CDI Lawyers for the first respondent as town agents for Jackson McDonald
"... we hold instructions to respond, on behalf of our client, to your client's [payment claim] by giving you, on behalf of our client, our client's 'payment schedule' for the purposes of section 76 of the BIFA within the requisite 15 business day time period.
To avoid doubt, on this occasion anything issued to your client by the Superintendent in respect of [the payment claim] is not to be construed as a 'payment schedule' for the purposes of the BIFA as our client will be providing its own response as foreshadowed above."
A payment schedule, responding to a payment claim, is a written document that -
(a) identifies the payment claim to which it responds; and
(b) states the amount of the payment, if any, that the respondent proposes to make; and
(c) if the amount proposed to be paid is less than the amount stated in the payment claim - states why the amount proposed to be paid is less, including the respondent's reasons for withholding any payment; and
(d) includes the other information prescribed by regulation."
"This Payment Schedule has been produced pursuant to the Works Contract for the residential flat being constructed at 98 River Terrace, Kangaroo Point, between the Principal 'Kangaroo Point Developments MP Property Pty Ltd' and the Contractor 'RHG Contractors Pty Ltd'. This Payment Schedule confirms that the Superintendent has assessed, calculated and certified the proper value of Work Under the Contract."
The Superintendent shall, within 10 business days after receiving such a payment claim, issue to the Principal and the Contractor:
(a) a payment schedule evidencing the Superintendent's opinion of the moneys due from the Principal to the Contractor pursuant to the payment claim and reasons for any difference ('payment schedule'); and
(b) a certificate evidencing the Superintendent's assessment of retention moneys and moneys due from the Contractor to the Principal pursuant to the Contract.
If the Contractor does not make a payment claim in accordance with clause 37.1, the Superintendent may issue the payment schedule with details of the calculations and shall issue the certificate in paragraph (b).
If the Superintendent does not issue the payment schedule within 10 business days of receiving a payment claim in accordance with subclause 37.1, that payment claim shall be deemed to be the relevant payment schedule.
The Principal shall within 5 business days after receiving both such certificates, or within 15 business days after the Superintendent receives the payment claim (whichever occurs first), pay to the Contractor the balance of the payment schedule after setting off such of the certificate in paragraph (b) as the Principal elects to set off. If that setting off produces a negative balance, the Contractor shall pay that balance to the Principal within 5 business days of receiving written notice thereof.
Neither a payment schedule nor a payment of moneys shall be evidence that the subject WUC has been carried out satisfactorily. Payment other than final payment shall be payment on account only.
In so far as necessary to ensure compliance with the Security of Payment Act, the Superintendent is deemed to issue any payment schedule under clause 37.2 or final payment schedule under clause 37.4 as the agent of the Principal and each such schedule shall constitute a payment schedule for the purposes of the Security of Payment Act.
For the purposes of and where permitted by the Security of Payment Act, each of the dates for delivery of a payment claim in subclause 37.1 constitutes a reference date." (italics in the original)
[1] [2020] QSC 51, [22] ff; see [2021] QCA 10, [25] ff on appeal.
[2] Style Timber Floor Pty Ltd v Krivosudsky [2019] NSWCA 171, [45].
[3] [2019] QSC 226, [44].
[4] [2013] QCA 386, [59] cited in Melaleuca View Pty Ltd (above).
[5] DL v The Queen [2018] HCA 26; (2018) 266 CLR 1, [130] ff.
[6] Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355, [91]; cf Kioa v West [1985] HCA 81; (1985) 159 CLR 550, 585 and see Wainohu v NSW (2011) 243 CLR 181, [56] as to the varying requirement for content and detail of judicial reasons depending upon the nature of the jurisdiction the Court is exercising, and the type of matter with which it is dealing.
Kangaroo Point Developments MP Property Pty Ltd
RHG Construction Fitout and Maintenance Pty Ltd & Ors [2021] QSC 30
(2018) 266 CLR 1
(1998) 194 CLR 355
(1985) 159 CLR 550
(2011) 243 CLR 181