[2024] ACTMC 13
Magistrates' Court of the ACT
2024-07-26
Magistrate Theakston
Original judgment source is linked above.
(a) Is the builder liable to compensate the owners for missing out on the homeowners' grant of $25,000?
(b) Did the builder complete the building works up to the painting stage?
(c) Were the building works deemed to have reached practical completion?
(d) What is the consequence of practical completion?
(e) Was the builder prevented from completing the building works?
(f) Do the liquidated damages provisions of the contract for delay apply in these circumstances?
(g) What are the losses suffered by the builder, including do they include the amount claimed on the variation?
(h) What are the losses suffered by the owners?
Is the builder liable to compensate the owners for missing out on the homeowners' grant of $25,000?
(a) in November 2020, the parties entered a preliminary agreement to build the home, and the owners applied for the ACT Home Builder Grant;
(b) in January 2021, the ACT Revenue Office refused the grant because the builder was not licenced as at a date in November 2020; and
(c) in January 2021, Mr Moustafa and an agent of the builder met and agreed that the builder would compensate the owner for that loss.
We'll lower the price by $25,000 and that way, you won't be out of pocket.
Did the builder complete the building works up to the painting stage?
(a) garbage throughout the premises,
(b) water leaking damage in the garage, kitchen, laundry, bedrooms and the second-floor ceiling,
(c) missing joinery to the kitchen, pantry and laundry areas,
(d) missing door handles and doors,
(e) missing electrical work,
(f) missing carpet in the bedrooms, and
(g) missing handrails to the staircase in the garage.
So when we say the substantial, it's not - we have to finish all the painting and then we start the second stage. So they are depending, like I explained, joinery thing. Joinery was installed. Doors was not and that was an invoice before painting which we advised, they inspect, they agree and they paid. Then we started the painting. Now, painting, when the main paint is done, then we put the joinery and then we do the touch-up if we need to do and - and before we hand over. If even they find out that this thing is not right at this stage, we fix that as well, and then the certifier come and inspect the property, and if they happy that, yes, all the stages are complete, then they issue a ... (inaudible) ... On the base of that we apply for the last invoice
Painting wise, I can see that, yes, it mightn't be a wise idea to sort of paint everything all at once, right, but if it's the painting stage, right, then I would expect that, yes, it would have two coats, or the three coat, whatever's finished, to complete the stage, right. But you are going to mess it up, right, put stuff in that you're going to scuff and knock and bash and whatever. Tradesmen are tradesmen, right. And so you're going to have to have a little bit of an allowance that this stage is not the completion of the work, it's the completion of this stage.
But before the cupboards are in, you need to have the stage finished. ... So you want to have all the paint - because when the cupboards are in, you can't go in and repaint everything where the edge of the cupboard is, because you can't go down the side. It's got to be finished, right.
(a) gyprock missing at various locations, including where masonry, heating or cooling appliances and ducting protruded into the living space, and where no framing or bulkheads were installed to secure the gyprock around those protrusions;
(b) a pedestrian door frame with exposed and protruding foam and without the architrave fitted and painted;
(c) missing external cladding adjacent to windows;
(d) front door not installed;
(e) missing external ceiling cornices;
(f) missing external tiles;
(g) missing balustrade and carpet on stairs;
(h) missing lights and electrical fittings, including associated electrical wiring behind gyprock;
(i) missing joinery, toilets and taps in the bathrooms and ensuite;
(j) no carpet in the house;
(k) unrepaired water leak damage;
(l) incomplete joinery in the kitchen, pantry and laundry, including missing bench tops, doors, drawers, sinks, plumbing fittings, tiles and appliances;
(m) top surfaces of internal doors not painted;
(n) missing balustrade and incomplete tiling on balcony;
(o) missing window flashing;
(p) missing guttering and down pipes;
(q) missing eave sheeting;
(r) water tanks not installed;
(s) power boards and air conditioning not installed; and
(t) electrical power not connected.
Were the building works deemed to have reached practical completion?
