ltd t/as Murphy Homes is to obtain an appropriate certificate of compliance (in a form to be decided by Mr Andrew Middleton) showing that the rectification work has been completed and that there is compliance with the contractual requirements and with relevant geotechnical and engineering requirements.
(iv) Murphy Builders Qld Pty Ltd t/as Murphy Homes is to obtain a certificate in respect of the completion of the rectification works to the architraves and window that require the rectification.
(v) any certificate issued by Mr Andrew Middleton shall be final and conclusive proof of compliance with the rectification works and has binding legal effect on Sarah Rebecca Katiza and Murphy Builders Qld Pty Ltd t/as Murphy Homes.
(vi) Murphy Builders Qld Pty Ltd t/as Murphy Homes is to give to Mr Andrew Middleton a copy of these Directions prior to the commencement of the rectification works.
(vii) Murphy Builders Qld Pty Ltd t/as Murphy Homes is to give written notice to Sarah Rebecca Katiza prior to the commencement of the rectification works that it has secured the retention of Mr Andrew Middleton for the purposes of these rectification works on the basis set out above.
(viii) in the event that the services of Mr Andrew Middleton are not able to be obtained or retained to provide the services referred to above, then both parties have liberty to apply to the Tribunal for the appointment of an appropriate person as an independent expert to carry out the services referred to above in lieu of Mr Andrew Middleton.
(d) all rectification work is to be undertaken between the hours of 9.00 am and 5.00 pm Monday to Friday (inclusive). (the Work Hours) No other rectification work outside of those hours should be undertaken.
(e) access to Sarah Rebecca Katiza's property for carrying out rectification work is on these terms;
(i) subject to the Work Hours terms, Sarah Rebecca Katiza is to allow Murphy Builders Qld Pty Ltd t/as Murphy Homes including its employees, workmen and contractors access to those parts of Sarah Rebecca Katiza's property required for rectification work and which access is to include access roads and areas for setting up for the rectification work, an area for stock piling any materials or parking of vehicles and or machinery necessary for the works and any other necessary ancillary area to undertake rectification work.
(ii) Murphy Builders Qld Pty Ltd t/as Murphy Homes, it's employees, workmen and contractors directly associated with the rectification works are only to access those areas of Sarah Rebecca Katiza's property required for the rectification works during the Work Hours terms for the period of the rectification works. There should be no unauthorised entry to those areas of the Applicants property which are not directly or indirectly required for the rectification work.
(iii) Murphy Builders Qld Pty Ltd t/as Murphy Homes must give prior written notification to Sarah Rebecca Katiza of the dates on which it will commence rectification works and will also give prior written notice when Murphy Builders Qld Pty Ltd t/as Murphy Homes, it's employees, workmen or contractors will be on site including identifying the individual persons involved by name.
(iv) Murphy Builders Qld Pty Ltd t/as Murphy Homes must give prior written notice to Sarah Rebecca Katiza details of the foreman on site or other responsible person for supervision of the rectification works and who is to be the contact person of Murphy Builders Qld Pty Ltd t/as Murphy Homes while the rectification works are taking place. That written notification is to include the name of the foreman or the responsible person including contact details such the email address of that person for the purposes of the rectification work.
(f) Murphy Builders Qld Pty Ltd t/as Murphy Homes is to comply with the insurance provisions, if any, in the contract between the parties during the period of the rectification works.
(g) On completion of the rectification work, Murphy Builders Qld Pty Ltd t/as Murphy Homes is to "Make Good" the site of the rectification works and any other areas of Sarah Rebecca Katiza's property used in the course of the rectification works.
BUILDING CONTRACTS - performance - breach of contract - building defects - rectification of defective building work - directions for the carrying out of rectification work by the builder.
Lyons v Dreamstarter Pty Ltd [2011] QCATA 142
(a) any additional orders the Tribunal should make to give effect to the completion of defective work; and
(b) Costs in the proceedings in the event that either party intended to make an application for costs.
Respondents Application for Extension of Time to File Costs Application.
(a) reliance was made on the Decision of 25 November 2024 which provided;[1]
The Tribunal will, in the circumstances, make directions to the effect that if either party seeks an order for costs then they must do so in accordance with the requirements of those directions and within the strict time limit provided. Otherwise, the general rule that each party bears their own costs are set out in s 100 of the QCAT Act will apply
(b) the parties are expected to comply with the Tribunal directions
(c) no reason has been given by the Respondents failure to comply with the extended date in the Tribunals directions;
(d) the Respondent is represented by lawyers who should be familiar with the Tribunal's practice and procedure;
(e) the Respondent has consistently delayed or extended this matter;
(f) the Respondent has already been afforded a lengthy extension until 28 February 2025;
(g) the Applicant has filed submissions in compliance with the Tribunal's directions;
(h) the Applicant has incurred significant costs to remediate other parts of the property to mitigate costs and damage;
(i) the Respondent would get an unfair advantage by having seen the Applicants submissions before filing its submissions out of time;
(j) the Applicant will be unfairly prejudiced and it will make a farce of the Tribunal's directions if an extension of time is granted;
An extension or waiver may be given under subsection (1) even if the time for complying with the relevant requirement has passed.
