_James Hardy Building Systems Pty Limited v Epoca Constructions Pty_
[2001] QSC 89
At a glance
Source factsCourt
Supreme Court of Queensland
Decision date
2001-03-03
Before
Ambrose J, Campbell CJ, Shepherdson J, Derrington J
Source
Original judgment source is linked above.
Judgment (45 paragraphs)
[1] The plaintiff ("the contractor") was the head contractor with the State of Queensland for construction of roadworks described as the South-East Transit Project Section 4.
[2] The defendant ("the subcontractor") was one of the subcontractors of the contractor, whose subcontract required it to construct certain bridge works required under the head contract.
[3] There was a great deal of material read upon the application which I will not attempt to analyse in detail. The contactor applies pursuant to s 21 of the Subcontractors' Charges Act 1974 ("the Act") for cancellation of a claim of charge of which the subcontractor gave the contractor notice on 7 November 2000.