[2021] TASSC 7
General information, not legal advice.
Supreme Court of Tasmania
2021-03-03
Brett J
Original judgment source is linked above.
CITATION: Hansen Yuncken Pty Ltd v Parliament Square Hobart
Landowner Pty Ltd [2021] TASSC 7
Contracts - Contracts - Building, engineering and related contracts - The contract - Construction of particular contracts and implied conditions - Security and retention funds - Whether the principal can have recourse to a bond which is constituted by an unconditional bank guarantee without notice to the builder - Certification of liquidated damages by sub-independent certifier - Whether valid - Whether builder required to pay damages so certified on a provisional basis.
Woodhall Ltd v Pipeline Authority [1979] HCA 21; (1979) 141 CLR 443; Fletcher Construction Australia Ltd v Varnsdorf Pty Ltd [1998] 3 VR 812 (Vict CA); Bachmann Pty Ltd v BHP Power New Zealand Ltd [1998] VSCA 40; [1999] 1 VR 420; Clough Engineering Ltd v Oil and Natural Gas Corporation Ltd [2008] FCAFC 136, 249 ALR 458; Electricity Generation Corporation v Woodside Energy Ltd [2014] HCA 7, 251 CLR 640; Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd [2015] HCA 37; 256 CLR 104; JKC Australia LNG Pty Ltd v CH2M Hill Companies Ltd [No 2] [2020] WASCA 112, referred to.
Second Defendant: Colin Biggers and Paisley Lawyers
Judgment Number: [2021] TASSC 7
(a) The payment of $3,330,000 by way of liquidated damages, as already described.
(b) The payment of $578,033.53 alleged as overpayments arising from variations to the work.
(c) The payment of $93,240 as liquidated damages arising from a shortfall in the minimum lettable area achieved on completion of the contract.
(d) The payment of $723,655.47 being asserted over-payments in respect of fit out works.
(a) A declaration that the first defendant has no present entitlement to have recourse to or draw down the defects bond, and an injunction restraining it from doing so in order to satisfy any of the claims set out above.
(b) Declarations that the second defendant did not have power to make the determination in respect of liquidated damages, and declaring the determination void.
(a) The first defendant's right to call upon the defects bond.
(b) Whether the second defendant certified the payment of liquidated damages in accordance with the contract.
(c) Whether cl 76.8(g)(ii) of the contract requires the plaintiff to pay the sum certified by the second defendant, notwithstanding any dispute in relation to such certification, including any dispute within the plaintiff's Type 1 notice of dispute dated 6 July 2020, or in the plaintiff's reply and defence to the counterclaim.
(a) The question of the principal's right to call upon such security is ultimately a matter of construction of the contract. That construction will be informed by and require consideration of the commercial purpose of the guarantee. The courts have recognised the commercial reasons for the provision of a performance guarantee. As summarised by the Full Court of the Federal Court in Clough: "One is to provide security for a valid claim against the contractor. The second, which is additional to the first, is to allocate the risk between the parties as to who shall be out of pocket pending the resolution of the dispute between them." In a case in which the guarantee is intended to allocate risk, it would generally be understood that the purpose is to ensure that the party benefiting from the guarantee is not out of pocket pending the resolution of the dispute.
(b) A further principle of construction is that the contract should be read as a whole. The effect of this is that where, as in this case, the form of the performance guarantee is set out in the contract, that must be taken into account in construction. In Fletcher Constructions (above), the Victorian Court of Appeal was concerned with the interpretation of a clause which provided for the principal to draw on standby letters of credit in the event of an unsatisfied demand for payment of pre-assessed damages relating to delay on the part of the builder. The builder argued that the proper meaning of the contract was that resort could only be had to the security if the entitlement to the damages was undisputed. Charles JA considered that the "critical question" was whether the commercial purpose of the provision of the letters of credit was limited to the provision of security for the builder's obligations, or whether it was to make provision for the allocation of risk between the parties pending resolution of any dispute. If the latter, then his Honour took the view that the principal would be entitled to have recourse to the security notwithstanding the existence of genuine dispute. In resolving this question, his Honour considered that the form of the undertaking was a significant matter. His Honour said:
"It is, I think, of great importance that Varnsdorf's right to the security which is to be provided under cl 6.6 and the Schedule of Contract Information, is in a form approved by Varnsdorf and 'in the form of an unconditional undertaking to pay in favour of' Varnsdorf. Hudson on Building and Engineering Contracts (para 17,075) asserts that:
'Insofar as a construction contract may make clear provision for the furnishing of an unconditional guarantee as security for due performance, the normal interpretation, ... will be that, in response to the stipulated demand, an unqualified transfer of the sums in question is intended, provided only that there is a bona fide dispute or claim on the secured party's part, and that any further investigation of its merits or extent is not usually intended by the contract."
Callaway JA took a similar view, and the remaining judge, Batt JA, agreed with both.
The agreed nature of the security was also considered to be an important matter in Woodhall. Stephen J observed that the incorporation of a guarantee which provided for payment upon demand without qualification was "as good as cash".
(c) In JKC Australia LNG Pty Ltd v CH2M Hill Companies Ltd [No 2] [2020] WASCA 112, the Western Australian Court of Appeal summarised the proper approach to the determination of whether a performance guarantee operates for the purpose of risk allocation at [82] as follows:
"2 The court should not too readily favour a construction which is inconsistent with an agreed allocation of risk as to who is to be out of pocket pending resolution of a dispute. However, whether an instrument has a purpose of allocating risk pending determination of a dispute cannot be assumed. It is to be identified as a matter of contractual construction. The description 'risk allocation device' expresses a process of conclusion after the process of construction has been worked through.
