[2000] VSC 415
Supreme Court of Victoria
2000-12-21
Gillard J
Original judgment source is linked above.
CONTRACT FOR PLANT HIRE - composition of contract - construction - entitlement to stand-by payment - counterclaim based on implied terms - implied terms of co-operation and acting in good faith do not oblige a party to agree to a variation of the agreement - counterclaim dismissed.
"We look forward to your early acceptance of the above to enable a final progress payment to be made."
(i) What comprised the contract of hire between the parties?
(ii) What were the terms of the contract concerning -
(a) the hire rates to be paid by Thiess to Howtrac;
(b) provision of tyres, tyre damage and truck repairs and responsibility for same.
(iii) Were there implied terms of the contract as alleged by Thiess to the effect -
(a) that each party would do all things as were necessary on its part to enable the other party to have the benefit of the agreement;
(b) that each party would comply with reasonable requests made by the other party;
(c) that each party was under a duty to act reasonably and in good faith in responding to requests made by the other party;
(d) that hungry boards would be fitted to each Cat 773B Dump Truck as required in order to meet its payload capacity?
(iv) What amount is due to Howtrac under the contract?
(v) If there were implied terms to the effect alleged by Thiess, did Howtrac breach any and which of the terms?
(vi) If Howtrac did breach any implied term did Thiess suffer any damage and if so in what amount?
Evidence
"Geoff, I hope this can conclude a hire agreement between the parties."
"Geoff, As discussed formal plant hire documents are currently being typed up. Will be faxed to you later this afternoon. The plant hire order for this work will be #83301 and the supply of the trucks is as per discussions between Greg Sparkman and yourself and outlined above."
"We trust the foregoing and attached schedule is to your satisfaction. Await your early reply in order that current shipping times can be met."
"Further to our discussion of 19/8/97 and 21/8/97 we confirm our agreement with Items 1 to 5 of your facsimile of 19/8/97."
"The existing bodies on your trucks do not carry a full pay load on the above mentioned project. Modifications are being carried out to increase the capacity of your trucks. Your on site fitter has been advised of our intended works. We have attached drawings and calculations for your information."
"Please note, that no modifications are to be carried out to the trucks without written authorisation from myself."
"If $100,000 payment is made today, then we have an agreement. Please leave a message with my office."
"Where you have to find your contract or your note or memorandum of the terms of the contract in letters you make take into consideration the whole of the correspondence which has passed. You must not at one particular time draw a line and say, 'We will look at the letters up to this point and find in them a contract or not, but we will look at nothing beyond'."
"In order that the time provisions of our offer can be maintained we will require your confirmation of the foregoing tonight. We are scheduled to leave for Japan early tomorrow and require that confirmation prior to departure."
"Further to our discussion of 19/8/97 and 21/8/97 we confirm our agreement with items 1 to 5 of your facsimile of 18/8/97. Regards, Mark Prater."
(i) the correspondence passing between the parties from 4 August 1997 up to and including the documents constituted by the Plant Hire Order form and attached documents also formed part of the written contract;
(ii) that there was an oral part of the contract constituted by alleged conversations between Messrs Sparkman and Howard between 1 - 6 August 1997;
(iii) that there were certain implied terms of the contract.
"In so far as it is oral it is constituted by conversations between Geoff Howard of the plaintiff and Greg Sparkman of the defendant during July and August 1997 to the effect as alleged."
"(a) The contract for the project may be extended from 52 weeks to 60 weeks in duration but the minimum 21,000 working hours would still apply to the 60 week period;
(b) In order to protect Howtrac's monthly cashflow Thiess would pay a minimum monthly payment of 200 hours per month;
(c) If the working hours were less than 200 hours per month then the balance up to 200 hours per month would be paid at a standing charge of $60 per hour;
(d) If the working hours in any month were greater than 200, any standby hours previously paid to make up the minimum requirement for previous months would be deducted from the working hours in excess of 200 to calculate the payment for that month;
(e) The entitlement at the end of the hire period would be determined by reference to total working hours with a minimum of 21,000 working hours."
"On the other hand, if one would nevertheless conclude from the background that something must have gone wrong with the language, the law does not require judges to attribute to the parties an intention which they plainly could not have had. Lord Diplock made this point more vigorously when he said in Antaiso Compania Naviera S.A. v Salen Rederierna A.B. (1985) A.C. 191 at 201: 'if detailed semantic and syntactical analysis of words in a commercial context is going to lead to a conclusion that flouts business common sense, it must be made to yield to business commonsense'
per Lord Hoffman in I.C.S. Ltd v West Bromwich B.S. (1998) 1 WLR at p.913.
