Hakea Holdings Pty Ltd v Neon Underwriting Limited for and on behalf of the Underwriting Members of Lloyds Syndicate 2468
[2023] FCAFC 34
At a glance
Source factsCourt
Federal Court of Australia (Full Court)
Decision date
2023-03-10
Before
Jackman JJ
Source
Original judgment source is linked above.
Judgment (10 paragraphs)
Introduction 77 This is an appeal from the judgment of Yates J in the matter of Hakea Holdings Pty Ltd v McGrath (No 2) [2022] FCA 995. The learned primary judge found that Mr McGrath was liable to Hakea Holdings Pty Ltd (Hakea) for breach of his duty as a director of Hakea under s 180(1) of the Corporations Act 2001 (Cth). Mr McGrath is not a party to the appeal and there is no appeal from that finding. 78 Mr McGrath was insured under a Directors and Officers Liability Insurance Policy for the period 23 January 2016 to 23 January 2017 (Policy), held by Hakea and underwritten by Neon Underwriting Limited for and on behalf of the underwriting members of Lloyds Syndicate 2468 (Neon). Neon was the active defendant in the Court below. The primary judge rejected Hakea's claim that Mr McGrath was entitled to be indemnified under the policy in relation to his liability. The learned primary judge found that Neon was entitled to rely on an exclusion clause in the policy, and the present appeal is brought from the primary judge's conclusion that that exclusion applies. The Policy is a 'claims made' policy of the nature described in FAI General Insurance Co Ltd v Australian Hospital Care Pty Ltd [2001] HCA 38; (2001) 204 CLR 641 at [64]-[68]. Salient factual findings made by the primary judge 79 As there is no appeal against any of the factual findings by the primary judge, and the appeal raises questions concerning the proper construction of the Policy, I summarise briefly the factual findings made at first instance. 80 In addition to being a director of Hakea, Mr McGrath was also the sole director, shareholder, secretary and general manager of Denham Constructions Pty Ltd (Denham). On 12 October 2012, Denham entered into a contract with Hakea to design and construct a residential aged care facility on property owned by Hakea in Hamlyn Terrace in New South Wales (Building Contract). The Building Contract was a lump sum contract, and Denham could claim payment by progress claims as and when progress certificates were issued by the Superintendent. Denham was obliged to ensure that the work reached practical completion by a specified date, which was subsequently extended. 81 Clause 39.11 of the Building Contract provided relevantly that if a party informs the other in writing that the party is insolvent or is financially unable to proceed with the contract, then the Principal may, without giving notice to show cause, exercise a contractual right to take out of Denham's hands the whole or part of the work remaining to be completed and suspend payment under the contract. The Building Contract also gave Hakea a right of termination of the contract if Denham committed a substantial breach and Hakea had given Denham a notice to show cause why Hakea should not exercise that right. 82 In late 2013, Denham commenced construction work on the project. By October 2014 the work was not progressing as quickly as had been anticipated. Unbeknown to Hakea, on 30 October 2014 Denham defaulted on a payment arrangement it had made with the Australian Taxation Office (ATO), which required it to pay $300,000 as a part payment to extinguish its then tax debt. In December 2014, the ATO proposed a further plan for instalment payments from Denham to meet its tax debt, which was then $939,199.56. On 20 March 2015, the ATO gave a statutory garnishee notice to Australia and New Zealand Banking Group Limited (ANZ) requiring it to deduct money to the value of $890,114.61 from any account held by Denham with ANZ and to pay that money to the Commissioner of Taxation. Three days later, Denham transferred all its employees to a related company. In late March 2015, Denham made a further payment offer to the ATO, but that offer was rejected by the ATO on 13 April 2015. On 20 April 2015, Denham raised an invoice on Hakea for a progress claim requesting payment into Denham's account with Commonwealth Bank of Australia, which the primary judge found was a request made to avoid the consequences of the statutory garnishee notice given to ANZ. 83 On 4 May 2015, the Deputy Commissioner of Taxation issued a demand to Denham under s 459E of the Corporations Act for the amount of $1,812,615.05. In the period 6 May 2015 to 20 November 2015, thirteen further statutory demands were issued on Denham by other creditors. 84 Throughout May 2015, the Chairman of Hakea, Mr Pardy, was becoming concerned about the delay to the progress of the project. Correspondence then ensued between Mr Pardy and Mr McGrath in which Mr McGrath sought to explain the delays in the project, but Mr McGrath's response on 21 May 2015 made no reference to Denham's financial difficulties at the time, including the fact that the ATO's statutory demand had been made. 85 On 30 July 2015, a meeting took place between Mr Pardy and Mr McGrath and others, which the primary judge said was attended by Mr McGrath on behalf of Denham. Mr McGrath sought to explain the delays to the project by reference to disputes with subcontractors which he said had now been resolved and said that a revised date for practical completion of 17 November 2015 could be met. 86 On 27 August 2015, Mr McGrath attended a meeting of Hakea's directors and said that Denham would meet the current program and Hakea should be able to commence its fit out by 30 October 2015. 