[2022] VSCA 209
General information, not legal advice.
Court of Appeal (Vic)
2022-09-30
Niall JA, Sifris JA, Walker JA
Original judgment source is linked above.
DANIEL INVESTMENTS (AUST) PTY LTD (ACN 090 946 446)
[2021] VSC 705 (Daly AsJ)
BUILDING AND CONSTRUCTION - Variation to domestic building contract - Where statutory notice provisions for variation not complied with - Whether builder can recover cost of variation - Whether completion date adjusted to take into account variation - 'Significant or exceptional hardship' included consequences of builder's inability to recover money - Meaning of 'varied in accordance with' - Completion date adjusted where VCAT satisfied of significant or exceptional hardship - Operation of statutory provision for adjustment of completion date unaffected by builder's non-compliance with contractual notice procedure - Leave to appeal granted - Appeal dismissed.
Mann v Paterson Constructions Pty Ltd [2019] HCA 32; (2019) 267 CLR 560, discussed.
(a) all the terms of the contract;
(b) a detailed description of the work to be carried out under the contract;
(c) the plans and specifications for the work, which must contain enough information to enable the obtaining of a building permit;
(d) the date when the work is to start, or how that date is to be determined;
(e) the date when the work will be finished, or, if the starting date is not yet known, the number of days that will be required to finish the work once it is started; and
(f) the contract price or, in the case of a cost plus contract, how the amount that the builder is to be paid is to be determined.
38 Variation of plans or specifications - by building owner
(1) A building owner who wishes to vary the plans or specifications set out in a major domestic building contract must give the builder a notice outlining the variation the building owner wishes to make.
(2) If the builder reasonably believes the variation will not require a variation to any permit and will not cause any delay and will not add more than 2% to the original contract price stated in the contract, the builder may carry out the variation.
(3) In any other case, the builder must give the building owner either -
(i) states what effect the variation will have on the work as a whole being carried out under the contract and whether a variation to any permit will be required; and
(ii) if the variation will result in any delays, states the builder's reasonable estimate as to how long those delays will be; and
(iii) states the cost of the variation and the effect it will have on the contract price; or
(b) a notice that states that the builder refuses, or is unable, to carry out the variation and that states the reason for the refusal or inability.
(4) The builder must comply with subsection (3) within a reasonable time of receiving a notice under subsection (1).
(5) A builder must not give effect to any variation asked for by a building owner unless -
(a) the building owner gives the builder a signed request for the variation attached to a copy of the notice required by subsection (3)(a); or
(6) A builder is not entitled to recover any money in respect of a variation asked for by a building owner unless -
(i) that there are exceptional circumstances or that the builder would suffer a significant or exceptional hardship by the operation of paragraph (a); and
(ii) that it would not be unfair to the building owner for the builder to recover the money.
(7) If subsection (6) applies, the builder is entitled to recover the cost of carrying out the variation plus a reasonable profit.
(8) This section does not apply to contractual terms dealing with prime cost items or provisional sums.
Unless the contrary intention appears, if the plans or specifications set out in a major domestic building contract are varied in accordance with section 37 or 38, any reference in this Act, the regulations or the contract to -
(a) those plans or specifications is to be read as a reference to them as varied; and
(b) the contract price is to be read as a reference to the contract price as adjusted to take account of the variation; and
(c) the completion date, or the number of days required to finish the work, is to be read as a reference to that date, or number of days, as adjusted to take account of the variation.
23.0 Either the Owner or the Builder may ask for the Building Works to be varied. The request must be in writing, must be signed and must set out the reason for and details of the variations sought.
23.1 If the Owner requests the variation and the Builder reasonably believes the variation will not require a variation to any permit and will not cause any delay and will not add more than 2% to the Contract Price the Builder may carry out the variation.