See also Schenker & Co (Aust) Pty Ltd v Maplas Equipment and Services Pty Ltd [1990] VicRp 74; (1990) VR 834 at 837, 840 and 848.
"The meaning of words is a matter of dictionaries and grammars: the meaning of the document is what the parties using those words against the relevant background would reasonably have been understood to mean".
"Interpretation is the ascertainment of the meaning which the document would convey to a reasonable person having all the background knowledge which would reasonably have been available to the parties in the situation in which they were at the time of the contract" - ibid at p.912.
"The problem for a court of construction must always be so to balance matters that, without the violation of essential principle, the dealings of men may as far as possible be treated as effective, and that the law may not incur the reproach of being the destroyer of bargains".
"A theme that runs through our law of contract is that the reasonable expectations of honest men must be protected. It is not a rule or a principle of law. It is the objective which has been and still is the principal moulding force of our law of contract. It affords no licence to a judge to depart from binding precedent. On the other hand, if the prima facie solution to a problem runs counter to the reasonable expectations of honest men, this criterion sometimes requires a rigorous re-examination of the problem to ascertain whether the law does indeed compel demonstrable unfairness."
"The result has been subject to one important exception, to assimilate the way in which such documents are interpreted by judges to the common sense principles by which any serious utterance would be interpreted in ordinary life. Almost all the old intellectual baggage of 'legal' interpretation has been discarded."
"The true rule is that evidence of surrounding circumstances is admissible to assist in the interpretation of the contract if the language is ambiguous or susceptible of more than one meaning. But it is not admissible to contradict the language of the contract when it has a plain meaning. Generally speaking facts existing when the contract was made will not be receivable as part of the surrounding circumstances as an aid to construction, unless they were known to both parties, although, as we have seen, if the facts are notorious knowledge of them will be presumed. It is here that a difficulty arises with respect to the evidence of prior negotiations. Obviously the prior negotiations will tend to establish objective background facts which were known to both parties and the subject matter of the contract. To the extent to which they have this tendency they are admissible. But in so far as they consist of statements and actions of the parties which are reflective of their actual intentions and expectations they are not receivable. The point is that such statements and actions reveal the terms of the contract which the parties intended or hoped to make. They are superseded by, and merged in, the contract itself. The object of the parol evidence rule is to exclude them, the prior oral agreement of the parties being inadmissible in aid of construction, though admissible in an action for rectification." (Emphases added.)
"The background was famously referred to by Lord Wilberforce as 'the matrix of facts', but this phrase is, if anything, an understated description of what the background may include. Subject to the requirements that it should have been reasonably available to the parties and to the exception to be mentioned next, it includes absolutely anything which would have affected the way in which the language of the document would have been understood by reasonable men. The exception is exclusion of negotiation and declarations of subjective intent." (Emphases added.)
"What a man intends and the expression of his intention are two different things. He is bound, and those who take after him are bound, by his expressed intention." - see Simpson v Foxon (1907) P.54 at 57.
"Consequently when the issue is which of two or more possible meanings is to be given to a contractual provision we look, not to the actual intentions, aspirations or expectations of the parties before or at the time of the contract, except in so far as they are expressed in the contract, but to the objective framework of facts within which the contract came into existence, and to the parties' presumed intention in this setting. We do not take into account the actual intentions of the parties and for the very good reason that an investigation of those matters would not only be time consuming but it would also be unrewarding as it would tend to give too much weight to these factors at the expense of the actual language of the written contract."
"What the court must do must be to place itself in thought in the same factual matrix as that in which the parties were. All of these opinions seem to be implicitly to recognise that, in the search for the relevant background, there may be facts which form part of the circumstances in which the parties contract and in which one, or both, may take no particular interest, their minds being addressed to or concentrated on other facts so that if asked they would assert that they did not have those facts in the forefront of their mind, but that will not prevent those facts from forming part of an objective setting in which the contract is to be construed." (Emphasis added.)
"Far more, and indeed totally, dangerous it is to admit evidence of one party's objective - even if this is known to the other party. However strongly pursued this may be, the other party may only be willing to give it partial recognition, in a world of give and take, men often have to be satisfied with less than they want. So again, it would be a matter of speculation how far the common intention was that the particular objective should be realised." (Emphasis added.)
"If on the true construction of a contract a right is given to a party, that right is not diminished because during some period either the existence of the right or its full extent was not appreciated."
