[2024] QSC 16
Supreme Court of Queensland
2024-02-21
Wilson J
Original judgment source is linked above.
(a) first, in relation to the adjudicator's treatment of retention monies (the retention monies issue);
(b) second, the adjudicator awarded the first respondent the sum of $781,628.24 (GST exc.) notwithstanding that the sum to which this item related was not claimed by it (the award of unclaimed insurance amounts);
(c) third, the adjudicator awarded an amount of $141,459.89 (GST exc.) to the first respondent notwithstanding that it did not claim for this sum within its adjudication application (the award of unclaimed structural engineer amounts);
(d) fourth, in relation to the adjudicator's valuation of the architect item (the architect item issue); and
(e) fifth, the payment claim the subject of the adjudication decision was not a valid payment claim under the Payment Act because it did not request payment for the claimed amount in accordance with section 68 (1) (c) (the request for payment issue).
(a) 28 July 2023;
(b) 25 August 2023;
(c) 28 August 2023; and
(d) 4 September 2023.
(a) an adjudicator's decision may be reviewed for jurisdictional error by the adjudicator in the performance of the adjudication function; and
(b) an adjudication decision may be declared invalid and void for jurisdictional error.
(a) the object of the Payment Act is to ensure cashflow to construction contractors in recognition of the fact that without cash flow, such contractors may not survive;
(b) the procedure of adjudication is subject to strict, fast time frames;
(c) section 101 (a) of the Payment Act preserves the parties' ultimate rights which may be pursued by litigation in the ordinary course; and
(d) the procedure of adjudication has been described as "pay now, argue later".[3]
"[163] In deciding whether writs of prohibition and certiorari (and analogous forms of relief) should be granted, a distinction is drawn between jurisdictional error and error within jurisdiction. This court has not accepted that this distinction should be discarded. As was noted in Craig v South Australia, that distinction may be difficult to draw. The difficulty of drawing a bright line between jurisdictional error and error in the exercise of jurisdiction should not be permitted, however, to obscure the difference that is illustrated by considering clear cases of each species of error. There is a jurisdictional error if the decision maker makes a decision outside the limits of the functions and powers conferred on him or her or does something which he or she lacks power to do. By contrast, incorrectly deciding something which the decision maker is authorised to decide is an error within jurisdiction. This is sometimes described as authority to go wrong, that is, to decide matters within jurisdiction incorrectly. The former kind of error concerns departures from limits upon the exercise of power. The latter does not."
The Principal may terminate the Contract for any reason by giving the Contractor 10 business Days' written notice, after which the Contract is ended, and the Principal, subject to the Contractor's compliance with this clause, shall pay to the Contractor.
(a) the amount due to the Contractor shown in any unpaid progress certificate;
(b) the amount certificate by the Superintendent for WUC carried out to the date the Contract is ended, evidencing the amount not otherwise included in the progress certificate which would have been payable had the Contract not been ended and had the Contractor been entitled to and made a claim for payment on the date the Contract is ended;
(c) the cost of materials reasonably ordered by the Contractor for WUC or work, which the Contractor cannot return, or which order cannot be cancelled, but only if the materials become the property of the Principal upon payment; and
(d) the amount certified by the Superintendent on account of reasonable demobilisation costs.
Without limiting any other rights of the Principal, subject to clause 5, the Principal shall release security without 10 business Days of the date of termination under this clause.
The provisions of this subclause survive the termination or expiration of the Contract."
"54. Pursuant to clause 68(2) of the Payment Act, the Contractor[5] is entitled to include in a Payment Claim an amount that "is held under the construction contract by the respondent and that the claimant claims is due for release".
44.5 If Descon's claim for retention is a claim for construction work or related goods and services which can be pursued in adjudication under the Payment Act, Descon must establish a contractual entitlement to retention and this requires establishing an entitlement under clause 41 of the General Conditions, as that is Descon's sole entitlement upon termination under that clause.
44.6 At [38] of the Adjudication Application submissions, Descon submits that, as at the date of the Payment Claim on 28 February 2023, Iris had no right to retain retention, as the Contract was terminated from 9 February 2023.
44.7 The question is, therefore, whether Iris's right to withhold retention survives termination of the Contract. It is clear that it does.
