[2022] QCAT 125
General information, not legal advice.
Queensland Civil and Administrative Tribunal
2022-04-11
Original judgment source is linked above.
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)
(a) Mr McPhail built Ms Judd's home in 2017/2018;
(b) During the course of the construction of the home, Mr McPhail was requested by Ms Judd to provide a quote for the construction of a retaining wall at the property;
(c) Mr McPhail was subsequently instructed by Ms Judd to undertake the construction of the retaining wall;
(d) When Ms Judd moved in to the home the retaining wall was approximately 75% complete;
(e) Approximately 11 months after Ms Judd moved in to the home Ms Judd made enquiries with Mr McPhail as to when the retaining wall would be completed;
(f) After some period of time it became apparent that Mr McPhail was not intending to complete the wall and had in fact relocated to Townsville;
(g) Mr McPhail offered to pay to Ms Judd '$6,000 to $6,500' (presumably in respect of the cost of the completion of the retaining wall) however Ms Judd is of the view that the cost of completion of the wall will be in the order of $9,559.00.
(a) Ms Judd is a building owner;
(b) Mr McPhail is a building contractor;
(c) The work undertaken by Mr McPhail was domestic building work;
(d) Prior to commencing these proceedings Ms Judd complied with the requirements of s 77(2) of the Queensland Building and Construction Commission Act 1991 (Qld);
(e) The dispute between the parties is a domestic building dispute;
(f) The Tribunal has jurisdiction to decide the dispute;
(g) Service of the application for domestic building dispute has been effected upon Mr McPhail;
(h) Mr McPhail has, without reasonable excuse, failed to comply with tribunal directions, including being directed to file a response, and is thereby causing unnecessary disadvantage to Ms Judd who is entitled to progress her claim to completion;
(i) Ms Judd is entitled to a final decision in the proceedings.
In particular, the ordinary relationship between a builder of a house and the first owner with respect to that kind of economic loss is characterized by the kind of assumption of responsibility on the one part (i.e. the builder) and known reliance on the other (i.e. the building owner) which commonly exists in the special categories of case in which a relationship of proximity and a consequent duty of care exists in respect of pure economic loss.[4]
(a) that Mr McPhail owed Ms Judd a duty to avoid a foreseeable and not insignificant risk of harm;
(b) that Mr McPhail breached the duty; and
(c) that Ms Judd suffered loss and damage as a consequence of the breach.
(a) In July 2020 she became aware that the local authority had not been informed about the construction of the retaining wall;
(b) Mr McPhail had previously advised Ms Judd that the local authority had been informed about the works and that the appropriate paperwork had been lodged;
(c) The local authority required payment by Ms Judd of an amount of $766.00 in respect of approval of the works and also required her to engage a structural engineer to prepare a design and plans for the retaining wall (the design works);
(d) Ms Judd paid a total of $4,400.00 to the engineer in respect of the design works;
(e) In November 2020, Ms Judd was notified that part of the retaining wall constructed by Mr McPhail was encroaching on an Ergon energy easement requiring the removal and reconstruction of the retaining wall;
(f) Mr McPhail was aware of the existence of the easement and had discussed with Ms Judd the construction of the retaining wall so as to avoid encroaching on the easement. Boundary pegs were placed by Mr McPhail and he used laser levels to ensure that the boundary of Ms Judd's property and the easement was accurately identified;
(g) One quarter of the wall remains incomplete;
(h) The wall as constructed is required to be moved to ensure that it does not encroach upon the Ergon easement.
(a) Boundary re-survey cost: $1,485.00. This amount was paid by Ms Judd to a surveyor in April 2021. I accept that this expense was incurred as a result of the identified encroachment issue and the necessity to ensure that a survey was conducted to identify the boundary of Ms Judd's property and the Ergon easement;
(b) Structural engineer costs: $4,400.00. This is referred to above;
(c) Anticipated costs of structural engineer in undertaking inspection of the retaining wall while it is being constructed: $242.00;
(d) Local authority fees: $766.00. This is referred to above;
(e) Anticipated costs associated with the reconstruction and completion of the wall: $19,690.00;
(f) Anticipated cost of additional blocks to complete construction of the retaining wall: $9,559.00;
(g) Search fee paid to local authority: $50.00.
