[2009] VCAT 2226
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2009-10-21
Original judgment source is linked above.
5. The claim and counterclaim are otherwise dismissed.
The letter advised "Your home will be complete and ready for handover on Thursday 24 January 2008. Please make contact with Grant Munro in order to confirm an appropriate handover time for settlement to occur. Please find enclosed a copy of your occupancy permit to keep for your records."
As you know, the contract between our clients provides (in clause 20.3) that your client may not terminate the contract unreasonably or vexatiously.
(a) alter the vertical sharpened edge to the kitchen splashback wall tiles and lay tiles in accordance with internal elevation kitchen A;
(b) replace the vanity splashback wall tile at the west end of the en suite;
(c) provide battens for ceiling fans to family meals, beds 1, 2, 3 and 4 if this has not already been done;
(d) install ixl tastic venting in accordance with the contract.
Our client contacted yours directly to make arrangements for those works to be done.
Our client does not accept that the remaining works nominated in your notice of intention to terminate contract are required pursuant to the building contract. In particular:-
(a) the family room sliding door lock and handle is installed in accordance with manufacturer's instructions;
(b) the notes to the contract drawings (sheet 3 of 11) indicate that only single glazing to the external entry door is required;
(c) the porch slab is not part of landscaping and it is not appropriate to refer to a landscaping plan to identify the work required for the porch slab. As the executive inclusions schedule which forms part of the contract as well as the slab design (drawing 2062311/1) makes clear, the porch slab is to be finished in concrete not exposed aggregate.
If your client wishes to dispute whether our client's interpretation of its contractual requirements is accurate, our client is prepared to have that dispute determined and comply with the terms of any such determination. In those circumstances it would clearly be unreasonable and vexatious for your clients to purport to terminate the building contract.
We are instructed that you have failed, refused or neglected to rectify all works in accordance with the Notice of Intention to Terminate Contract, and that you have failed to proceed with the works with due diligence or in a competent manner.
On that basis we hereby enclose by way of service, pursuant to Clause 20.2 of the contract a Notice of Termination due to your substantial breaches of the contract, bringing the contract to an end. We hereby put you on notice that you and your subcontractors are no longer permitted access to our clients' property and should you do so, it will be considered a trespass and our clients will summons the assistance of the Victorian Police."
These are the particulars that the owners rely upon to justify terminating the building contract. I will consider each of the alleged defects separately.
"Concrete paving to Porches, Verandahs, Portico's and Alfresco area."
Clause 3.2 Subject to clause 3.1 any discrepancy or ambiguity in or between the document comprising the contract shall be resolved by adopting the following order of precedence:
Clause 3.3Where any discrepancy exists between figured and scaled dimensions in the plans, the figured dimensions shall prevail. All dimensions are approximate to the extent that they are based on dimensions estimated from any Existing Building.
D The works undertaken to correct kitchen splashback and the fitting of battens to the ceilings resulted in further defects.
Experience sitting in the Domestic Building List and a reading of judgments in building disputes demonstrates that building is a complex process and this complexity and human frailty mean that defects in a structure are common and sometimes, at least on a temporary basis, unavoidable....Given that it is difficult to avoid some defects and that the process of rectification may take some time it seems inherently unlikely that a standard form building contract prepared by a builders' association would intend to leave a builder at risk of contract cancellation for failure to rectify within 14 days of a notice any defect which was more than ephemeral or de minimus.
Repair fencing -allowing replacement of some of the capping
(a) we believe that the fair rate for solid rock removal is $130/m3 plus builder's margin of 15% - the amount of $220/m3 quoted on page 11/16 is unfair and overpriced.
That is our price......will stockpile all the rocks to one side for inspection and then it is rated on that rock on site.
(b) we would like to state in the contract that the rock removed is "solid" measured in the ground with no allowance for over excavation, with the option to inspect the trench prior and after rock removal" (there is no point digging out rock unnecessarily just to pour concrete on it).
If we strike rock and it is in the way then we will remove it and stock pile for inspection?
(c) we would also like to have stated in the contract a definition for rock "rock is material that cannot be removed with a ripper on a 20T excavator"
No......we are using our equipment that is used every day by the construction dept contractors all the time.
The builder warrants that any provisional sum included by the builder in the contract has been calculated with reasonable care and skill taking account of all the information reasonably available at the date the contract is made, including the nature and location of the building site.
Builder generally not entitled to extra amounts for excavations or footings
After entering into this Contract the Builder cannot seek from the Owner an amount of money not already provided for in the Original Contract Price if the additional amount could reasonably have been ascertained had the Builder obtained all the Foundations Data required under the Act.
Builder's entitlement to extra amounts for excavations and footings
The Builder will be entitled to claim an amount of money not already provided for in the Original Contract Price if the need for the additional amount could not have been ascertained from the Foundations Data.
14.3 Owner to pay additional cost if builder entitled to extra amount
If the Builder is entitled to any additional amounts which could not reasonably have been ascertained for excavations or footings under this Contract or the Act, the owner will pay to the Builder in the Builder's next Progress Claim, the agreed cost of the additional work or, if the cost is not agreed, the cost incurred by the Builder plus 15% for the Builder's margin.
JG King Pty Ltd
Sansome & Anor