44.8 As set out in the Payment Schedule, Descon has no entitlement to the release of retention under clause 41 of the General Conditions because:
(a) the provision for the release of security under clause 41 of the General Conditions is expressly provided to be '[w]ithout limiting any other rights of the Principal', and also to be subject to clause 5 of the General Conditions;
(b) pursuant to clause 5.7(a) of the General Conditions, Iris may continue to hold security or retention moneys 'where the contract may otherwise require it to be released or after termination of the Contract for any reason, if there is any amount claimed by the party under or in connection with the Contract (whether liquidated or otherwise)'; and
(c) Iris has claims against Descon under or in connection with the Contract entitling it to retain the retention (including those set out in Part E, below).
44.9 Accordingly, while clause 41 may 'otherwise' provide for the release of security, clause 41 is expressly subject to clause 5, and clause 5.7(a) provides that Iris may continue to hold retention moneys, '[d]espite any other provision of the Contract'.
44.10 For the purposes of clause 5.7(a) of the General Conditions, Iris has two substantial claims against Descon which are the subject of proceedings before the Supreme Court of Queensland. Contained at Annexure I to this Adjudication Response are Iris's claims and statements of claim filed and served in those proceedings."
(a) a party holding security or retention moneys may continue to hold security or retention monies (in an amount reasonably determined by that party to cover any amount claimed by that party) where the Contract may otherwise require it to be released or after termination of the Contract for any reason, if there is any amount claimed by the party under or in connection with the Contract (whether liquidated or otherwise)..."
"440. The Claimant has claimed for the full release of retention of $1,838,287.25 excluding GST on the basis that clause 41 of the Contract provides that security must be released by the Respondent within 10 business days after the day of termination of the Contract which is before the reference date for the Payment Claim.
(a) as it is subject to clause 5;
(b) clause 5.7(a) provides that the Respondent may continue to hold retention where the contract may otherwise require it to be released or after termination of the contract for any reasons, if there is any amount claimed by the party under or in connection with the contract; and
(c) the Respondent claims against the Claimant under or in connection with the Contract entitled it to retain the retention.
(a) denied it procedural fairness by failing to seek submissions about the effect clause 5.2 of the contract; and / or
(b) did not "consider" the applicant's submissions as to why clause 5.7 (a) of the contract entitled it to withhold the retention, as mandated by section 88 (2) (d) of the Payment Act.
"Accordingly, while clause 41 may 'otherwise' provide for the release of security, clause 41 is expressly subject to clause 5, and clause 5.7 (a) provides that Iris may continue to hold retention moneys '[d]espite any other provision of the Contract."
Security shall be provided in accordance with Item 14 or 15. All delivered security, other than cash or retention moneys, shall be held in accordance with the requirements of this Contract.
If security is provided by a financial institution the security shall be in the form of two unconditional undertakings given by a financial institution acceptable to the Principal's Financier.
If the Contract sum increases in accordance with the Contract by a total of 5% or more, and for each 5% increase thereafter, the Principal may direct the Contractor to provide additional security in accordance with Item 14 that is proportionate to the increase in the Contract sum.
The Contractor is not entitled to any payment under the Contract to the extent that it has not lied with this clause.
(a) where an amount due to the Principal under the Contract remains unpaid after the time for payment;
(b) in respect of any bona fide claim to payment (liquidated or otherwise), the Principal may have against the Contractor under the Contract,
on the giving of 5 days written notice to the Contractor.
The provisions of this subclause 5.2 survive the termination or expiration of the Contract.
The Contractor may by written notice to the Principal request permission to substitute the form of security. The Principal may, in its absolute discretion, accept or reject the request. If permission is granted to the extent that another form of security is provided, the Principal shall promptly release and return the original security.
Upon the issue of the certificate of practical completion, the Principal's entitlement to security (other than in Item 14(e)) shall be reduced by the percentage or amount in Item 14(f), and the reduction shall be released and returned within 14 days to the Contractor.
The Principal's entitlement to security in Item 14(e) shall cease 14 days after incorporation into the Works of the plant and materials for which that security was provided.
The Principal's entitlement otherwise to security shall cease 14 days after the later of:
(a) the date of issue of the final certificate; or
(b) the date upon which the Contractor has duly executed the completed copy of the Deed of Release - Final issued to the Contractor by the Superintendent and returned the same to the Superintendent and the Principal.