If the Owner possesses or uses the Works or any part of them without the written agreement of the Builder, the date of practical completion is the date of possession or use, unless Practical Completion has already been reached.
the building and construction work being undertaken by the Builder pursuant to this contract, as described in the terms of the Contract, the Specifications and Approved Plans or as varied under the Contract.
The builder and/or their sub-contractors are not permitted to enter, or do any work, at the owners' work site during the dispute resolution period.
The builder can still access the site if they want to proceed with the incomplete and defective works in the previous and painting stages.
What is the consequence of practical completion?
(a) painting stage - $63,750,
(b) practical completion - $21,250, and
(c) any other money payable under the contract, including any variation or actual cost provided under the contract.
The significant consequences of this is that Practical Completion has been reached and our client is entitled to receive the unpaid balance of the Contract Sum together with all other money payable under the Contract including interest of 20% per annum on late payments: clause 25a. of the Contract.
F. The Owners failed, refused or neglected to pay the Progress Claim within 10 business days after service of the written claim and following Practical Completion. > > ... > > EE. By Clause 25(a) of the Contract, on Practical Completion, the Builder is entitled to receive the unpaid balance of the Contract Sum together with any other money which is payable under the Contract. > > FF. The Owner has failed, refused or neglected to pay the Builder the unpaid balance of the Contract Sum together with other money which is payable under the Contract. > > NOW TAKE NOTICE
... > > IV. not paying the Builder the unpaid balance of the Contract Sum together the (sic) other money which is payable under the Contract in accordance with clause 24f. of the Contract
To be clear, our client: > > a. claims the sum of at least $103,527.50 plus interest in accordance with the Contract;
Was the builder prevented from completing the building works?
Do the liquidated damages provisions of the contract for delay apply in these circumstances?
What are the losses suffered by the builder, including do they include the amount claimed on the variation?
(a) painting stage - $63,750, plus
(b) practical completion - $21,250, plus
(c) any other money payable under the contract, including any variation or actual cost provided under the contract; minus
(d) liquidated damages for delay - $9,028;
We say, 'Project going to get delayed. We have to wait a long to get the framing, timber framing or we go for the steel framing,' and they say, 'So what that mean?' I say, 'If you go for the steel framing, it's expensive. It's a back-up order but it expensive, otherwise we have to wait for the timber and they - if you pay 50 per cent of the cost,' I suppose, by example, I'm just making a figure, if it a $30,000 extra to have a steel frame as compared with the timber, so we, 'Okay, you pay 15, we will put the 15,' so we agreed. And that's the kind of obligation he give me. He agree and then he say, 'Okay, I don't have the money but I will pay you in part.' So we took the 50 per cent of the burden and they took the 50 per cent of burden moving from timber to the steel frame, but they agreed with that, 'Okay, just go for the steel. Better product. Okay, we will pay that 50 per cent extra.' (Emphasis added)
a. The Owner may, without affecting the Owner's other rights, by written notice served on the Builder, terminate this Contract if the Builder: > > ... > > iii. without reasonable cause wholly suspends the carrying out of the Works before Practical Completion; or ... > > ... > > c. If the Owner so terminates this Contract, the Owner may engage another person to carry out the Works and: > > i. if the reasonable cost of the works exceeds that which would have been otherwise payable under this Contract, then the amount of that excess is a debt due and payable by the Builder to the Owner; > > ii. if the reasonable costs of the Works is less than that which would have been otherwise payable under this Contract, then the difference is a debt due and payable by the Owner to the Builder. > > d. The Owner may not terminate this Contract if the Owner is in breach of it.
I certify that the preceding seventy-nine [79] numbered paragraphs are a true copy of the Reasons for Decision of his Honour Magistrate Theakston
Heaven Builders Pty Ltd
Moustafa & Anor
Codelfa Construction Pty Ltd v State Rail Authority (NSW) [1982] HCA 24
Hera Project Pty Ltd v Bisognin (No 3) [2017] VSC 268
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd [2015] HCA 37
Wilkie v Gordian Runoff Ltd [2005] HCA 17
(1982) 149 CLR 337