87 By October 2015, there was minimal activity on the site and by early November 2015, all substantive work on the project had ceased. At a meeting on 5 November 2015, between representatives of Hakea and Denham, the representatives from Denham (which did not include Mr McGrath) disclosed, for the first time, that Denham had liquidity problems. In a later telephone conversation, Mr McGrath said to Mr Pardy that he had resolved the liquidity issues. 88 On 1 December 2015, Hakea issued a notice to show cause under the Building Contract, and that notice stated that Hakea had formed the view that Denham was no longer ready, willing and able to perform the building contract. Denham failed to show cause to the satisfaction of Hakea, and on 10 December 2015 Hakea issued a letter of termination under the building contract and terminated the contract. 89 Given the time of year, it was difficult for Hakea to contact builders to discuss working on the project. However, in the latter part of January 2016, Hakea engaged an alternative builder to complete the contract, and the project reached practical completion on 30 June 2016. 90 On 1 September 2016 the Supreme Court made an order that Denham be wound up. 91 The primary judge concluded that Denham was in severe financial distress as at 21 May 2015 and that Mr McGrath knew that fact. Further, the primary judge found that this financial distress was the substantial reason why work on the project was not progressing as quickly as it should have been. His Honour also concluded that, as at 21 May 2015, Denham was not in a financial position to complete the building work by 1 September 2015 (the then agreed date for practical completion) or in the reasonably foreseeable future, despite representations made by Mr McGrath to the contrary. His Honour found that, in terms of cl 39.11 of the building contract, Denham was, at that time, financially unable to proceed with the contract. The learned primary judge concluded that Mr McGrath knew the true state of Denham's severe financial distress as at 21 May 2015 and its inability, at that time, to complete the project in a timely fashion. 92 The primary judge went on to find that Mr McGrath deliberately did not disclose these facts to Hakea at that, or any later, time: at [184]. His Honour observed that, of all the directors of Hakea, Mr McGrath was uniquely placed to know Denham's financial position and its ability, from that perspective, to undertake and complete the work it was required to perform under the building contract. His Honour found that the fact that, as at 21 May 2015, Denham was suffering severe financial distress and unable to complete the project in a timely fashion was fundamentally important information which it was essential for Hakea to know. 93 Importantly, the learned primary judge found that there was no reason why Mr McGrath would not have disclosed this information to Hakea apart from, firstly, an awareness on his part, that such disclosure would jeopardise the continuation of the Building Contract and, secondly, a desire to keep that contract on foot in the hope that, somehow, Denham's financial circumstances would improve sufficiently to enable it, eventually, to complete the project: at [185]. His Honour found that Mr McGrath, as an experienced builder undertaking large projects of this kind, must have appreciated the real possibility that, if this information was disclosed, Hakea would look to the Building Contract and take such steps as were available to it to either terminate the contract or replace Denham as the builder. 94 His Honour concluded that, as a director of Hakea, Mr McGrath breached the duty imposed on him by s 180(1) of the Corporations Act by not disclosing, on or after 21 May 2015, that Denham was in severe financial distress and unable to complete the project in a timely fashion: at [186]. Section 180(1) provides that: A director or other officer of a corporation must exercise their powers and discharge their duties with the degree of care and diligence that a reasonable person would exercise if they: (a) were a director or officer of a corporation in the corporation's circumstances; and (b) occupied the office held by, and had the same responsibilities within the corporation as, the director or officer. 95 The learned primary judge then found that, had Mr McGrath disclosed Denham's severe financial distress as at 21 May 2015 and its inability, at that time, to complete the project in a timely fashion, Hakea's Directors, on taking legal advice on Hakea's rights under the Building Contract, would have proceeded to take out of Denham's hands the remaining work to be performed. His Honour was satisfied that the directors would have acted promptly in this regard and that it was likely that a replacement builder would have been appointed within about one month (by about 22 June 2015) and that the project would have been completed within approximately six months thereafter (by about 22 December 2015): at [192]. It was accepted by Neon that Hakea had suffered loss as a result of Mr McGrath's breach of duty.