Upon the Principal's entitlement to security ceasing, the Principal shall release and return forthwith the security to the Contractor.
Except where held by a government department or agency or a municipal, public or statutory authority, any portion of security (and interest earned thereon) which is cash or retention moneys, shall be held in trust for the party providing them until the Principal or the Contractor is entitled to receive them.
Interest earned on security not required to be held in trust shall belong to the party holding that security.
(a) the Contractor must lodge with the Principal prior to commencing work on the Site, and within 14 days of the date of the Contract, the deed of guarantee and indemnity (Performance Guarantee) annexed as Annexure Part F executed by the Contractor's ultimate holding company (as that term is defined in the Corporations Law) or if there is no ultimate holding company the n the directors of the Contractor;
(b) the Principal must not be required to lodge a Deed of guarantee, Undertaking and Substitution; and
(c) the Principal may refuse to make any payment otherwise due under the Contract until the Contractor has fully complied with its obligation under paragraph (a).
(a) a party holding security or retention moneys may continue to hold security or retention monies (in an amount reasonably determined by that party to cover any amount claimed by that party) where the Contract may otherwise require it to be released or after termination of the Contract for any reason, if there is any amount claimed by the party under or in connection with the Contract (whether liquidated or otherwise);
(b) where the Contract is terminated by reason of the Contractor repudiating the Contract, being in breach of the Contract or having an event referred to in clause 39.11 (insolvency) occur in respect of it, the Principal may have immediate recourse to security or retention moneys after termination for any claim to money which the Principal may have against the Contractor whether for damages (including liquidated damages) or otherwise; and
(c) where the Contract is terminated in circumstances other than those referred to in paragraph 5.7(b), the Principal may have recourse to security or retention moneys after termination where the Contract fails to pay any amount which becomes due to the Principal within the agreed period for payment or if no period is agreed, within 5 days.
If the security is in the form of an undertaking from a financial institution or insurance company and such issuer:
(a) becomes insolvent or is unable to pay its debts as and when they fall due; or
(b) is an individual Person or a partnership including an individual Person, and if that Person:
(i) commits an act of bankruptcy;
(ii) has a bankruptcy petition presented against him or her or presents his or her own petition;
(iii) is made bankrupt;
(iv) makes a proposal for a scheme of arrangement or a composition; or
(v) has a deed of assignment or deed of arrangement made, accepts a composition, is required to present a debtor's petition, or has a sequestration order made, under Part X of the Bankruptcy Act 1966 (Cth); or
(c) is a corporation, and in respect of such corporation:
(i) notice is given of a meeting of creditors with a view to the corporation entering a deed of company arrangement;
(ii) the corporation enters a deed of company arrangement with creditors;
(iii) a controller or administrator is appointed;
(iv) an application is made to a court for the winding up of the corporation and not stayed within 14 days;
(v) a winding up order is made in respect of the corporation;
(vi) the corporation resolves by special resolution that it be wound up voluntarily (other than for a member's voluntary winding-up);
(vii) a mortgagee of any property of the corporation takes possession of that property;
(viii) the shareholders or directors of the corporation attempt to pass or pass a resolution which bas as an object the winding up of that corporation; or
(ix) the corporation goes into voluntary administration, then the Contractor must within 14 days of a written request by the Principal provide new security in accordance with this clause."
(a) formed the view that because the applicant had provided no evidence that it had notified the first respondent in accordance with clause 5.2 of the contract prior to termination of the contract (despite not having asked the parties for submissions as to whether or not that had occurred), the applicant's right to hold the retention was somehow lost;
(b) applied the test for the existence of the right to withhold as being conditional upon the giving of 5 days' notice in writing, which is not a requirement of clause 5.7(a) of the contract; and
(c) purported to determine the first respondent's entitlement to the retention on the basis of arguments that were not put to her by either party, and about which she gave neither party an opportunity to make submissions.
"[41] ... the valid exercise of an adjudicator's jurisdiction is conditioned on the adjudicator having accorded to the parties what White JA described in Northbuild Construction Pty Ltd v Central Interior Linings Pty Ltd [2011] QCA 22; [2012] 1 Qd R 525 as "the necessary level of procedural fairness". The juridical basis for this proposition is the same as the preceding propositions. The legislature must be taken to have contemplated that an adjudicator would have accorded the parties the necessary level of procedural fairness, such that failure to do so would be regarded as breach of a condition of the valid exercise of the jurisdiction..."