23.2 If the Builder requests the variation, the notice given by the Builder must state the following further particulars:
23.3 If the Owner requests a variation and if the Builder has not agreed to carry out the variation under Clause 23.1, the Builder must give the Owner, within a reasonable time of receiving the notice under Clause 23.0, a notice:
23.4 Subject to Sub-Clause 23.1, the Builder must not give effect to any variation unless the Owner gives the Builder a signed consent to or request for the variation attached to a copy of the notice referred to in Clauses 23.2 or 23.3.
23.5 If, within 7 Days of the Builder giving the Owner the notice of particulars under Clause 23.3, the Owner does not give the Builder:
the request by the Owner for the variation is deemed withdrawn.
34.0 The date for Commencement is put back or the Building Period is extended if the carrying out of the Building Works is delayed due to:
34.1 The Builder is to give the Owner a written notice informing the Owner of the extension of time. The written notice must state that cause and the extent of the delay.
34.2 To dispute the extension of time the Owner must give the Builder a written notice, including detailed reasons why the Owner disputes the claim, within 7 Days of receiving the Builder's notice.
34.3 If there is an extension of time due to anything done or not done by the Owner or by an agent, contractor or employee of the Owner, the Builder is, in addition to any other rights or remedies, entitled to delay damages worked out by reference to the period of time that Building Period is extended and the greater of $250 per week or that amount set out in Item 12 of Schedule 1. Delay damages will accrue on a daily basis.
34.4 The Owner must pay any delay damages with the next Progress Payment.
(a) Could the builder recover payment for the variations it had claimed, in circumstances where the variations had not been requested in writing and the builder had not given the information required by s 38 of the DBCA?
(b) Could the builder rely on the time spent in undertaking the variations to extend the time for completion under the contract, and if so, what was the duration of the extension?
(c) Was the owner entitled to liquidated damages because the works had not been completed within time?
[Counsel for the builder] submitted that the Builder is entitled to an extension of time in any of the circumstances listed in Clause 34.0, even where the procedure set out in the succeeding parts of Clause 34 are not followed.
I think that is correct. Clause 34.0 is not prefaced by the words: "Subject to compliance with this clause ..." or some similar phrase. The entitlement to an extension is prima facie absolute. Quite obviously, if the procedure is not followed, then the machinery set out in the clause cannot be used to establish an entitlement to an extension of time. However, [Counsel] says that the entitlement encompasses a variation under either of the sections.[14]
The role of hardship under s 38(6)(b)
Extension of time for completion under s 39 of the DBCA
Section 39 provides that, unless the contrary intention appears (presumably in the contract itself), if the plans or specifications in a major domestic building contract are varied in accordance with ss 37 or 38, the completion date in the contract is to be adjusted to take into account the variation. Accordingly, the critical question is, whether a variation for which payment is allowed under s 38(6)(b) is a variation "in accordance with" s 38 of the DBCA for the purpose of s 39(c).
...
In my view, there is some ambiguity in the use of the phrase "in accordance with" in s 38 and s 39. On one view, s 39 cannot provide relief to a builder which has failed to comply with the notification requirements, given that the language of that phrase is arguably synonymous with "in compliance with". Any variation claim by a builder under s 38(6)(b) is, axiomatically, a variation which has not been made "in accordance with" the notification requirements, which is the primary obligation imposed by s 38. Arguably, s 38(6)(b) does not authorise, or validate, a variation claim where the builder has not complied with the notification requirements. Rather, it is an ameliorative provision designed to relieve the potentially harsh consequences of the strict enforcement of the notification requirements.
However, notwithstanding the ambiguity in the use of the term "in accordance with", I am persuaded that the construction of s 39 advanced by the builder is to be preferred. First, s 39 refers to variations made in accordance with s 38, and is not confined in its terms to variations made in compliance with the requirements in ss 38(1) to (5) inclusive, that is, the notification requirements. Further, the builder's preferred construction promotes a more harmonious operation of the provisions of the DBCA concerning variation claims than the owner's preferred construction, and, as noted in Project Blue Sky, a statute "must be construed on the prima facie basis that its provisions are intended to give effect to harmonious goals". A construction that provides that variations for which a builder is entitled to recover payment are said to be variations made "in accordance with" s 38 promotes the harmonious operation of those provisions: that is, undocumented variations are to be discouraged, but if a builder can overcome the relatively high bar imposed by s 38(6)(b), the relevant contract is varied so as to ensure that the builder is not automatically in breach of the warranties in s 8 of the DBCA, and the term of the contract prescribing the contract price and the completion date of the works.
