[2018] VCAT 1595
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2018-10-22
Mr P
Original judgment source is linked above.
"As a result of the interlocutory orders made on the first day, all we have attempted to address here is issues of liability and it comes down to whether or not the respondent caused a delay on the critical path of construction over stages 1, 2 and 3... If the Tribunal finds there was no attributable delay (attributable to the respondent) then there will be no further process in this hearing."[1]
A. Was the Construction Schedule an express term of the contract?
(a) [Dowcon shall employ] sufficient men ... to complete the work generally in accordance with the construction schedule and within any time and dates stated on the Subcontract Order... A copy of the current construction schedule can be viewed at The Contractor's office.
(f) [Dowcon] must bring the Works to Completion by the Date for Completion stated in the Construction Schedule.
This quote is offered on the basis that the items set out in each stage of this quotation will be installed as one complete stage in one visit (possibly over multiple days). Dividing the stages set out in the quotation into smaller installs may create extra costs that would be passed on to the builder. If you would like the staging changed to suit your program, please advise your Dowcon representative and a new quote will be offered if necessary.
"We have issued your steel for fabrication and have a preliminary install date of 13/3. Your job is scheduled to run for 2 days.
This install date is considered preliminary and is subject to change.
As per our project managers advice we need you to complete the following before we can come to install...
We often have to push jobs back by a number of days due to a range of factors including whether, install times at other jobs going longer than expected, changing programs in our customers etc...
Either way, we will call you the day before we are planning to begin install to check that you are expecting us and that you are ready...."[9]
"Hey Brendan, we had a problem in our system and booked a bunch of jobs for that day which can't go ahead. We then had trouble rebooking cranes and have had to push your job to begin on Wed 15th. Everything from the original email still applies. Sorry for the stuff around."[11]
The subcontractor must comply with the contractor's instruction within the time stated by the contractor or, if no time is stated, within a reasonable time.
The existence of a contract of variation must be clearly demonstrated by reference to the usual rules of formation. A definite agreement, going beyond discussion or negotiation, must be established, but as with any contract such an agreement may be inferred from conduct. Consideration must also be established...
An intention to create a legally binding agreement, as well as sufficient certainty of the varied terms, must also be established; unless this is achieved the original contract continues in undiminished operation.
[2] JCM's closing submissions paragraph 1
[3] JCM conceded that defects in the lift shaft did not cause any delay in replacing the roof
[4] Dowcon provided two quotations for the subcontract works. The first, no. 34206, was superseded by the second, no. 34208 dated 24 January 2017. There is no relevant difference between the two.
[6] Dowcon Closing Submission paragraph 27
JCM Builders Pty Ltd
Hicks General Construction Pty Ltd [2018] VCAT 1595