"[107] ... It may readily be accepted that the Act provides for a somewhat rough and ready way of assessing a builder's entitlement to progress claims. It may also be accepted that the procedure is intended not only to be swift, but also to be carried out with the minimum amount of formality and expense. Nonetheless, what an adjudicator is required to do is to decide the dispute between the parties. Under the scheme of the Act, that dispute is advanced by the parties through their adjudication application and adjudication response (which, no doubt, will usually incorporate the antecedent payment claim and payment schedule). If an adjudicator is minded to come to a particular determination on a particular ground for which neither party has contended then, in my opinion, the requirements of natural justice require the adjudicator to give the parties notice of that intention so that they may put submissions on it..."
"[40] The adjective "substantial" has been used in the relevant authorities to capture the principle that the opportunity denied was material, namely that the matter about which the adjudicator did not provide an opportunity to be heard was a point upon which the adjudicator based his or her decision and was significant to the Payment Actual determination. In addition, the Court's concern is with the practical effect of the alleged denial of natural justice. Reference to the High Court's decisions in Stead v State Government Insurance Commission and Ex parte Aala supports the proposition that even if the Court is satisfied that there has been a denial of natural justice, relief may be denied if it can be shown that compliance with the requirements of natural justice could have made no difference to the outcome. It is probably sufficient in this regard for the applicant for relief to show that there were substantial submissions that, as a matter of reality and not mere speculation, might have persuaded the adjudicator to change his or her mind."
"447. The Payment Schedule notes that the Respondent wants to withhold retention for alleged overpayments. However, as I have found above that the Respondent is not entitled to withhold amounts from the Payment Claim for such reasons and in the absence of any evidence from the Respondent that it has provided written notice to the Claimant of a bona fide claim to which clause 5.2 relates, I find that the Respondent is not entitled to withhold retention from the Payment Claim."
"However, as I have found above that the Respondent is not entitled to withhold amounts from the Payment Claim for such reasons..."
"... and in the absence of any evidence from the Respondent that it has provided written notice to the Claimant of a bona fide claim to which clause 5.2 relates, I find that the Respondent is not entitled to withhold retention from the Payment Claim."
(a) the amount of the progress payment, if any, to be paid by the respondent to the claimant (the adjudicated amount); and
(b) the date on which any amount became or becomes payable; and
(c) the rate of interest payable on any amount."
"(2) In deciding an adjudication application, the adjudicator is to consider the following matters only -
(a) the provisions of this chapter and, to the extent they are relevant, the provisions of the Queensland Building and Construction Commission Act 1991, part 4A;
(b) the provisions of the relevant construction contract;
(c) the payment claim to which the application relates, together with all submissions, including relevant documents, that have been properly made by the claimant in support of the claim;
(d) the payment schedule, if any, to which the application relates, together with all submissions, including relevant documents, that have been properly made by the respondent in support of the schedule;
(e) the results of any inspection carried out by the adjudicator of any matter to which the claim relates."
"[35] Second, the valid exercise of an adjudicator's jurisdiction is conditioned on the adjudicator having arrived at his or her conclusion by a process which considers the matters set out in s 88(2) of the Payment Act. But as to this, the following important matters must be noted:
(a) The valid exercise of an adjudicator's jurisdiction is not conditioned on the adjudicator reaching what is objectively the correct conclusion on all of the questions of fact or law required by the consideration of the matters set out in s 88(2). Or, to put it another way, there are many errors of fact and law which might be made by an adjudicator which would not be regarded as going to jurisdiction.
(b) On an application to set aside an adjudicator's decision for jurisdictional error, the question is not whether the Court would have come to the same conclusion as the adjudicator. Rather, the question is whether the adjudicator arrived at his or her conclusion by a process which failed to consider the matters set out in s 88(2).
