[2025] VCAT 815
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2025-09-17
Original judgment source is linked above.
Will the demolition of the building adversely affect the significance of the heritage place?
I am of the option that even if the Kelly Park Centre had formally recognised historical and social value, it would not likely meet the threshold for aesthetic significance and therefore demolition with the conditions of archival recording, the development of an interpretation strategy and a more appropriate replacement building would be an appropriate planning response.[7]
I do not believe that the Kelly Centre would meet the threshold for architectural or aesthetic significance, or that potential social significance of the Kelly Park Centre would be so significant that it would override the cultural heritage significance of the broader Kelly Park precinct.
In keeping with article 15.4 of the Burra Charter, emphasising the landscape and aesthetic significance of Kelly Park, and interpreting the potential historical and social significance of the Kelly Park Centre could be justified as the building fabric is of potential slight (or no) cultural heritage significance, and that which is conserved and interpreted (the landscape elements and social history respectively) is of much greater cultural significance.
Will the demolition lead to an adverse impact on trees protected under HO16?
Will the proposal conserve and enhance the heritage place HO16?
Loss of a community service and social impact
There were over 50 objections lodged to the application. These objections were, as we understand it, overwhelmingly from users (and former users) of the Hall, who made arguments about the significant social effects of losing important community infrastructure.
The SEMP must be in accordance with Council's SEMP template and guidelines. The approved SEMP must be implemented at all times to the satisfaction of the Responsible Authority. Any non-compliance may be enforced under the Planning and Environment Act and other related legislation.
Access to the site must be available at all times for Council representatives to monitor implementation of the SEMP.
The SEMP applies for all works approved in this Permit up to the completion of all works to the satisfaction of the responsible authority.
(a) Prior to commencement of works, contractors must be inducted into the SEMP and all flora and fauna conservation requirements.
(b) Prior to commencement of works, the works zone must be enclosed by secure and obvious temporary fencing. The work zone fence must remain in place until works are completed. Fill, machinery and building materials must not be placed outside of the works zone.
(c) All litter and building waste must be contained on the site and must not be allowed to leave the site until the time it is correctly disposed of.
(d) All works must be undertaken in a manner that adheres to the Civil construction building and demolition guide (EPA publication 1834.2 September 2025) or updated version.
(e) Any construction stockpiles, fill and machinery must be placed away from areas supporting native vegetation and drainage lines to the satisfaction of the responsible authority.
(f) Noxious weeds and serious threat environmental weeds must be controlled. Any weed infestations resulting from soil disturbance and/or the importation of sand, gravel and other material used in the construction process must be controlled. Weed control must be at no cost to and to the satisfaction of the responsible authority.
(a) The development is not started within two (2) years of the date of this permit;
(b) The development is not completed within four (4) years of the date of this permit.
The responsible authority may extend the periods referred to if a request is made in writing whereby either of the following instances apply:
(a) before or within six (6) months after the permit expiry date, where the use or development allowed by the permit has not yet started; or
(b) within twelve (12) months after the permit expiry date, where the proposal allowed by the permit has lawfully started before the permit expires.
[1] Returned and Services League of Australia.
[2] The submissions and evidence of the parties, any supporting exhibits given at the hearing and the statements of grounds filed have all been considered in the determination of the proceeding. In accordance with the practice of VCAT, not all of this material will be cited or referred to in these reasons.
[6] Extent Heritage Pty Ltd, Kelly Park Heritage Impact Statement 25 March 2024: Page 18.
Heinrichs
Wyndham CC [2025] VCAT 815