"The broad purpose of the parole evidence rule is to exclude extrinsic evidence (except as to surrounding circumstances) including direct statements of intention (except in cases of latent ambiguity) and antecedent negotiation, to subtract from, add to, vary or contradict the language of a written instrument."
"There comes a point at which the court should remind itself that the task is to discover what the parties meant from what they have said, and that to force upon the words a meaning which they cannot fairly bear is to substitute for the bargain actually made one which the court believes could better have been made. This is an illegitimate role for a court. Particularly in the field of commerce, where the parties need to know what they must do and what they can insist on not doing it, is essential for them to be confident that they can rely on the court to enforce their bargain according to its terms." Charter Reinsurance Co Ltd v Fagan (1997) AC 313 at 388. (Emphases added.)
"$95AUD/working hr (Keinzle measure) $60AUD/standby hr"
"In the event that a spare truck is placed on site to ensure high availability, the aggregate minimum hours guaranteed will remain unchanged, however the cost of establishment and disestablishment will be noted for the main trucks, set out in the special conditions attached hereto."
"6.3 No 'standby' rates of hire shall be payable by the hirer unless specified in this order."
"Standby rates do not apply for industrial disputes, wet weather, force majeure or breakdowns."
"The point is that such statements and actions reveal the terms of the contract which the parties intended or hoped to make. They are superseded by, and merged in, the contract itself."
"To simplify the operating conditions clause may I recommend using a standing and operating cost as set out below based on a 4,000 hour projected use of each unit with a guaranteed minimum of say, 3,500 hours subject to mechanical availability of your plant. We would expect an availability in excess of 95% over the duration of the hire period."
"Our offer requires that Howtrac rentals be reimbursed each month for the hours worked or the minimum hours, whichever is the greater, subject only to: * A continuing monthly adjustment of the hours worked against the hours measured as standby. At the conclusion of the hire period of 14 months, all adjustments will have to be carried out and Thiess will have received the benefit of any standby hours and Howtrac rentals receive any benefit of working hours in excess of the guaranteed minimum. * All monthly payments for hours worked or standby hours that make up the minimum monthly total will be paid at the quoted rate of $95 per hour." (Emphasis added.)
"The agreed procedure for payment is based on a minimum monthly hourly usage, adjusted each month for idle time. The parties have agreed that providing Howtrac Rentals is paid the minimum 3,500 hours per unit, then idle time beyond that figure will not be charged. Conversely, if the total working hours exceed this minimum figure then Howtrac Rentals will be paid in accordance with the agreed hourly rate."
"Standby will only be paid as an interim payment for your cashflow consistency when a total of 1500 hours are not worked during any one month. Standby will be paid to make up any shortfall in the 1,500 hours and will be deducted in the preceding months when the 1,500 hours are exceeded."
"We confirm our verbal advice that the claims from our CAT 773B truck supplier, Howtrac, for standby hours have been paid at $60AUD. Our claim was submitted at $95AUD and that is the figure that our sub-contractor believes he is entitled to be reimbursed at. As discussed, we are currently in dispute with our sub-contractor on various items relating to the truck supply, the appropriate standby rate being one. Our claim was submitted at $95 per hour as this is what our sub-contractor realistically expects to be paid for standby hours. As we have an expectation that we will pay him something less than $95 per hour we have not claimed any costs for labour, which could not be effectively utilised in the January/February period. In consideration that we have absorbed the labour costs and accepted the Howtrac risk, we request you to accept payment of this labour item in full." The underlined parts are arguably fraudulent. At no stage did Howtrac seek to claim $95 per hour for standby.
"Revised Claim Amount per letter of 16 April 1998. (a) Reduction in Howtrac claims to amounts actually paid on January and February invoices." (Emphasis added.)
"It is clear that any civilised system of law is bound to provide remedies for cases of what is being called unjust enrichment or unjust in benefit, that is, to prevent a man from retaining the money of, or some benefit derived from, another which it is against conscience that he should keep. Such remedies in English law are generically different from remedies in contract or in tort, and are now recognised to fall within a third category of the common law which has been called quasi-contract or restitution."
"In any case, so long as the contract continued on foot, it governed the relations between the parties and there is no basis in these circumstances for an appeal to the law of quasi-contract."
"We confirm our agreement to pay for reasonable (less than $5,000) costs incurred by yourselves in advancing the hungry board issue to resolution."
"Damage to plant caused by operator error that is not covered by insurance to be at Thiess cost."
"As per summary subject only to approval of the insurance claim noted."