(c) This point was succinctly made in Northbuild Construction Sunshine Coast Pty Ltd v Beyfield Pty Ltd [2014] QSC 80; [2015] 1 Qd R 463, 469-470 [29], where McMurdo J pointed out (footnotes in original):
"To determine an application, an adjudicator must identify the relevant terms of the contract upon which the claim is made and then apply the facts, as he or she finds them to be, to those terms upon their proper interpretation. The identification of the terms and the interpretation of those terms are thereby questions which the adjudicator must answer in the exercise of his jurisdiction. It follows that an error in the identification of the terms or in their interpretation will not be a jurisdictional error: Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd; Clyde Bergemann Senior Thermal Pty Ltd v Varley Power Services Pty Ltd; BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd."
(d) His Honour distinguished between that sort of error - which was not jurisdictional error - and that which was, in the following passage ([2015] 1 Qd R 463, 470 [30]):
"However, where it appears that an adjudicator is not meaning to apply the contract, as he or she interprets it, but is instead allowing the claim upon some other basis, the position is different, because the adjudicator is thereby misunderstanding the scope of the adjudicator's jurisdiction."
(e) Adjudicators under the Payment Act do not have to get the answer right, but if it is demonstrated that they have not gone about their task by carrying out the Payment Active process of intellectual engagement with the issues and the submissions before them that the Payment Act requires, then they will have fallen into jurisdictional error because they will not have done the very thing s 88(2) of the Payment Act required them to do."
(1) A conclusion that the decision-maker 'has not engaged in an active intellectual process will not lightly be made and must be supported by clear evidence, bearing in mind that the judicial review applicants carry the onus of proof'.
(2) What is required is the reality of consideration by the decision-maker, the Court on judicial review being required to assess, in a qualitative way, whether the decision-maker has as a matter of substance had regard to the relevant matter.
(3) The onus lies on the appellant to establish on the balance of probabilities that a relevant matter was not considered, taking into account that the reasons must be read fairly and not in an unduly critical manner..."
"[66] John Holland may have substantial reasons for disputing the conclusion that Schedule R did not govern entitlements to variations and the reasoning that led to it. However, in circumstances in which adjudicators are required to determine complex legal issues quickly, the detection of flaws in reasoning or poorly expressed reasons in an adjudication decision do not compel the conclusion that the adjudicator did not attempt to understand and apply the contract. Adjudicators provide their determinations in a "somewhat pressure cooker environment". In some instances the adjudicator "cannot possibly, in the time available and in which the determination is to be brought down, give the type of care and attention to the dispute capable of being provided upon a full curial hearing". The Court should be slow to conclude that adjudicators who work under the very tight deadlines imposed by the Payment Act, and who, in seeking to do their best, make a mistake, have not acted in good faith."
"... The respondent has simply stated that it has a claim against the Claimant without identifying the basis for the claim, the contractual provision on which it relies to withhold the retention from the Payment Claim etc."
(a) the contractual provision on which it relied (clause 5.7 (a)); and
(b) the basis for the two claims it made against the first respondent.
(a) either did not consider the applicant's submissions regarding clause 5.7 (a) of the contract; or
(b) did not carry out a process of active intellectual engagement with the applicant's submissions.
(a) they have been denied procedural fairness; and
(b) the adjudicator failed to consider their submission about the effect of clause 5.7 (a) of the contract.
Ground 2 - The award of unclaimed insurance amounts
(a) $1,885,048 (GST exc.) (being the total cost of the insurance);
(b) $1,541,062.38 (GST exc.) (being the total value of refunds available); or
(c) $648,490.04 (GST exc.) (being the total sum of refunds actually received by the first respondent) from payment claim 7.
(a) conceded that the applicant "will be entitled to the benefit of any refund received from the insurance policy ... limited to the pro-rated value that is refunded by the insurer" (this concession being consistent with the first respondent's position in the prior adjudication decision); and
(b) stated that "the amount of the anticipated insurance refund is $1,574,226.82 however an amount of $781,628.24 is yet to be refunded by the insurers".
(a) the applicant was not entitled to its claimed setoff; or
(b) that an amount ought to be awarded in its favour in respect of insurances.
(a) the first respondent claimed no amount for insurance in payment claim 7;
(b) the applicant explained the basis for its setoff within its response submissions; and
(c) the first respondent made relevant concessions within its further submissions.