Accordingly, in my view, the phrase "in accordance with" in s 39 encompasses not only variations where the builder has complied with the notification requirements, but also variations where VCAT is satisfied that builders should be relieved of the harsh consequences of the builder's failure to comply with the notification requirements. Further, as noted by the builder in its submissions, this construction of s 39 does not provide a builder with a windfall, as the builder still needs to satisfy the strict test under s 38(6)(b).[18]
First, the absence of any qualifying words in cl 34.0 supports the builder's contention that the entitlement is absolute, provided that the delay to the works is occasioned by one or more of the circumstances enumerated in the bullet points in cl 34.0.
My view that the builder's entitlement to an extension of time is not conditioned upon the compliance by the builder with the notice requirements is borne out by a careful reading of cl 34 itself.
...
That the builder's entitlement to an extension of time is not conditioned on the notice requirements is also illustrated by a comparison of the notice requirements and the notification requirements. Section 38(6) precludes a builder from recovering payment for a variation unless the builder complies with the notification requirements, or is able to satisfy VCAT of the matters set out in s 38(6)(b). In contrast, while cl 34.1 provides that a builder must comply with the notice requirements, no consequence for the builder's failure to comply with the notice requirements is provided for in cl 34.
Accordingly, while cl 34.0 governs the entitlement to an extension of time, cll 34.1 and 34.2 amount to no more than a dispute resolution procedure, and an incomplete one at that, given that it fails to provide a mechanism for resolving any dispute between the owner and the builder concerning an extension of time claim to which an owner objects. The balance of cl 34 concerns the entitlement of the builder to delay damages and the time for payment of delay damages, which are not relevant to the current appeal.[19]
The question remains though, given that the reasons disclose that [VCAT] may have acted on an erroneous understanding of the relationship between cl 34.0 and s 38(6)(b), what consequences should flow from that? None, in my view. While it would be open to me to reach a conclusion that [VCAT's] findings regarding the source of the builder's entitlement to an extension of time were tainted by an error of law, or at least were expressed in such terms as to not make clear the path of his reasoning in that regard, in my view, I would dismiss any appeal on those grounds.[21]
[T]here is no need for any remitter, because I am satisfied that, even if [VCAT] was in error in determining that the requirements in cl 34.0 were satisfied by reason of him allowing payment for a variation claim under s 38(6)(b), I agree that s 39 of the DBCA operates to extend the completion date where a variation for which payment has been awarded under s 38(6)(b).[22]
(1) The Judge erred in finding that the builder's entitlement to an extension of time (and consequential change to the building period) was not conditional upon compliance with the notice requirements of cl 34.1 of the contract.
(2) The Judge erred in finding that cl 34.0 governs the builder's entitlement to an extension of time absolute, whilst cls 34.1 and 34.2 amount to no more than a dispute resolution procedure and an incomplete one at that.
(3) The Judge erred in finding that s 39 of the DBCA operates to extend the builder's completion date under the contract where there is a variation for which payment has been awarded under s 38(6)(b).
(4) The Judge erred in finding that the phrase 'in accordance with' in s 39 of the DBCA encompasses not only variations where the builder has complied with the notification requirement, but also variations where VCAT is satisfied that the builder should be relieved of the harsh consequences of the builder's failure to comply with the notification requirements.
(5) The Judge erred in construing s 38(6)(b) of the DBCA and should have found that the correct test for assessing hardship to the builder pursuant to s 38(6)(b)(i) requires consideration of the effect of the builder being required to comply with the prescriptive requirements of sub-ss 38(1)-(5) of the DBCA before it is able to recover the cost of variations plus a reasonable profit.