(a) the procedure for the proceedings is at the discretion of the Tribunal;
(b) the Tribunal must;
(i) act fairly and according to the substantial merits of the case;
(ii) observe the rules of natural justice;
(iii) must ensure, so far as is practicable, that all relevant material is disclosed to the Tribunal to enable it to decide the proceedings with all the relevant facts
(a) commencement and completion date;
(b) identification of the persons/contractors undertaking the rectification works;
(c) access arrangements and authority to carry out works on the site;
(d) any other orders necessary
(a) within three weeks of the commencement date for the rectification to the northern and southern batters; and
(b) three days from the commencement date for the "indoor" rectification works.
(c) Prior to commencement of rectification works, provision of a timeline showing where each aspect will be completed;
(d) provision of updates (no less than weekly) on progress of the rectification works;
(e) rectification works to be carried out only between the hours of 9.00 am and 5.00 pm from Monday to Friday;
(a) the slope reprofiling, including compaction standards;
(b) proposed measures of testing and sign off by the RPEQ engineer appointed; and
(c) and a final landscaping, reinstatement of finishing details were relevant
(a) pre-work photos of the exterior architraves and window areas subject to cracks (not the interior, unless relevant);
(b) if painting or minimal interior works are needed, the respondent is to arrange in advance scheduling of the works to ensure no privacy or property issues arise;
(c) durable materials are to be used (not cheap filler) and uniform painting of the affected surface.
(a) recent persistent rainfall in South East Queensland has caused the stability of the building site to be further compromised and damaged due to the Respondents defective works;
(b) an engineering report dated 15 April 2025 from Amanda Lane, Associate Geotechnical Engineer at SLR Consulting Australia, recording additional technical defects that have occurred is result of weather conditions during the wet season. The report went on to state;
These defects have not been recorded in the ongoing QCAT case and have been occurring in the period between the Hearing and the Directions being put into effect for rectification commencement. The original defects were recorded in the letter report of January 2023
(a) the appointment of Mr Middleton as the final arbitrator to determine whether or not that rectification work has been completed; and
(b) to require that work to be completed by the Respondent is generally in accordance with the Scott Schedule in the proceeding and for the Respondents adjusted construction program.
(a) the rectification work should be commenced and completed in accordance with its construction program which specifies a period of 18 days for the batter remediation;
(b) Mr Middleton be appointed as the "independent expert" to provide oversight of the rectification works and to ensure satisfactory completion of those works;
(c) access should be provided to the Respondent (and its subcontractors) to complete the rectification works in accordance with the adjusted construction program; and
(d) the Respondents "Scope of Works" is sufficient and no other orders are contemplated.
From our calculations, the submissions are almost 2 months overdue. Where do you say the provision of these submissions fit into the orders made on 26 November 2024 and amended on 22 January 2025.
No response was provided by the Respondent solicitors to the Applicants solicitors. The Applicants "formally object" to these documents being lodged by the Respondent outside the required time frame.
What are the Requirements of the Parties for the Rectification Works
Respondent is Responsible for the Rectification Works
Commencement and Completion of Rectification Work
Access to the Applicants Site to Carry Out Rectification Work
Orders for Carrying Out and Completing the Rectification Work
(a) the Respondent is responsible for carrying out and completing the rectification works in accordance with the contractual documents between the parties including the Geotechnical Report from Mr Andrew Middleton of 19 December 2022;
(b) the Respondent is to commence rectification work for the Geotechnical issues on the northern and southern batters and the architraves and windows within four (4) weeks of the date of these directions and will complete all of those rectification works within a further period of four (4) weeks.
(c) the Respondent is to obtain and retain the services of Mr Andrew Middleton on these terms;
(i) the services provided by Mr Andrew Middleton are to supervise and to provide certification of compliance by the Respondent in undertaking and completing the rectification works in accordance with the contract between the parties including all relevant geotechnical and engineering requirements.
(ii) the services to be provided by Mr Andrew Middleton are at the Respondents sole cost. The Respondent is solely responsible for all costs, fees and charges of Mr Andrew Middleton relating to his engagement and performance of duties in carrying out and discharging the obligation to provide supervision and certification of compliance with the rectification work.
(iii) the Respondent is to obtain an appropriate certificate of compliance (in a form to be decided by Mr Andrew Middleton) showing that the rectification work has been completed and that there is compliance with the contractual requirements and with relevant geotechnical and engineering requirements.
(iv) the Respondent is to obtain a certificate in respect of the completion of the rectification works to the architraves and window that require the rectification.
(v) any certificate issued by Mr Andrew Middleton shall be final and conclusive proof of compliance with the rectification works and has binding legal effect on the Applicant and the Respondent.
(vi) the Respondent is to give to Mr Andrew Middleton a copy of these Directions prior to the commencement of the rectification works.
(vii) The Respondent is to give written notice to the Applicant prior to the commencement of the rectification works, that it has secured the retention of Mr Andrew Middleton for the purposes of these rectification works and on the basis set out above.