Ground 3 - The award of unclaimed structural engineer amounts
(a) copied the "claim to date" amounts from payment claim 7 into her column entitled "total in payment claim", notwithstanding that these were not the amounts actually claimed by the first respondent within payment claim 7 in respect of the structural engineer; and
(b) then copied the amounts within her column entitled "total in payment claim" to her column entitled "total adjudicated amount" notwithstanding that not all of these amounts were the subject of payment claim 7.
"274. In the Payment Claim, the Claimant has claimed the total amount of $203,780 excluding GST for this item. The total amount previously approved for this work package by the Respondent was $160,000 excluding GST.
(c) the certified value reflects work completed to date;
(d) the Claimant must establish what WUC it has actually achieved and why it is entitled to a progress payment in respect of that WUC;
(e) the Claimant has claimed on a cost reimbursable basis, without attempting to establish the proportion of the design services that have been carried out having regard to the scope of the WUC and work;
(f) the Claimant must establish the value of WUC carried out to the date the Contract was ended pursuant to clause 41(b);
(g) the Claimant has not demonstrated that it has incurred the amounts that it has claimed for consultants in the Payment Claim;
(h) the DBI invoices that the Claimant refers to in the Payment Claim show the value complete to be $183,780.
"87 Valuation of work etc. in later adjudication application
(1) This section applies if, in deciding an adjudication application, an adjudicator has decided the value of -
(a) any construction work carried out under a construction contract; or
(b) any related goods and services supplied under a construction contract. Note - See section 72 for the valuation of construction work and related goods and services.
(2) Any adjudicator must, in any later adjudication application that involves the working out of the value of the construction work or of the related goods and services, give the work, or the goods and services, the same value as that previously decided by the adjudicator unless the claimant or respondent satisfies the adjudicator concerned that the value of the work, or the goods and services, has changed since the previous decision..."
"[57] Where s. 27(2) applies, it informs the manner in which the adjudicator is to perform the function imposed by s. 26(1) of deciding the amount of a progress payment. In performing that function, s. 26(2) requires the adjudicator to take into account only the matters described in paragraphs (a)-(e) of that subsection..."
"(d) ... all submissions, including relevant documents, that have been properly made by the respondent in support of the [payment] schedule..."
"23.1 The following table summarises the position from the Payment Claim and the Payment Schedule:
(a) certified an additional $20,000 as being payable in relation to this item, for a total approved amount of $180,000 for this items; and
(b) stated the following reason for withholding payment: 'Based on DBI Reconciliation of Paid To Date'.
23.3 In addition, as stated at Annexure D of the Payment Schedule, for each of the consultant items, the Payment Schedule stated that:
(a) it is necessary for Descon to establish what WUC it has actually achieved and why it is entitled to a progress payment in respect of that WUC (paragraph 10.4);
(b) Descon has claimed on a cost-reimbursable basis, without attempting to establish the proportion of the design services that have been carried out having regard to the scope of the WUC and work (paragraph 10.7);
(c) pursuant to clause 41(b) of the General Conditions, Descon must establish the value of WUC carried out to the date the Contract was ended (paragraph 10.9); and
(d) Descon has not demonstrated that it has incurred the amounts that it has claimed for consultants in the Payment Claim (paragraph 10.10).
23.4 Further reasons for withholding payment were also set out by the covering letter of the Payment Schedule, contained at Annexure L of this Adjudication Response, which Descon has omitted to include.
23.5 These issues have not been addressed in the Adjudication Application. Paragraphs 22.8 to 22.11, above, explain why Descon's submissions do not address the real issues.
23.6 The Adjudicator should find that Descon is not entitled to any additional payment and that Descon is entitle to payment of no more than $180,000.
23.7 The Adjudication Application does not substantiate Descon's claim to payment of $203,780 because:
(a) Descon relies on two invoices from DBI Design Pty Ltd (DBI) totalling $43,780, to claim a total amount to date of $203,780.
(b) Descon has not established that it has performed the architectural WUC to the value of $203,780. Indeed, the two invoices from DBI support a different position. Invoice 10130 from DBI states a 'value complete' of $180,000, and invoice 10140 from DBI states a 'value complete' of $183,780. Accordingly, even taking Descon's evidence at its highest, no amount more than $183,780 could be assessed for this item.
23.8 Further, as set out in the Third Goldman Declaration, Descon has made payment to DBI in the amount of $180,000. As set out above, the Superintendent's assessment was based on a reconciliation of the amount paid to date to DBI.
