[2020] QCAT 379
General information, not legal advice.
Queensland Civil and Administrative Tribunal
2020-10-09
Original judgment source is linked above.
ADMINISTRATIVE LAW - ADMINISTRATIVE TRIBUNALS - QUEENSLAND CIVIL AND ADMINISTRATIVE TRIBUNAL - where review about scope of works decision - where scope of works depends upon the wording of the policy terms of the statutory insurance scheme - whether works "reasonable and necessary" or otherwise "necessary" to rectify defects - where Part 4 of the Policy indemnifies the reasonable cost of necessary works to remedy the residential construction work - whether defective pier installation a cause of an identified defect - whether correct and preferable decision on review to include works which address the defective pier installation - where both experts agree works to address defective pier installation only required if stabilisation works unsuccessful in addressing differential movement.
Queensland Building and Construction Commission Act
Col Jenkins & Associates v Queensland Building and
Construction Commission [2019] QCAT 117
Shi v Migration Agents Registration Authority [2008] HCA 31; (2008) 235 CLR 286
Tadc Pty Ltd v Queensland Building Services Authority [2004] QCCTB 503-03
a decision about the scope of works to be undertaken under the statutory insurance scheme to rectify or complete tribunal work.
s 71A of the QBCC Act. Under s 71A(6) the QBCC may only have work carried out under s 71A to the extent that the cost of the work is covered by the assistance under the statutory insurance scheme that the person may be entitled to.
(b) the decision is set aside and substituted with the Tribunal's own decision; or
(c) the decision is set aside and the matter returned to the Commission to reconsider the decision with directions the Tribunal considers appropriate.[2]
...the decision, and the statutory question it answers, should be identified with some precision, for it marks the boundaries of the review.
66 Existing policies of insurance
(1) A policy of insurance that came into force under former part 5 continues in force on the terms stated in the board's policies for that purpose.
(2) Despite the replacement of part 5 by the Amendment Act, former part 5 continues to apply to a contract for residential construction work if the contract was entered into before the replacement day.
(3) To remove any doubt, it is declared that subsection (2) -
(a) applies to a contract even if an insurance premium is paid in relation to the contract on or after the replacement day; and
(b) does not prevent the consumer for the contract from obtaining optional additional cover under section 67Z.
(4) The board's policies that are relevant for this section continue for that purpose despite the replacement of part 5 by the Amendment Act or the repeal of the policies under schedule 1, section 67.
(5) In this section -
"board's policies" means the policies of the board made for the purposes of section 19 and relating to the statutory insurance scheme.
"replacement day" means the day former part 5 was replaced under the Amendment Act.
67 Repeal of board's policies about statutory insurance scheme
On the commencement all policies of the board made, for the purposes of section 19, about the terms of cover under the statutory insurance scheme are repealed.
4.1 Payment for Defective Construction
Subject to the terms of this policy, the QBBC agrees to pay the cost of rectifying defects in the residential construction work that is primary building work, other than for defects from subsidence or settlement referred to in Part 5 of this policy.
4.2 Amount of Payment
(a) Subject to clause 4.2(c) and Parts 6, 7 and 8 of this policy, the amount of the payment under this Part will be limited to the reasonable cost, as determined by the QBBC, of undertaking those works necessary to rectify the defects, less, where the insured contracted with the contractor for the undertaking of the residential construction work which is defective, the owner's remaining liability under the contract.
(b) Where the QBCC has admitted a claim for payment for loss relating to defects, it may if it thinks fit, having given prior written approval, pay the insured for the reasonable alternative accommodation of the insured and any removal and storage costs of the insured as determined by the QBCC as having been necessarily incurred by the insured as a result of the need to rectify the defects and because the residential construction work is, in the opinion of the QBCC, uninhabitable.
(c) Where, in the opinion of the QBCC, the undertaking of remedial works is unnecessary or unreasonable, the payment under this clause 4.2 will be limited to the loss in value, if any, as determined by the QBCC in the residential construction work, produced by the departure from the plans or specifications or by the defective workmanship or materials.
I consider that the words "scope of works" in sub-paragraph (g) are not meant as a reference to a specific document by that title...I consider that what is intended in sub-paragraph (g) is simply that the word "scope" is to bear its ordinary meaning, namely "extent or range", and that the proper interpretation of sub-paragraph (g) is that the review is to be about the extent or range of the proposed rectification works, and limited to such matters.