(d) In a case where on the proper construction of the contract, the performance guarantee fulfils the function of risk allocation, and is facilitated by an undertaking on the part of the third party which is unconditional and irrevocable, the court will not prevent access to the security by the benefiting party, except:
(ii) in order to prevent unconscionable conduct on the part of the benefiting party, or
(iii) where to do so would contravene a negative stipulation contained in the contract. It is accepted that the negative stipulation can be express or implied.
(e) The cases have generally accepted that a precondition of recourse to the security is that there must be a bona fide dispute on foot. This seems to be simply another way of saying that the party benefiting from the guarantee must not act fraudulently or unconscionably.
"1 The rights and liabilities of parties under a provision of a contract are determined objectively by reference to its text, context (the entire text of the contract) and purpose.
(a) a Bank Guarantee in the amount of 5% of the Contract Sum; and
(b) a [sic] insurance bond in the amount of 2.5% of the Contract Sum."
"Defects Bonds means a Bank Guarantee in the amount of 2.5% of the Contract Sum."
"Bank Guarantee means an irrevocable, unconditional guarantee:
(a) given by one of the four major Australian banks;
(i) as defined in the Banking Act 1959 (Cth):
(b) enforceable in Australia on presentation in Hobart; and
(c) in the form set out in Schedule 4 or such other form as the Principal agrees to in writing from time to time."
(a) The Performance Bond that consists of the insurance bond of 2.5% of the Contract Sum will be returned to the Contractor within 5 Business Days of the issue [sic] the Certificate of Stage Practical Completion.
(b) The Performance Bond that consists of the Bank Guarantee of 5% of the Contract Sum will be exchanged for the Defects Bond within 5 Business Days of the Contractor's compliance with clause 36.4(g).
(c) Subject to paragraph (c) below, the Defects Bond will be returned within 5 Business Days of the issue of a certificate under clause 68.4
(d) If the Defects Liability Period is extended more than 12 months in relation to any works to make good an omission or defect in the Works, at the expiry of the original Defects Liability period the Contractor may replace the Defects Bond with a Bank Guarantee for the value of the cost of rectifying those works that are subject to the extended Defects Liability Period (that value as determined by the Sub-Independent Certifier)."
If a Default Event has occurred and the Default Event is:
(a) capable of being remedied and is not remedied by the Contractor to the Principal's satisfaction (which may include the payment of compensation) within the Remedy Period;
the Principal may (in addition to any other Rights under this Deed, any other Project Document or at Law) do any, or a combination of any of, the following:
(e) subject to clause 6, have recourse to any or all of the Performance Bonds and the Defects Bonds for the purpose of paying to the Principal any Performance Bond Secured Amounts;
(b) The first defendant must serve a default notice on the plaintiff.
(c) The plaintiff then has 15 business days in which to remedy the default event specified in the notice.
(d) The plaintiff must fail to remedy the default to the first defendant's satisfaction during that period.
"A moment's reflection will show that the beneficiary, unlike the bank, may be restrained if there is an express prohibition in the underlying contract against calling upon the guarantee. In theory an implicit or implied prohibition is just as good. The practical problem is that it is much harder to establish. That is not because of a requirement that an implicit or implied prohibition against calling upon a guarantee must be clear. It is because the implication cannot be made if it would stultify, or even if it would be inconsistent with, the purpose for which the guarantee was taken.
I should explain the sense in which I am speaking of express, implicit and implied prohibitions. By an express prohibition I mean a provision of the underlying contract, which may be positive or negative in form but is specifically directed to calling upon the guarantee, as for example a provision saying that it shall not be called upon during stage 1 of a contract to be performed in stages or, as in this case, that it is necessary to give 10 days' notice before calling upon it. A provision simply saying that recourse may be had to the guarantee for moneys due or the like is not an express prohibition in the sense that I intend. The question in a case like that is whether a prohibition against recourse is implicit in the words of the contract. By an implied term I mean a term of the kind associated with the decision of the Privy Council in BP Refinery (Westernport) Pty Ltd v Shire of Hastings (1977) 180 CLR 266. Implication is the process of discerning either an implicit or an implied term.
No implication may be made that is inconsistent with an agreed allocation of risk as to who shall be out of pocket pending resolution of a dispute and clauses in the contract that do not expressly inhibit the beneficiary from calling upon the security should not be too readily construed to have that effect. As I have already indicated, they may simply refer to the kind of default which, if it is alleged in good faith, enables the beneficiary to have recourse to the security or its proceeds."
"(a) a failure by the Contractor to comply with any provision of this Deed or any other Project Document;
(d) the occurrence of a Construction Activity Default; and
(e) a representation or warranty given by the Contractor under this Deed or any other Project Document being or becoming incorrect or misleading in any respect."
(i) certified by the Sub-Independent Certifier under clause 42B; and
(ii) payable by the Contractor notwithstanding any dispute in relation to such certification."
"The principal requests the sub-independent certifier provide a certificate forthwith as required by clause 76.8(g)."
Hansen Yuncken Pty Ltd
Parliament Square Hobart Landowner Pty Ltd [2021] TASSC 7