23.9 Mr Isaac's statutory declaration (sworn on 28 February 2023) that was included within the Payment Claim did not disclose that Descon has not paid DBI's 30 January 2023 invoice, but this is what the Superintendent's investigations have confirmed, as deposed to by Mr Goldman in the Third Goldman Declaration.
23.10 Pursuant to clause 38.2 of the General Conditions, Iris is entitled to withhold moneys until Descon provides evidence to the Superintendent's satisfaction that Descon has paid DBI under invoice 10140. As set out in the Third Goldman Declaration, Mr Goldman was not satisfied that Descon had paid more than $180,000 to DBI.
23.11 Accordingly, the Adjudicator should find that no additional amount is payable to Descon in relation to this item."
"MR AMBROSE: - - - and do that. The issue is she has not even dealt with that point. So she said, "That is not a submission asking me to revalue the work." If your Honour finds that it is in truth not a submission asking her to revalue the work, then this part - this ground will fall away.
HER HONOUR: So the question is, when she says, "Neither party has made any submissions to show why I should revalue this package", you say there are, and that is at 23.7?
HER HONOUR: And then the question is, is that a submission to show why she should value the package as something less than the amount?
HER HONOUR: And what can be said against you is, that's fairly vague and you haven't put it in terms of actually what you're - what the bottom line is.
MR AMBROSE: If it was a requirement, for example, that we were - we had to expressly draw her attention to 87.3, we haven't done that. But she identified that that was the relevant provision.
MR AMBROSE: But she doesn't, for example, say, "I've seen the submission and 27.3. That doesn't satisfy me that I need to exercise that discretion." What she says is, "No submission has been made."
HER HONOUR: So the question is - the question really is, is that a submission?
MR AMBROSE: We say it is because it identifies, in (b) - in (a) and (b), that the amount that had been claimed and the amount that had been previously provided are in excess of what the evidence establishes, which is the invoices which show that the earlier claim that was $200,000 should have been no more than 180,000, and the new claim seeking a further $3780 could mean that the total value must be less than the original $200,000. It could be no more than 183,780."
(a) was a document that was not before the adjudicator for the prior adjudication decision; and
(b) is also evidence that the value of the work had changed since the prior adjudication decision.
"Further Comments on the Principal's Payment Schedule
The Principal at Part B of its "Reasons for withholding Payment" makes generic submissions as to the entitlement of the Contractor to claim being based on the completion of the WUC.
The invoices that accompanied the Payment Claim issued to the Principal make specifical reference to the nature of the work performed and the percentage basis of such works completion, for example, the works performed by the Geotechnical engineering consultant are detailed in each of the invoices included as part of the payment claim that established the basis of the WUC and work completed.
There is no specific response to each of the consultant invoices supplied by the Contractor denying that any of the services claimed were either not provided or a dispute raised as to the value of such services.
In the payment schedule the Principal has then made unsubstantiated deductions to consultant fees based on heresay and does not meet the requirements of section 69(c) of the Payment Act."
"(1) A payment claim, for a progress payment, is a written document that -
(a) identifies the construction work or related goods and services to which the progress payment relates; and
(b) states the amount (the claimed amount) of the progress payment that the claimant claims is payable by the respondent; and
(c) requests payment of the claimed amount; and
(d) includes the other information prescribed by regulation."
(1) A person mentioned in section 12 who is or who claims to be entitled to a progress payment (the "claimant") may serve a payment claim on the person who, under the construction contract concerned, is or may be liable to make the payment (the "respondent").
(a) must identify the construction work or related goods and services to which the progress payment relates; and
(b) must state the amount of the progress payment that the claimant claims to be payable (the "claimed amount"); and (c) must state that it is made under this Act. (3) The claimed amount may include any amount - (a) that the respondent is liable to pay the claimant under section 33(3); or (b) that is held under the construction contract by the respondent and that the claimant claims is due for release. (4) A claimant can not serve more than 1 payment claim for each reference date under the construction contract, but may include in any payment claim an amount that has been the subject of a previous payment claim..."
"[209]... lays down clear specifications of time and other requirements to be observed. It is not difficult to understand that the availability of those rights should depend on strict observance of the statutory requirements that are involved in their creation."