I consider that I am assisted in that interpretation by the following -
There is no reference in any associated sections of the relevant Acts (those sections dealing with the statutory insurance scheme and the calling of tenders) to any document entitled a "scope of works". Having said that, I accept in a practical sense, a document might come into existence which might bear such a title, however, that is neither required nor envisaged by the relevant legislation.
...
...I consider that any such review should be confined to considerations as to whether the proposed rectification works are reasonable and necessary to rectify the defects noted in the Direction to Rectify, or whether they go beyond what is reasonable and necessary.
It is to be remembered, in the above regard, particularly when considering what is reasonable, that there is often more than one method of rectifying defective work. Accordingly, the relative costs of such differing modes of rectification may become pertinent to the above considerations, in my view.[16]
Background to the formulation of the scope of works
(viii) "Slab edge dampness - moisture wicking through slab to internal areas adjacent walls".
Allow for external pavements and driveway to be removed back to the first sawn joint to undertake the plumbing and drainage issues in conjunction with the slab edge remedial works.[19]
(b) Allow for removal and replacement of concrete where necessary.
(c) Allow for external pavements and driveway to be removed back to the first sawn joint where necessary to undertake the plumbing and drainage issues in conjunction with the slab edge remedial works.
(a) Allow for removal and replacement of concrete where necessary.
(b) Allow for external pavements and driveway to be removed back to the first sawn joint where necessary to undertake the plumbing and drainage issues in conjunction with the slab edge remedial works.
Allow to lower the finished ground levels in preparation for a concrete pavement and 900mm deep cut-off wall to extend around the remainder of the building.
Allow to install a moisture barrier (minimum 2.5m deep) as close to the front of the building as practically possible, and extend to the boundaries on either side of the site as per Booth Engineers Drawing No BE2018/180530 (sheet 5) and associated detail (sheet 6)....On completion allow to extend concrete paving from the front of the building as required to extend over the moisture barrier to ensure no areas remain where stormwater can enter (without resistance) the ground inside of the cut off wall.
(a) Allow to lower the finished ground levels in preparation for a concrete pavement and 900mm deep cut-off wall as described in item 8.
(a) Allow to expose the slab edge to the full perimeter of the building and entry piers to the base level. Allow to clean slab edge with suitable method (to minimise water use) to remove soil etc/clean in preparation for moisture seal application. Allow to install 'Xypex', 'Sureseal', or 'Sika' etc strictly in accordance with manufacturer's recommendations to the exterior of the exposed slab edges and piers.
(b) Do not install moisture seal to internal areas at this time. This is to allow any moisture in the concrete to dry out naturally.
Allow to install field gullies to the engineer details and provide the required fall incorporating a spoon drain (refer to Annexure A to this scope of works).
Allow to remove sealants from vertical control joints/articulation Joints, prepare masonry substrate and install joint sealant in accordance with the manufacturer's specifications.
Rectification of Internal consequential damage and required remedial work:
Preamble: The scope of work to generally include removal of floor coverings to affected areas only, all external wall joinery and plasterboard linings to 1200 above the floor to all areas systematically opened and identified as containing mould spores, sanitising the wall cavity and reinstating all including painting to match existing. The work to be completed after the slab moisture content has reached the required Relative Humidity - Refer Item 18.
(i) Mould remediation clean to remaining building interior surface components using HEPA vacuuming and damp wiping.
(ii) Antimicrobial treatment to all wall cavities and affected areas/building components.
(iii) Structural drying of any at risk building components (if required).
(iv) Mould remediation clean to wall mounted AC units.
(v) Post remediation verification (PRV) testing to confirm successful remediation by independent Environmental Professional.
Rectification work if required associated with the movement in the footing system:
...dwelling has not been adequately protected from moisture entry into the footings of the dwelling resulting in slab edge dampness occurring and moisture entry into the dwelling.
Background and relevant evidence relating to item 25
Conclusion
We recommend the following rectifications be considered as measures aimed at addressing the complex problems affecting this property:
Stage 1: Ensure no plumbing leaks are present and upgrade site drainage conditions around building and property. During removal of gravel walkways to the sides of building, consideration could also be given to the application of waterproofing to exposed footing edge noting however that this will not address moisture issues noted elsewhere around building. Consider the use of a moisture barrier/cut off wall around the front of the property. Such a moisture barrier would be used to attempt to divert subsurface water from the underside of the building pad and footing system. Monitor moisture content levels and possible improvements.
