[2014] VCAT 396
Victorian Civil and Administrative Tribunal
2014-04-09
Original judgment source is linked above.
The practice of VCAT is to designate cases of interest as 'Red Dot Decisions'. A summary is published and the reasons why the decision is of interest or significance are identified. The full text of the decision follows. This Red Dot Summary does not form part of the decision or reasons for decision.
Mr and Mrs Tony Inglese v Yarra Ranges Shire Council
Application for review under section 97P Planning and Environment Act 1987 for certificate of compliance
REASONS WHY DECISION IS OF INTEREST OR SIGNIFICANCE
LEGISLATION - interpretation or application of statutory provision
Consideration of application for review under section 97P Planning and Environment Act 1987 - certificates of compliance under part 4A Planning and Environment Act 1987 - declarations under sections 149A & 149B Planning and Environment Act 1987 to establish existing use rights
The Planning and Environment Act 1987 offers various opportunities to establish existing use rights by way of application for a certificate of compliance, or application for a declaration under sections 149A or 149B. The appropriateness of each procedure will depend on the circumstances of each case and the needs of the person making the application. However, there is nothing in the legislation that inhibits or should inhibit a person from selecting which procedure to adopt based on the complexity or contention of the subject matter.
Part 4A of the Act governing certificates of compliance introduced a comprehensive scheme into the Act to enable certificates to be issued stating whether an existing or proposed use or development complies with the planning scheme. The existence of such a comprehensive scheme means it should be the preferred means of establishing whether an existing or proposed use or development complies with the planning scheme, unless there is good reason for pursuing an alternative remedy. McDonald v Nillumbik SC, Studley Street Developments Pty Ltd v Yarra CC and Di Biase v Yarra Ranges SC not followed.
Part 4A of the Planning and Environment Act 1987 - certificates of compliance and declarations as means of establishing existing use rights - no basis to distinguish between remedies on basis of difficulty or complexity - certificate of compliance is preferred remedy - McDonald v Nillumbik SC, Studley Street Developments Pty Ltd v Yarra CC and Di Biase v Yarra Ranges SC not followed
Inglese v Yarra Ranges SC (Includes Summary) (Red Dot) [2014] VCAT 396
Mr Peter Merrigan, town planner, of Millar & Merrigan Pty Ltd
(4) The responsible authority must refuse to issue a certificate applied for under section 97N(1)(a) if the use or development or any part of the use or development would require a permit or is prohibited under the planning scheme.
The evidence/documentation supplied does not prove that a "contractors Depot" has been running on the land for more than 15 years.
(1) A person may apply to the Tribunal for a declaration concerning -
(a) any matter which may be the subject of an application to the Tribunal under this Act; or
(b) anything done by a responsible authority under this Act.
(2) On an application under subsection (1), the Tribunal may make any declaration it thinks appropriate in the circumstances.
149A Application by certain persons for declarations
(1) A specified person may apply to the Tribunal for the determination of a matter if -
(a) the matter relates to the interpretation of the planning scheme or a permit in relation to land or a particular use or development of land;
(b) the matter relates to whether section 6(3) applies to a particular use or development of land; or
(c) the matter relates to a provision of a planning scheme or amendment permitting the continuation of a use lawfully existing before the coming into operation of the planning scheme or amendment, or permitting the use of buildings or works for a purpose for which they were lawfully erected or carried out before the coming into operation of the planning scheme or amendment.
[7] On the one hand, there is previous Tribunal caselaw that 'existing use rights' disputes of this type should be resolved by way of an Application for Declaration to the Tribunal, rather than by way of a contested Section 97P application. See for example McDonald Mary v Nillumbik SC [2000] VCAT 772 and Logie HC&CM v Campaspe SC [1999] VCAT 431. On a very strict view, the Tribunal in theory could refuse this Application on this basis alone ie that this Application has been brought in the wrong manner. However in all the circumstances I consider that it would be overly harsh to take this course of action, particularly when Council has not seriously challenged this procedural point in the lead up to the hearing eg through a strike out application.
[8] However for future reference, I endorse that the Tribunal expects these types of disputes to be dealt with by way of an Application for Declaration.
If, in relation to an application or proceeding under the Act or this scheme, including an application for a certificate of compliance under Section 97N of the Act, the extent of any existing use right for a period in excess of 15 years is in question, it is sufficient proof of the establishment of the existing use right if the use has been carried out continuously for 15 years prior to the date of the application or proceeding.
An existing use right may be established under this clause even if the use did not comply with the scheme immediately prior to or during the 15 year period, unless either:
A Certificate is a statement about the effect of the planning scheme on the use or development on the land on the day it was issued.
(ke) subject to subsection (3), specify what effect (if any) the planning scheme will have on a use or development of land for which a permit or certificate of compliance has been issued;
[28] The Tribunal will not commonly make a declaration where other equivalent relief is available through a different form of proceeding. As will be seen, I have decided the application under s 97P favourably to the applicant. I therefore see no utility in granting the declaration sought under s 149A, and that second application is dismissed.
[1] Section 97O(5) relates to a proposed use or development, which in turn relates to an application for a certificate of compliance under section 97N(1)(b).
[3] For example, Egan v Boroondara CC [2004] VCAT 182
[5] Regulation 45 Planning and Environment Regulations 2005
[6] Form 14 Planning and Environment Regulations 2005
[7] Form 15 Planning and Environment Regulations 2005
[8] This provision was introduced into the Act by clause 4 of the Planning and Environment (Amendment) Act 1993. Clause 4, which also inserted sub-paragraphs (kc) and (kd) of section 6(2) of the Act, was referred to in the second reading speech of the Planning and Environment (Amendment) Bill 1993 in the context of addressing certificates of compliance.
[9] Section 200 Planning and Environment Act 1987
[13] [2005] VCAT 653 at [109]. See also Wellington v Surf Coast Shire Council & Ors [2011] VCAT 2317 at [24] - [25]
Inglese