THE TOTAL OF RECTIFICATION COSTS AND COMPLETION COSTS
Ms Mace's oral evidence that the contract price had been increased from the stipulated $800,000 to $1,200,000.
Other amounts payable under the building contract by the owners
THE BUILDER'S CLAIM FOR APPORTIONMENT AND CONTRIBUTION AGAINST THE CONSULTANTS
(a) a claim for economic loss or property damage in an action arising from a failure to take reasonable care within the meaning of s 24AF(1) of the Wrongs Act and
(b) an apportionable claim within the meaning of s 24AE of the Wrongs Act.[13]
The warranties contained in ss 8(b), (c) and (f) are absolute
In Barton v Stiff[18], Hargrave J (as he then was) confirmed the principle that a builder's liability for design and construction was not merely an obligation to use reasonable care. In particular, the warranty of fitness for purpose was absolute. His Honour added that: "the absolute warranty of fitness for purpose relates to the purpose as properly identified". That is, the obligation of the builder must be measured by reference to the purpose for which the building was required under the conditions likely to be encountered at the land
The other warranties implied by s8 of the Domestic Building Contracts Act
(a) the work will be carried out in a proper and workmanlike manner and in accordance with the plans and specifications set out in the contract;
(d) the work will be carried out with reasonable care and skill and will be completed by the date (or within the period) specified by the contract;
(e) if the work consists of the erection or construction of a home, or is work intended to renovate, alter, extend, improve or repair a home to a stage suitable for occupation, the home will be suitable for occupation at the time the work is completed.
The builder's claim for contribution from the building surveyors, the architect and engineer
[1] The equivalent under the BCA 2014 which was in force at the relevant time, to a Performance Solution under the current BCA 2016.
[3] Building Regulations 2006 (Vic) Regulation 109.
[4] [1954] HCA 36; (1954) 90 CLR 613 at 617
[6] See the progress payments scheduled breakdown contained in the contract.
[9] Owners' written submissions dated 8 May 2019, at [161].
[10] Builder's Points of Claim dated 23 December 2016
[11] Ms Mace and Mr Fleischer's Points of Defence dated 7 April 2017, paragraph 7
[13] Builder's defence to Amended Consolidated Points of Counterclaim filed 30 October 2018, at [18]
[15] Builder's defence to amended consolidated points of counterclaim filed 30 October 2018, at [21]
Jinalea Pty Ltd
Mace
(1954) 90 CLR 613