Stage 2: Consider the use of proprietary sealing products such as 'Xypex', 'Sureseal', 'Sika' etc to be applied externally and internally - apply to the concrete footing/slab edge to manufacturers recommendations (this could also be applied internally around perimeter areas for best results). ...Monitor moisture content levels and possible improvements.
The Booth Engineers Report and design to address the slab edge dampness issues on the site includes a deep cut-off wall across the front of the dwellings to stop water traversing down the slope through the ground to the slab. The installation of the cut-off wall will require a section of concrete approximately 600mm wide cut and removed across the full width of the concrete apron areas in front of both dwellings. The removed concrete section will be replaced with a match as possible (sic) to the existing scheme.
QBCC advised the concrete must be cut to rectify the defect, however, the whole area will not be replaced as it is not necessary to do that in order to rectify the defect. The HWS allows for the reasonable cost of rectification as determined by the QBCC. The replacement of significant areas of concrete not considered defective would be considered unreasonable.
The blistering and peeling paint was found to relate to rising damp caused by moisture entering the concrete footings and wicking into the lower masonry walls under the dampcorse (sic) as a result of defective site and piped drainage work undertaken by the licensee.
...
QBCC conclusion
The construction of the dwelling does not meet a reasonable standard of construction or finish that would be expected from a competent holder of a contractor's licence for the relevant class in that dwelling has not been adequately protected from moisture in accordance with standards to stop slab edge dampness from occurring and entering into the dwelling. The issue has caused a health and safety concern for the occupants and deterioration of building elements.
The exterior and interior of the dwelling was inspected and it was identified there are signs of moisture permeating up from the under slab in areas around the perimeter of the dwelling particularly to masonry walls. An inspection of the internal areas of the dwelling identified salt build up, carpet smooth edged rot/decay and mould as a result of water wicking up through the slab.
The moisture is the result of defective construction in that plastic has not wrapped around the lower areas of the footing and up the external face to stop water entering the bare concrete.
A complete plumbing inspection and test was undertaken of all services attached to the dwelling. The plumbing test revealed damage to the drainage pipes surround the dwelling. Drainage pipes attached to the central courtyard areas were found to be blocked and possibly not connected to council discharge outlets. All the drainage issues noted were adding to the moisture in the ground, significantly increasing the moisture to very wet conditions not allowing the soil to dry naturally.
The result of the plumbing and site drainage issues has caused a condition called slab edge dampness and requires extensive external rectification to site and piped stormwater systems to correct the defect.
QBCC has obtained advice from Booth Engineers and Associates and Leakless Plumbing Pty Ltd as to how to rectify the slab edge dampness.
....
2.The construction of the dwelling does not meet a reasonable standard of construction or finish that would be expected from a competent holder of a contractor's license for the relevant class in that dwelling has not been adequately protected from moisture in accordance with standards to stop slab edge dampness from occurring and entering into the dwelling. The issue has caused a health and safety concern for the occupants and deterioration of building elements.
- Pertains to Item 6 of the QBCC Complaint form.
...
4.The construction of the dwelling does not meet a reasonable standard of construction or finish that would be expected from a competent holder of a contractor's license for the relevant class in that dwelling has not been adequately protected from moisture entry into the dwelling. The issue is a health and safety issue for the occupants of the dwellings and is causing deterioration of building elements.
- Pertains to Item 8 of the Complaint form.
Differential movement exceeding 50mm has occurred in the waffle raft slab system which is 20mm greater than recorded by Booths on 18/5/2018.
The following further engineer investigation is required:
Due to limited height of adjacent ground levels, poorly graded subgrades and highly reactive clays sealed concrete pavements including cut off walls are recommended.
The slab construction does not appear to comply with any of the details shown in Figure 3.2.2.3 of the National Construction Code 2012, the aim of which is to prevent moisture from being stored against the slab edge below slab level.
Booth in their report 'admit' that attempts to address "site drainage" may not be successful and that their recommendations are, in that event, not rectification.
Focus should be sealing (waterproofing) the exposed slab edge, from the vapour barrier beneath the slab up to the underside of the slab rebate or the threshold in the case of the garage doors.
Lowering the ground surface level and paving to a level below the slab rebate.