A construction that would promote the purpose or object underlying the Act or subordinate instrument (whether or not that purpose or object is expressly stated in the Act or subordinate instrument) shall be preferred to a construction that would not promote that purpose or object.
Issue 1 - Construction of s 38(6)(b) of the DBCA
(a) The 'significant or exceptional hardship' suffered by the builder is that occasioned by the 'operation' of s 38(6)(a) of the DBCA. Section 38(6)(a) operates to preclude the builder from 'recover[ing] any money' unless the builder has given the relevant notice. The hardship is therefore directed to the builder's inability to recover any money.
(b) The text of s 38(6)(b)(i) does not expressly link the hardship to either the notice requirement (which is imposed by s 38(3)) or to compliance with s 38 more generally.
(c) Accordingly, the language does not confine the hardship to that associated with complying with the notice. Rather, it is only confined by the requirement that such hardship be 'significant or exceptional'.
The apparent purpose and legislative effect of these provisions is that a builder shall not be permitted to recover any money in respect of owner-initiated variations (other than for prime cost items and by way of provisional sums) except in accordance with these provisions. As such, they function as protective provisions, designed to prevent the kinds of problems likely to arise where domestic building contract variations are dealt with informally, as by oral request by an owner for a variation and compliance by the builder without first agreeing with the owner on the price and other consequences of giving effect to the variation; in particular, to avoid the surprises and consequent disputation likely to arise where plans and specifications under a major domestic building contract are varied without the degree of formality mandated by s 38(1) and (2) or (3). Hence, subject to only one exception, they prohibit a builder recovering any money in respect of owner-initiated variations unless the required degree of formality has been observed. The one exception [to s 38(6)(a)] reflects a legislative recognition that there can sometimes be instances of non-compliance which are in themselves exceptional or would result in the builder suffering exceptional hardship and in which it is not unfair to require the owner to pay a reasonable recompense for the variation, namely, the cost of the variation and a reasonable profit margin in accordance with s 38(7).[27]
Issue 2 - Consequential extension of time under s 39(c) of the DBCA
Unless the contrary intention appears, if the plans or specifications set out in a major domestic building contract are varied in accordance with section 37 or 38, any reference in this Act, the regulations or the contract to -
(a) those plans or specifications is to be read as a reference to them as varied; and
(b) the contract price is to be read as a reference to the contract price as adjusted to take account of the variation; and
(c) the completion date, or the number of days required to finish the work, is to be read as a reference to that date, or number of days, as adjusted to take account of the variation.
(a) the owner must give a notice requesting the variation;
(b) the builder must respond with a notice either:
(i) setting out the effect the variation would have on the work as a whole, the extent of any delay that would ensue and the cost; or
(ii) stating that the builder refuses or is unable to carry out the variation and giving a reason; and
(c) the owner must then give the builder a signed copy of the request attached to the builder's notice.
Issue 3 - Does cl 34 of the contract preclude any extension of time?
SIFRIS JA: My specific question is this: 39(c) says that the completion date is to be read as a reference to that date as adjusted to take account of the variation.
MR MARGETTS: That's right.
...
MR MARGETTS: No, but there's no contractual claim. If there is no contractual claim, how do you then have any adjustment?
SIFRIS JA: Well, the adjustment is by force of 39, including (c), which refers to the taking into account of the variation.
...
MR MARGETTS: But there's no contractual claims - what's the source of the extension of time? Where does it come from?
...
MR MARGETTS: It can only come from the contract or alternatively only come from the exercise of discretion by the tribunal. The tribunal doesn't have that power so you don't get - how do you get an adjustment of 39(c) if you don't satisfy 34? You can't. So when I said to the court earlier today that the court need not answer the issue about 34, in circumstances that it may go straight to 39, I was wrong, as debates moved today. I worked on the basis of course that my arguments would be accepted on 39. But if one tries now to look at the alternative argument ‑ ‑ ‑
SIFRIS JA: You've got to bring it back to contract, is your argument, yes.
