JUDGMENT
- These proceedings arise following an application to the Court under s 4.55(8) of the Environmental Planning and Assessment Act 1979 (EPA Act) to modify development consent DA30/2021 granted by the Court on 28 October 2021 in Hillcrest Rose Bay Pty Ltd v Woollahra Municipal Council [2021] NSWLEC 1662.
- The application proposes works to the approved ground floor unit of the existing residential flat building at 780-786 New South Head Road, Rose Bay to revert it back to a dual unit arrangement, add a private gym and pool terrace in the area above the approved basement, and to reconfigure the existing car park to accommodate changes due to service requirements.
- The Court arranged a conciliation conference under s 34(1) of the Land and Environment Court Act 1979 (LEC Act) between the parties, which was held on 26 April 2024. I presided over the conciliation conference.
- During that process, the Council approved, pursuant to s 113(1) of the Environmental Planning and Assessment Regulation 2021 (EPA Reg), the applicant amending the modification application to address the contentions raised in the Council's Statement of Facts and Contentions. The documents comprising the amended modification application are set out in the table below and were filed with the Court on 14 June 2024. Tab 1. Architectural plans Drawing Number Plan name Date Revision Prepared By DA000 Cover Sheet 1 May 2024 G Woods Bagot DA001 Project Summary 1 May 2024 F Woods Bagot A DA102 Basement Level B1 1 May 2024 G Woods Bagot DA103 Lower Ground Floor Plan 1 May 2024 G Woods Bagot DA104.2 Ground Level 1 May 2024 G Woods Bagot DA105 Level 01 1 May 2024 G Woods Bagot DA106 Level 02 1 May 2024 G Woods Bagot DA107 Roof Plan 1 May 2024 G Woods Bagot DA201 Elevations - East and North 1 May 2024 G Woods Bagot DA202 Elevations - West and South 1 May 2024 G Woods Bagot DA301 Section A 1 May 2024 F Woods Bagot DA302 Section B 1 May 2024 F Woods Bagot DA520 FSR Diagram 1 May 2024 F Woods Bagot DA550 Private Open Space _ Natural Ventilation Diagram 1 May 2024 F Woods Bagot DA560 Storage Diagram 1 May 2024 F Woods Bagot Tab 2. Stormwater plans Drawing Number Plan name Date Revision Prepared By C-01 Cover Sheet 3 April 2024 E Enscape Studio C-05 Sediment & Erosion Control Plan & Details 27 February 2024 D Enscape Studio C-10 Stormwater Management Plan - Basement 1 3 April 2024 F Enscape Studio C-11 Stormwater Management Plan - Lower Ground 3 April 2024 H Enscape Studio C-12 Stormwater Management Plan - Ground 29 February 2024 F Enscape Studio C-15 Stormwater Management Details 3 April 2024 F Enscape Studio Tab 3. S138 Civil Engineering Works Drawing Number Plan name Date Issue Prepared By C-00 Cover Sheet 7 March 2024 B Enscape Studio C-20 Street Frontage Plan & Driveway Cross Sections 14 March 2024 G Enscape Studio C-21 Southern Footpath Works 22 November 2023 A Enscape Studio C-24 Public Footpath Long Section 5 February 2024 A Enscape Studio C-25 Stormwater Connection Details 8 November 2023 A Enscape Studio C-26 Public Domain Details - Sheet 1 2 May 2024 D Enscape Studio C-27 Public domain Details - Sheet 2 3 April 2024 C Enscape Studio C-28 Public Domain Details - Sheet 3 3 April 2024 A Enscape Studio Other documents Description Date Tab 4. Schedule of amendments prepared by Woods Bagot undated Tab 5. Response to contentions re ceiling cornices prepared by Architectural Projects (with enclosures). 4 March 2024