austlii:tas/TASRMPAT/1998/70
appellant. Decision of Glamorgan/Spring Bay Council varied by consent: (1) Condition 1 amended to require payment of $750 for construction and sealing of entrance off Tasman Highway, to be undertaken...
4 cited instruments linked from this judgment.
This case involved an appeal against a council's approval of a quarry. Rather than proceed to a full hearing, the parties reached an agreement through a conference process. The Tribunal approved the agreed terms, which modified some of the conditions attached to the quarry approval, including payment arrangements for road works and limits on crushing operations. The parties were to bear their own legal costs unless one party applied for a costs order within two weeks.
AI-generated legal information, not legal advice. Zoe can make mistakes. Check the cited source, and for advice about your situation consult a qualified Australian lawyer.
JB & P Salmon -v- Glamorgan/Spring Bay Council [1998] TASRMPAT 70 (31 March 1998)
Tasman Highway, South of Triabunna - Quarry - Consent Decision
This was an appeal pursuant to Section 61(4) of the Land Use Planning and Approvals Act 1993, against Council's grant of conditional approval for a quarry.
A preliminary hearing was held at Triabunna on the 26th of March 1998.
As a result of a conference pursuant to Section 17 of the Resource Management and Planning Appeal Tribunal Act 1993 held on the 26th March 1998 at Hobart, agreement was reached between the parties as to the terms of a decision of the Appeal Tribunal and the terms of that agreement were reduced to writing and were signed by the parties and given to the Appeal Tribunal.
The Appeal Tribunal being satisfied that a decision in the terms as agreed by the parties would be within the powers of the Appeal Tribunal and would be an appropriate decision makes a decision accordingly without holding a hearing.
The decision of the Appeal Tribunal is that the decision of the Glamorgan/Spring Bay Council is varied as follows:
"That Mr Salmon pay Council the sum of $750.00 as complete payment for the construction and sealing of the entrance off the Tasman Highway; the work to be undertaken at the same time as the sealing of the entrance to Council's refuse disposal site at Orford."
"That crushing for 15 days, or 5000 cubic metres of material, be permitted annually subject to the General Manager being notified prior to the beginning of each crushing operation."
The Tribunal will entertain any application for an order for costs in this appeal, if made to the Tribunal in writing with supporting submissions within the next fourteen days. If requested the Tribunal will reconvene to hear any evidence in respect of any matter bearing on an order for costs.
In the absence of any such application for an order for costs the order of the Tribunal is that each party bear its own costs.
JB & P Salmon
Glamorgan/Spring Bay Council [1998] TASRMPAT 70
Decision of Glamorgan/Spring Bay Council varied by consent: (1) Condition 1 amended to require payment of $750 for construction and sealing of entrance off Tasman Highway, to be undertaken concurrently with sealing of Council's refuse disposal site entrance at Orford; (2) Condition 3 amended to permit crushing for 15 days or 5000 cubic metres annually, subject to prior notification to General Manager; (3) Condition 2 unchanged. Costs: each party to bear own costs unless application made within 14 days.