HEADNOTE
[This headnote is not to be read as part of the judgment]
The first and second appellants, Mr Housman and Ms Alda, own harbourside land at Lavender Bay. The respondent, Ms Camuglia, owns neighbouring land, on which is constructed a building containing six apartment units. Ms Housman and Ms Alda engaged the third appellant, Pacific Plus Constructions Pty Ltd to undertake substantial building and construction works, including excavation works, on their land. The works caused damage to Ms Camuglia's land; in particular, the supporting foundations for a stairway providing access to four of the units had collapsed and the stairway showed signs of cracking and settlement. Temporary propping was installed to restore access to the stairway. An engineering report indicated that the temporary measures were adequate to ensure the safety of the stairway until a permanent solution was implemented. Notwithstanding the temporary propping, Ms Camuglia's leasing manager, Mr D'Ettorre, advised her that the property was incapable of being advertised to let.
Ms Camuglia commenced proceedings in the District Court of New South Wales seeking damages for, inter alia, negligence. The primary judge entered judgment for Ms Camuglia in the amount of $231,316.32, comprising $74,076.18 in respect of rectification costs and $157,240.14 for consequential loss relating to lost rent. It emerged that an offer by Ms Camuglia that the proceedings be discontinued on the basis that each party bear their own costs and the defendants/appellants pay Ms Camuglia lump sums of $100,000 in respect of the proceedings and $100,000 in respect of costs was refused. The primary judge ordered costs in Ms Camuglia's favour on an ordinary basis to 7 September 2019 and thereafter on an indemnity basis.
The principal issues on appeal were:
1. Whether the primary judge erred in finding that the damage caused by the building and construction works had caused the units to be unlettable, such that damages for consequential loss should not have been awarded;
2. Whether the primary judge failed properly to assess whether it had been unreasonable for the appellants to reject the Calderbank offer made by Ms Camuglia, such that a special costs order should not have been made in her favour. An associated issue was whether leave to appeal was required in respect of this ground.
The Court held (Leeming JA, Bell P and White JA agreeing), dismissing the appeal:
- It was not unreasonable for Ms Camuglia to await the construction of a permanent solution to access before re-letting the premises, notwithstanding the indication in Mr Herbertson's engineering report that the temporary solution was adequate in terms of safety: at [1]; [36]-[40]; [95].
a. A permanent solution was reasonably expected in the short term and there would be a need for a prospective tenant's furniture and other possessions to be delivered to the premises: at [1]; [36]; [95].
b. The opinion of Ms Camuglia's leasing agent that the property was incapable of being advertised to let was inherently plausible, as the obstacles to access, if disclosed in advertising material, might have made the apartments unappealing to prospective tenants, and if not disclosed, might have caused irritation upon inspection: at [1]; [37]; [95].
c. Ms Camuglia's and Mr D'Ettorre's evidence, which had been subject to rulings restricting use, had not been misused, as it was those witnesses' perceptions of the position as to the stairway that were critical, not whether, from an engineering perspective, the stairway had in fact been unsafe: [1]; [39]; [95].
Inutility of adequacy of reasons as a ground of appeal where an appeal proceeds by way of rehearing discussed: at [33]-[35].
Capilano Honey Ltd v Dowling (No 2) [2018] NSWCA 217; Stephenson v Santos [2020] NSWCA 262 referred to.
Relationship between causation and failure to mitigate loss discussed: at [41].
Bunge SA v Nidera BV [2015] UKSC 43; 3 All ER 1082 referred to.
- Leave to appeal against the special costs order was not required: at [1]; [84]; [95]. Where there is a substantive ground of appeal as of right, then even if that ground fails, the appellant may challenge the costs order as of right: at [1]; [83]; [95]. An appeal raising bona fide substantive grounds as well as costs is not an appeal "as to costs only" within the meaning of s 127(2) of the District Court Act 1973 (NSW) or s 101(2)(c) of the Supreme Court Act 1970 (NSW), even if the substantive grounds are rejected: at [1]; [84]; [95].
History of s 127(2) of the District Court Act 1973 (NSW) and s 101(2)(c) of the Supreme Court Act 1970 (NSW) and United Kingdom antecedents discussed: at [46]-[83].
Harris v Aaron (1877) 4 Ch D 749; Harpham v Shacklock (1881) 19 Ch D 207; Robinson v Sutton (1909) 9 SR (NSW) 295 referred to.
Road Chalets Pty Ltd v Thornton Motors Pty Ltd (1986) 47 SASR 532 considered.
Wheeler v Somerfield [1966] 2 QB 94; Dillon v Gosford City Council [2011] NSWCA 328; 284 ALR 619 applied.
- No basis on which to re-exercise the discretion as to costs was made out: at [1]; [90]; [95].
a. The fact that Ms Camuglia's costs were now shown to be some $113,696.10 rather than the $150,000 which had been represented to be Ms Camuglia's costs at the time the offer was made did not materially detract from the substantiality of the compromise when viewed as a whole: at [1]; [90]; [95].
b. The fact that Mr D'Ettorre's affidavits had not been served when the offer was made was not material in circumstances where the essential case advanced by Ms Camuglia was available to the defendants at the time they reviewed the offer: at [1]; [92]; [95].