(a) Mr McPhail failed to obtain necessary local authority approvals before undertaking construction of the retaining wall;
(b) Mr McPhail failed to have the wall designed and certified by an engineer before commencing construction of the wall;
(c) Mr McPhail failed to construct the wall in accordance with properly designed and certified plans prepared by an engineer;
(d) Mr McPhail failed to construct the wall so as to ensure that it did not encroach on the Ergon easement.
(a) Boundary re-survey cost: $1,485.00. This relates to the failure by Mr McPhail to avoid constructing the wall on the Ergon easement. I accept the evidence of Ms Judd that Mr McPhail had placed boundary pegs in place before commencing construction of the wall. I accept that whatever steps were undertaken by Mr McPhail in this regard, he either failed to properly identify the property boundary or failed to construct the wall within the boundary of Ms Judd's property or possibly both. In any event, the amount claimed is the consequence of Mr McPhail's breach of duty and is allowed in full;
(b) Structural engineer costs: $4,400.00. This relates to the failure by Mr McPhail to obtain council approvals and to have the wall designed and certified by an engineer. Had there been an enforceable contract between the parties, the amount claimed would likely have been recoverable on the basis that it was an implied term of the contract that all necessary council and other approvals would be obtained which would have required engineered drawings, etc. However, and for the reasons I have set out, Ms Judd is not entitled to pursue a claim in contract. I referred earlier in these reasons to the necessary elements of a claim in negligence. I accept that Mr McPhail breached the duty he owed to Ms Judd to ensure that the wall was constructed in accordance with appropriately engineered designs and plans. However Ms Judd must also prove that as a result of the breach of duty, she has suffered loss. Whilst I accept that the amount claimed is a considerable expense, it is nevertheless a cost Ms Judd would have incurred in any event even if Mr McPhail had not breached the duty he owed to Ms Judd. There is no evidence, for example, that the amount paid to the engineer was more than the amount that would otherwise have been paid had the necessary engineering works been undertaken before the construction of the wall was undertaken. As such, the claim is not analogous to a claim for the rectification of defective work where work has actually been undertaken and must be remedied. The amount claimed is disallowed;
(c) Anticipated costs of structural engineer in undertaking inspection of the retaining wall while it is being constructed in order for a final certificate to be issued upon completion: $242.00. For the reasons outlined above relating to the claim for the engineer's fees, this claim is disallowed;
(d) Local authority fees: $766.00. This is the fee charged by the local authority for the necessary approval for the construction of the wall. Again, for the reasons outlined above, the claim is disallowed;
(e) Search fee paid to local authority: $50.00. This amount was paid by Ms Judd to undertake a search of council records to ascertain whether necessary building approvals had been obtained by Mr McPhail. I allow the amount claimed in full.
(a) Mr McPhail has been paid an amount of money by Ms Judd (the enrichment);
(b) The amount relates to work Mr McPhail did not perform, namely, the unfinished 25% portion of the wall (the benefit obtained at the expense of Ms Judd);
(c) It would be unjust for Mr McPhail to retain the benefit of monies he received from Ms Judd for work he failed to perform (the unjust enrichment).
(a) Boundary re-survey cost $ 1,485.00
(b) Council search fee $ 50.00
(c) Costs of reconstruction of relocated wall $19,690.00
(d) Restitution $11,948.80
[1] Queensland Building and Construction Commission Act 1991 (Qld) (QBCC Act) sch 1B, s 3(1).
[4] Bryan v Maloney (1995) 182 CLR 609, 624.
[5] Brookfield Multiplex Ltd v Owners Corp Strata Plan 61288 [2014] HCA 36.
[6] Olindaridge Pty Ltd v Tracey [2016] QCATA 23.
[7] Kaze Constructions Pty Ltd v Housing Indemnity Australia Pty Ltd (1990) 10 BCL 63.
[8] Campbelltown City Council v Mackay (1989) 15 NSWLR 501.
Judd
McPhail [2022] QCAT 125
Brookfield Multiplex Ltd v Owners Corp Strata Plan 61288 [2014] HCA 36
Olindaridge Pty Ltd v Tracey [2016] QCATA 23
(1995) 182 CLR 609
(1989) 15 NSWLR 501