Opening the cavity between the slab rebate and the DPC to allow the cavity to breathe and dissipate any saturated atmosphere that may develop within that cavity from time to time. (This could be achieved by creating voids in the first course of bricks on top of the slab rebate).
Our investigations have revealed other issues, principally that some piers beneath the perimeter footing are founded in fill material or in one case on a tree root. This issue may well be relevant to the long term performance of the footing and slab system particularly given the proximity of the building to significant vegetation in neighbouring properties.(emphasis added)
8.7.1 Morgan Consulting Engineers designed a 460mmdeep waffle raft for the site. The raft was designed to be fully supported on 450mm bored piers founded not less than 600mm into natural firm material.
8.7.2 A 460mm deep waffle raft is consistent with a deemed to comply footing design for articulated masonry veneer construction on a class H2-D site.
I am of the opinion that the majority of the distortion in the building is due to fluctuations in moisture in the highly to extremely reactive subsoils. There may well be a component of the movement due to settlement of fill material particularly at the back left corner of the building where piers, designed to support the slab over fill material, were not founded into natural firm material.
The floor levels of the dwelling are within compliant parameters of AS2870-2011 Appendix C.
There is cracking and damage to walls AS2870-2011 Category 1-3.
The issues on the site relate to moisture entering the ground from defective plumbing installations and poor site drainage and damage to installed plumbing pipes.
The cause of damage and movement is considered to be the result of a combination of heave relating to leaking services and poor site drainage, as well as trees and settlement to the rear.
Recommendations/Remedial work
Re-profile the ground levels around the building to ensure surface water does not pond near the footing system and to comply with design and BCA requirements as indicated on drawings BE2019/180530a.
Carry out slab edge dampness rectifications as per Booth Engineers report and consider HBW comments pertaining to increased ventilation at this time.
Remove trees within their mature height of the building where possible.
Inspection and monitoring during rectification to be undertaken by Booth.
After site rectifications, Booth to take level survey data and prepare a level survey plan and contour plan.
A monitoring inspection with a complete level survey and moisture ingress monitoring should also be undertaken at six (6) months and twelve (12) months after the works have been completed. This level survey data and monitoring inspection would then be used to confirm any ongoing movement prior to cosmetic rectifications being undertaken. Undertake cosmetic repairs utilising flexible fillers wherever possible following monitoring period and provide suitable articulation to wall fabrics. Should additional movement or ongoing moisture ingress be identified following the monitoring period, additional works may at this stage be considered which may include underpins to rear and rear left in particular and/or additional measures aimed at addressing slab edge dampness...
Cause of movement and damage including issues of site maintenance and drainage and construction works
In this case we believe that damage and movement around the dwelling are related to a combination of heave conditions as reflected in the level survey data with some fill settlement which could also be occurring around the rear left of the building in particular (up to 0.7 metres of fill noted and piers founded in fill as per HBW report).
8.02 The building damage and movement have occurred as a result of soil moisture related movements.
8.03 In summary, the footing and slab system and movements that have occurred adversely affect the structural adequacy and serviceability of the building and the expected performance and functional use of the building when compared to the performance criteria for footings and slabs pursuant to AS2870 in regards to the category 2 to 3 cracks and gaps observed.
The experts, Martin Helisma and Stephane Rebibou are to prepare a joint report on the defects in the construction of the works of the relevant property, the cause of defects and the scope of works to rectify the defects.
The abnormal moisture and rising damp conditions are due to GW Homes (sic) failure to provide the following:
....The issues detailed above, collectively have caused the rising damp.
The differential movement and consequential damage is primarily the result of site conditions which were either not rectified or completed by GW in a competent manner....this work was the responsibility of GW and was included in both the Sergon SOW and in the GW Contract Specification ...
The relevant defects include:
The full extent of non-conforming footing pier installation has not been identified by the QBCC. Therefore the effects or movement in the area of fill cannot be quantified. The issues relating to necessary further investigation of defects in the footing system have been ignored by the QBCC.
New item - rectification work if required associated with the movement in the footing system.
Mr Helisma: I confirm that an assessment of such should be made as identified within my report and Stage 1 recommendations. Underpinning or other rectifications may then be considered as deemed appropriate.
Mr Rebibou: QBCC fail to provide this defect in the scope of work. Further investigation required to address the defective piers and assess what rectification work is necessary if required. Engineer assessment required.