"[50] The principles which govern the approach to, and consequences of, noncompliance with provisions of the Payment Act are now well trodden ground.
[51] Punctilious compliance with provisions of the Payment Act upon which the effectiveness of the decision making process under it depends is required."
(a) it included the term "invoice";
(b) there was a separate invoice that came with the payment claim stating "amount due"; and
(c) it included bank details as to where payment could be made.
"This Month's Claim Total Progress Claim Value for the Month (Excl. GST): $13,432,898.29
Total Progress Claim Value for the Month (Incl. GST):
"This Progress Claim is submitted under the Building Industry Fairness (Security of Payment) Act 2017..."
"I am making this statutory declaration in connection with the payment of Progress Claim No. 7 dated 28 February 2023 pursuant to the Contract."
(a) Ground 1 - the retention of monies issue;
(b) Ground 2 - the award of unclaimed insurance amounts;
(c) Ground 3 - the award of unclaimed structural engineer amounts; and
(d) Ground 4 - the architect item issue.
[1] Adjudication decision number 2285814.
[2] Northbuild Construction Pty Ltd v Central Interior Linings Pty Ltd [2011] QCA 22; [2012] 1 Qd R 525, [9], [25], [32] and [69]. See also Thiess Pty Ltd v Warren Brothers Earthmoving Pty Ltd [2012] QCA 276; [2013] 2 Qd R 75, [77].
[3] Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC 1140 at [96].
[4] Re Refugee Review Tribunal; Ex parte Aala [2000] HCA 57; (2000) 204 CLR 82 at [163].
[5] The first respondent in these proceedings.
[7] Acciona Agua Australia Pty Ltd v Monadelphous Engineering Pty Ltd [2020] QSC 133; (2020) 4 QR 410 at [41].
[9] Musico v Davenport [2003] NSWSC 977 at [107].
[10] John Goss Projects Pty Ltd v Leighton Contractors Pty Ltd (2006) 66 NSWLR 707 at 716.
[12] Adjudication decision number 2285814 at [227] - [245].
[13] Adjudication decision number 2285814 at [246] - [273].
[14] Re Minister for Immigration & Multicultural Affairs; Ex parte Lam (2003) 214 CLR 1 at [37].
[15] Acciona Agua Australia Pty Ltd v Monadelphous Engineering Pty Ltd [2020] QSC 133; (2020) 4 QR 410 at [35].
[16] Jabari v Minister for Immigration, Citizenship, Migrant Services and Multicultural Affairs [2023] FCAFC 98; (2023) 298 FCR 431 at [55]. Although dealing with a migration decision, the principles are of a much wider application.
[18] [2008] QCA 213; [2008] 2 Qd R 495 at [57] (with whom McMurdo P and Keane JA agreed).
[19] Acciona Agua Australia Pty Ltd v Monadelphous Engineering Pty Ltd [2020] QSC 133; (2020) 4 QR 410 at [35(e)].
[20] Building and Construction Industry Payments Act 2004 (Qld) s 17.
[21] See Niclin Constructions Pty Ltd v SHA Premier Constructions Pty Ltd & Anor [2019] QCA 177; (2019) 2 QR 190 specifically Applegarth J's reasons at [12]; Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd [2010] NSWCA 190; (2010) 78 NSWLR 393 per McDougall J at [209]. Whilst the objects of the Payment Act seek to "preserve the cash flow to a builder", strict compliance with the requirements of the Payment Act is essential and a precondition to that entitlement arising.
[22] Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd [2010] NSWCA 190; (2010) 78 NSWLR 393 at [209].
[23] Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd [2010] NSWCA 190; (2010) 78 NSWLR 393 at [209].
[24] Parkview Constructions Pty Ltd v Total Lifestyle Windows Pty Ltd T/as Total Concept Group [2017] NSWSC 194 at [50] - [51].
[25] See JAG Projects Qld Pty Ltd v Total Cool Pty Ltd [2015] QSC 229.
Iris Broadbeach Business Pty Ltd
Descon Group Australia Pty Ltd & Anor [2024] QSC 16
(2010) 78 NSWLR 393
(2006) 66 NSWLR 707
(2000) 204 CLR 82
(2003) 214 CLR 1
(2023) 298 FCR 431