MR MARGETTS: Yes, you always have to come back to the contract.
SIFRIS JA: So you would need compliance with 34, even if you rely on 39.[32]
[1] Raised by proposed ground of appeal 5 (hereafter proposed grounds of appeal are referred to as grounds of appeal, for convenience).
[2] Raised by grounds 3 and 4 of the appeal.
[3] Raised by grounds 1 and 2 of the appeal.
[4] Daniel Investments (AUST) Pty Ltd v Jolin Nominees Pty Ltd (Building and Property) [2020] VCAT 480, [419] ('VCAT reasons').
[17] Reasons, [128(b)-(c)], [134]-[135], [137], [142], [145].
[18] Ibid [197], [202]-[204] (emphasis in original) (citations omitted).
[19] Ibid [177]-[178], [181]-[182].
[23] Thiess v Collector of Customs [2014] HCA 12; (2014) 250 CLR 664, 671 [22] (the Court); [2014] HCA 12.
[24] SAS Trustee Corporation v Miles [2018] HCA 55; (2018) 265 CLR 137, 149 [20] (Kiefel CJ, Bell and Nettle JJ), 157 [41] (Gageler J), 162-3 [64] (Edelman J); [2018] HCA 55. See also Alcan (NT) Alumina Pty Ltd v Commissioner of Territory Revenue [2009] HCA 41; (2009) 239 CLR 27, 46-7 [47] (Hayne, Heydon, Crennan and Kiefel JJ) and the several cases there cited at n 105; [2009] HCA 41.
[25] Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355, 381 [69] (McHugh, Gummow, Kirby and Hayne JJ); [1998] HCA 28 ('Project Blue Sky').
[26] R v Young (1999) 46 NSWLR 681, 687-8 [15] (Spigelman CJ); [1999] NSWCCA 166. See also Project Blue Sky (1998) 194 CLR 355, 384 [78] (McHugh, Gummow, Kirby and Hayne JJ). See generally the discussion in Dennis Pearce and Robert Geddes, Statutory Interpretation in Australia (LexisNexis Butterworths, 8th ed, 2014) 79-83 [2.38]-[2.40].
[27] [2019] HCA 32; (2019) 267 CLR 560, 621-2 [157]; [2019] HCA 32 (citations omitted).
[28] Carr v Western Australia [2007] HCA 47; (2007) 232 CLR 138, 143 [5] (Gleeson CJ); [2007] HCA 47; Construction Forestry Mining & Energy Union v Mammoet Australia Pty Ltd [2013] HCA 36; (2013) 248 CLR 619, 632-3 [40]-[41] (Crennan, Kiefel, Bell, Gageler and Keane JJ); [2013] HCA 36.
[30] We refer, of course, to the legislative intention in the sense discussed in Zheng v Cai [2009] HCA 52; (2009) 239 CLR 446, 455-6 [28] (the Court); [2009] HCA 52.
[37] 'It has long been established that contractual or statutory provisions prescribing in positive terms a procedure to be followed necessarily imply that the same matter will not be dealt with under a different procedure': ABB Power Plants Ltd v Electricity Commission (NSW) t/as Pacific Power (1995) 35 NSWLR 596, 599 (Handley JA), approved in PMT Partners Pty Ltd (In liq) v Australian National Parks & Wildlife Service [1995] HCA 36; (1995) 184 CLR 301, 321-2 (Toohey and Gummow JJ); [1995] HCA 36.
Jolin Nominees Pty Ltd
Daniel Investments
(2019) 267 CLR 560
(2014) 250 CLR 664
(2018) 265 CLR 137
(2009) 239 CLR 27
(1998) 194 CLR 355
(1999) 46 NSWLR 681
(2007) 232 CLR 138
(2013) 248 CLR 619
(2009) 239 CLR 446
(1995) 35 NSWLR 596
(1995) 184 CLR 301