The applicants' position in relation to item 25
Adequately investigate the issues properly so you are not reworking issues already refixed...
Should additional movement or ongoing moisture ingress be identified following the monitoring period, additional works may at this stage be considered which may include underpins to rear and rear left in particular and/or additional measures aimed at addressing slab edge dampness...
The Commission's position in relation to item 25
Consideration of whether to include Item 25 in the Scope of works
CT Testing shows shrink/swell value for the site ranges between 4.5 and 7.2 which may have the potential for differential movements under normal conditions exceeding 70mm; the footing piers have not been installed into 600mm through the fill into natural ground as specified by the design engineer, that is, the footing piers fall short of the foundation requirements by up to 800mm to 1000mm.
(a) Should additional movement or ongoing moisture ingress be identified following the monitoring period, additional works may at this stage be considered which may include underpins to rear and rear left in particular and/or additional measures aimed at addressing slab edge dampness...
Cause of movement and damage including issues of site maintenance and drainage and construction works
The soil moisture conditions relating to a combination of poor site drainage and plumbing leaks/pipe breaks around the dwelling in all likeliness have had a significant influence on observed movement and damage particularly since these have been existing for some time (years in some cases) and are contributing to both SED and footing movement.
In this case we believe that damage and movement around the dwelling are related to a combination of heave conditions as reflected in the level survey data with some fill settlement which could also be occurring around the rear left of the building in particular (up to 0.7 metres of fill noted and piers founded in fill as per HBW report).
The full extent of non-conforming footing pier installation has not been identified by the QBCC. Therefore the effects or movement in the area of fill cannot be quantified. The issues relating to necessary further investigation of defects in the footing system have been ignored by the QBCC.
New item - rectification work if required associated with the movement in the footing system.
Mr Helisma: I confirm that an assessment of such should be made as identified within my report and Stage 1 recommendations. Underpinning or other rectifications may then be considered as deemed appropriate.
Mr Rebibou: QBCC fail to provide this defect in the scope of work. Further investigation required to address the defective piers and assess what rectification work is necessary if required. Engineer assessment required.
The scope of works decision made by the QBCC dated 13 August 2018 is amended as follows:
(a) amendments to items S2, S3, S4, S8, S10 and S17 in the terms provided in these Reasons;
(b) the addition of S23 in the terms provided in these Reasons; and
(c) the addition of S24 in the terms provided in these Reasons.
[5] Re Control Investment Pty Ltd and Australian Broadcasting Tribunal (No 2) (1981) 3 ALD 88.
[7] QCAT Act, s 19(c); Shi v Migration Agents Registration Authority [2008] HCA 31; (2008) 235 CLR 286, [147].
[8] Shi v Migration Agents Registration Authority [2008] HCA 31; (2008) 235 CLR 286, [133] , (Kiefel J).
[11] Samimi v Queensland Building and Construction Commission [2015] QCA 106, [31] (Boddice J, Margaret McMurdo P and Morrison JA agreeing).
[12] Col Jenkins & Associates v Queensland Building and Construction Commission [2019] QCAT 117, [21], citing Middling v QBSA [2005] CCT Q600-03; J & K Homes Pty Ltd v Queensland Building and Construction Commission [2017] QCAT 269, [21]; Tadc Pty Ltd v QBSA [2004] QCCTB 503-03, [117]-[120]; Turcinovic v Queensland Building Services Authority [2012] QCAT 14, [6].
[13] Col Jenkins & Associates v Queensland Building and Construction Commission [2019] QCAT 117, [21].
[17] I note clause 4.2(c) which refers to remedial works which are "unnecessary or unreasonable". In my opinion, those words in that context are insufficient to rebut the plain meaning of clause 4.2(a).
[18] Tribunal Directions dated 16 March 2020.
[19] Applicants' Proposed Amendments to the Sergon SOW.
[20] Queensland Building Services Authority Regulation 2003 (Qld), s 11(3)(d)(ii).
[21] Policy, cl 4.6; Queensland Building Services and Authority Regulation 2003 (Qld), s 11(2), s 11(3).
[23] QBCC's closing submissions (after oral evidence), [62].
[24] But incorrectly dated 10 January 2019.
[25] Supplementary statement of Stephane Rebibou of 9 March 2020.
Hall & Anor
Queensland Building and Construction Commission [2020] QCAT 379
(2008) 235 CLR 286