"Subject to the matter of insurance for truck 3189 and the satisfactory completion by Thiess for the repairs of 3191, we will accept the sum of $34,477 to cover all repairs invoice to Thiess by Howtrac and Howtrac will be responsible to effect those repairs."
"Hungry Boards Our offer for settlement of this issue was $5,000AUD. This is reasonable and adequately compensates Howtrac for its Actual costs in pursuing this issue."
"We stand by our previous offer for settlement of this issue ($5,000AUD) which was more than reasonable given the less than enthusiastic nature Howtrac displayed in assisting Thiess with this issue."
"We look forward to your early acceptance of the above to enable a final progress payment to be made."
"We further note that Thiess Contractors (NZ) Limited has shown remarkable restraint to this point in not choosing not to pursue Howtrac for the full impact of its failure to perform in accordance with the contract we cite: * Unavailable hours well in excess of the 800 offered as settlement of minimum hours. * Delay in contract completion and corresponding additional costs resulting from the large amount of unavailable hours. * Additional operational costs through mismatched/undersigned fleets. * Other costs noted or implied in various items of contract correspondence."
" ... The judicial function can, I believe be epitomised as an educated reflex to the facts."
"17A. Further or alternatively, there were implied terms of the agreement that:
(a) each party agreed to do all such things as were necessary on its part to enable the other party to have the benefit of the agreement;
(b) each party would comply with reasonable requests made by the other party;
(c) each party was under a duty to act reasonably and in good faith in responding to requests made by the other party;
(d) Hungry Boards would be fitted to each Cat 773B dump truck as required in order to meet its payload capacity.
PARTICULARS
The terms pleaded in sub-paragraphs (a) and (b) were implied by law.
The term pleaded in sub-paragraph (c) is implied by law and to give business efficacy to the agreement.
The term pleaded in sub-paragraph (d) was implied by custom and usage in the civil engineering industry and to give business efficacy to the Agreement."
"Their Lordships do not think it necessary to review exhaustively the authorities on the implication of a term in a contract which the parties have not thought fit to express. In their view, for a term to be implied, the following conditions (which may overlap) must be satisfied: (1) it must be reasonable and equitable; (2) it must be necessary to give business efficacy to the contract so that no term will be implied if the contract is effective with out; (3) it must be so obvious that it 'goes without saying'; (4) it must be capable of clear expression; (5) it must not contradict any express term of the contract."
"(1) The existence of a custom or usage that will justify the implication of a term into a contract is a question of fact;
(2) There must be evidence that the custom relied on is so well known and acquiesced in that everyone making a contract in that situation can reasonably be presumed to have imported that term into the contract;
However, it is not necessary that the custom be universally accepted, for such a requirement would always be defeated by the denial by one litigant.
(3) A term will not be implied into a contract on the basis of custom where it is contrary to the express terms of the agreement;
(4) A person may be bound by custom notwithstanding the fact that he had no knowledge of it."
"In matters of this kind, that phrase means no more than that the general notoriety of the custom makes it reasonable to assume that the parties contracted on the basis of the custom, and that it is therefore reasonable to import such a term into the contract."
"It is not for a witness, but for the court, to say whether the article should be properly included under the statutory designation. It is not a matter of scientific or trade opinion whether they ought to be so included. Trade usage and commercial appellation are matters of actual fact and the evidence properly admissible on such a head is as to what merchants and others did at the date of the act in fact call such articles."
"I think I may safely say, as a general rule, that where in a written contract it appears that both parties have agreed that something shall be done, which cannot effectually be done unless both concur in doing it, the construction of the contract is that each agrees to do all that is necessary to be done on his part for the carrying out of that thing, though there may be no express words to that effect."
Quoted with approval in Electronic Industries Ltd v David Jones Ltd [1954] HCA 69; (1954) 91 CLR 288 at 297.
I certify that this and the 75 preceding pages are a true copy of the reasons for judgment of Gillard J of the Supreme Court of Victoria delivered on 21 December 2000.
Howtrac Rentals Pty Ltd
Thiess Contractors
(1907) 5 CLR 68
(1994) 2 VR 106
(1985) 2 NSWLR 309
(1982) 149 CLR 337
(1993) 2 VR 34
(1996) 2 VR 235
(1987) 162 CLR 221
(1977) 2 NSWLR 880
(1989) 168 CLR 385
(1997) 180 CLR 266
(1995) 185 CLR 410
(1915) 20 CLR 118
(1979) 144 CLR 596
(1954) 91 CLR 288
(1998) 44 NSWLR 349