(viii) in the event that the services of Mr Andrew Middleton are not able to be obtained or retained to provide the services referred to above, then both parties have liberty to apply to the Tribunal for the appointment of an appropriate person as an independent expert to carry out the services referred to above in lieu of Mr Andrew Middleton.
(d) all rectification work is to be undertaken between the hours of 9.00 am and 5.00 pm Monday to Friday (inclusive). (the Work Hours) No other rectification work outside of those hours should be undertaken.
(e) access to the Applicants property for carrying out rectification work is on these terms;
(i) subject to the Work Hours terms, the Applicant is to allow the Respondent including its employees, workmen and contractors access to those parts of the Applicants property required for rectification work and which access is to include access roads and areas for setting up for the rectification work, an area for stock piling any materials or parking of vehicles and or machinery necessary for the works and any other necessary ancillary area to undertake rectification work.
(ii) the Respondent, it's employees, workmen and contractors directly associated with the rectification works are only to access those areas of the Applicants property which the Applicants allows during the Work Hours terms for the period of the rectification works. There should be no unauthorised entry to those areas of the Applicants property which are not directly or indirectly required for the rectification work.
(iii) the Respondents must give prior written notification to the Applicants of the dates on which it will commence rectification works and will also give prior written notice when the Respondent, it's employees, workmen or contractors will be on site including identifying the individual persons involved by name.
(f) the Respondent must give prior written notice to the Applicants of the foreman on site or other responsible person for supervision of the rectification works and who is to be the contact person of the Respondent while the rectification works are taking place. That written notification is to include the name of the foreman or the responsible person including contact details such the email address of that person for the purposes of the rectification work.
(g) the Respondent is to comply with the insurance provisions, if any, in the contract between the parties during the period of the rectification works.
(h) on completion of the rectification work, the Respondent is to "Make Good" the site of the rectification works and any other areas on the Applicant's property used in the course of the rectification works.
(a) there was significant complexity in these proceedings given the nature and number of items in the Scott Schedule;
(b) because of this complexity the Respondent benefited the proceedings by having solicitor and counsel as it's representative;
(c) overall, there were weak claims in the proceedings by the Applicant as opposed strong claims by the Respondent;
(d) the Respondent made concessions in respect of the amount of approximately $8,390.00 in item 8 of the Scott Schedule;
(e) the Respondent made an offer to settle items 15 and 25 in a written offer dated 17 February 2023. That offer was not accepted
A jurisdiction given in general terms allows the Tribunal to make an order as to costs that is justified in the circumstances. It is a broad general discretion which must be exercised judicially, not upon irrelevant or extraneous considerations but upon facts connected with or leading up to the litigation.
Accordingly, an enabling Act, the QBSA Act, does, provide otherwise. As a result, the usual position as to costs in the Tribunal is displaced. That result is reinforced by other provisions dealing with the relationship between the QCAT Act and enabling Acts.
(a) The Tribunal does not consider either party to the proceedings acted in a way that unnecessarily disadvantaged another party to the proceedings;
(b) These proceedings involved complex geotechnical engineering issues as well as diverse multiple factual situations in the Scott Schedule which were the subject of competing evidence from experts called in the proceedings;
(c) While the Applicant was unsuccessful in a number of the defects claimed in the Scott Schedule nevertheless there was expert building evidence called to support the Applicants case in these proceedings. That evidence had to be assessed in conjunction with expert building evidence from the Respondent. Both parties brought to the Tribunal bona fide and genuine disputes in relation to matters in the Scott Schedule requiring a decision of the Tribunal;
(d) Neither party provided evidence of their financial circumstances and the Tribunal is unable to make any finding or determination in respect of this matter;
(e) The Respondents case for an award of costs is substantially based upon what it says is its "overwhelming success" in these proceedings. But that success has to be considered against the background of seriously contested opinions and facts in the proceedings were both parties had bona fide and genuine dispute relating to defects in the Scott Schedule;
(f) Usually, where an offer to settle is made and not accepted, the Tribunal would attach significant weight, at least, to such an offer particularly if it was made, as is the case here, at an early stage of the proceedings. However, the written offer made by the Respondent and not accepted by the Applicant gave a timeline of two (2) days during which it was open for acceptance, which included a Saturday and Sunday, on complex issues in these proceedings. The Tribunal in these circumstances does not attach to that written offer the significant weight which would normally be afforded. Had the offer remained open for a reasonable length of time the Tribunal would have attached significant weight to such an offer.
[1] (2024) QCAT 609 at paragraph 247
[4] Applicants submissions filed 12 March 2025 at paragraph 2.6
[7] Tribunal's Directions made 22 January 2020
[8] Applicants submissions filed on 28 February 2025 at paragraph 1.1
[9] Applicants submissions filed on 28 February 2025 at paragraph 3.1
[12] See Affidavit of Brendan Joseph Bathersby dated 4 March 2025 at Exhibits BJB 2 and BJB 4
Katiza
Murphy Builders Qld Pty Ltd t/as Murphy Homes [2025] QCAT 305