[2025] NSWCATAP 243
General information, not legal advice.
NCAT Appeal Panel
2025-09-30
S Westgarth, Deputy PresidentP H Molony, Senior Member
Original judgment source is linked above.
Alexandria Landfill Pty Ltd v Transport for NSW (2020) 103 NSWLR 479; [2020] NSWCA 165
Bimson, Roads & Maritime Services v Damorange Pty Ltd [2014] NSWSC 734
CEO of Customs v AMI Toyota Ltd [2000] FCA 1343; (2000) 102 FCR 578 (Full Fed Ct), [2000] FCA 1343
Collins v Urban [2014] NSWCATAP 17
Ferella & Anor v Chief Commissioner of State Revenue [2014] NSWCA 378
FVA v Commissioner for Police, NSW Police Force [2024] NSWCATAP 127
Craig v South Australia [1995] HCA 58; (1995) 184 CLR 163 at 179; [1995] HCA 58
Haritos v Federal Commissioner of Taxation (2015) 233 FCR 315; [2015] FCAFC 92
Jackson v NSW Land and Housing Corporation [2014] NSWCATAP 22
Kostas v HIA Insurance Services Pty Ltd [2010] HCA 32; (2010) 241 CLR 390
Kudrynski v Orange City Council [2024] NSWCA 33
Naylor Parramatta Pty Ltd atf Chan & Naylor Paramatta Trust [2020] NSWCA 62
Orr v Cobar Management Pty Limited (2020) 103 NSWLR 36; [2020] NSWCCA 220
Orr v Hunter Quarries Pty Ltd [2022] NSWCCA 39
Pholi v Wearne [2014] NSWCATAP 78
Prendergast v Western Murray Irrigation Ltd [2014] NSWCATAP 69
Ryan v BKB Motor Vehicle Repairs Pty Ltd [2017] NSWCATAP 39
Schwartz Family Co Pty Ltd v Capitol Carpets Pty Ltd [2017] NSWCA 223
Unique Commercial Group Pty Ltd v Cusumano [2024] NSWCATAP 204
"83 As the undisputed facts at the commencement of the hearing were that by 4 November 2024, the Contract was still on foot, the Builder was still in possession of the site and practical completion was not yet achieved, I find that the Builder has failed to complete the works in accordance with Item 6 of Schedule 1 of the Contract and is in breach of statutory warranty of s 18 B(1)(d) by failing to reach practical completion by 11 September 2023."
(1) Loss of rental income for the original house which was demolished being a loss of rent for 52 weeks from 11 May 2022 to 30 September 2022 at $750 per week (which was the amount of the weekly rent paid by the outgoing tenants) = $39,000
(2) Loss of rental income for the two duplexes to be constructed under the Contract estimated at $1200 each per week (total of $2400 per week) for a period of 46 weeks commencing 26 August 2023 = $110,400
(3) Monthly bank interest for the period 26 August 2023 to 21 August 2024 totalling $164,383.44
(4) Monthly bank interest for the period August 2024 to 31 January 2025 totalling $82,191.72
(5) Cost of mental health professional $4305
(6) Other costs such as legal fees, expert fees and filing fee.
"In their submissions on costs the Homeowners set out extensive submissions reiterating the merits of their application which was determined by the orders dated 14 February 2025. They also press for costs associated with ongoing delays. This is not the purpose of the costs application. ... A costs application is not a further application for compensation arising from the substantive dispute between the parties."
The principles applicable to applications to extend time
(1) The Tribunal may, of its own motion or on an application by any person, extend the period of time for the doing of anything under any legislation in respect of which the Tribunal has jurisdiction despite anything to the contrary under that legislation.
(2) Such an application may be made even though the relevant period of time has expired.
The considerations that will generally be relevant to the Appeal Panel's consideration of whether to grant an extension of time in which to lodge a Notice of Appeal include:
(1) The discretion can only be exercised in favour of an applicant upon proof that strict compliance with the rules will work an injustice upon the appellant - Gallo v Dawson [1990] HCA 30, 93 ALR 479 at [2], Nanschild v Pratt [2011] NSWCA 85 at [38];
(2) The discretion is to be exercised in the light of the fact that the respondent (to the appeal) has already obtained a decision in its favour and, once the period for appeal has expired, can be thought of as having a "vested right" to retain the benefit of that decision - Jackamarra v Krakouer (1998) 195 CLR 516 at [4], Nanschild v Pratt [2011] NSWCA 85 at [39] and, in particular, where the right of appeal has gone (because of the expiration of the appeal period) the time for appealing should not be extended unless the proposed appeal has some prospects of success - Jackamarra at [7];
(3) Generally, in an application for an extension of time to appeal the Appeal Panel will be required to consider:
(a) The length of the delay;
(b) The reason for the delay;
(c) The appellant's prospects of success, that is usually whether the applicant has a fairly arguable case; and
(d) The extent of any prejudice suffered by the respondent (to the appeal),
- Tomko v Palasty (No 2) [2007] NSWCA 369; (2007) 71 NSWLR 61at [55] (per Basten JA) but note also [14], Nanschild v Pratt [2011] NSWCA 85 at [39] to [42]; and
(4) It may be appropriate to go further into the merits of an appeal if the explanation for the delay is less than satisfactory or if the opponent has a substantial case of prejudice and, in such a case, it may be relevant whether the appellant seeking an extension of time can show that his or her case has more substantial merit than merely being fairly arguable - Tomko v Palasty (No 2) [2007] NSWCA 369; (2007) 71 NSWLR 61 at [14] (per Hodgson JA, Ipp JA agreeing at [17]) and Molyneux v Chief Commissioner of State Revenue [2012] NSWADTAP 53 at [58] - [59].
"Any internal appeal may be made":
(a) "in the case of an interlocutory decision of the Tribunal at first instance - with the leave of the Appeal Panel", and
(b) "in the case of any other kind of decision (including an ancillary decision) of the Tribunal at first instance - as of right on any question of law, or with the leave of the Appeal Panel, on any other grounds".
An Appeal Panel may grant leave under section 80 (2) (b) of this Act for an internal appeal against a Division decision only if the Appeal Panel is satisfied the appellant may have suffered a substantial miscarriage of justice because:
(a) the decision of the Tribunal under appeal was not fair and equitable, or
(b) the decision of the Tribunal under appeal was against the weight of evidence, or
(c) significant new evidence has arisen (being evidence that was not reasonably available at the time the proceedings under appeal were being dealt with).
"Those questions of law should be, in our opinion, what are sometimes described as 'pure questions of law.' They should not draw the Court of Criminal Appeal into questions of fact. Moreover, they must be questions whose character as a question of law can be recognised on the face of the question, and not depend upon the answer given to the question. This does not include a question which may ultimately disclose an error of law depending on an analysis of the facts but where this cannot be known without scrutiny of the facts."
(1) Denial of procedural fairness (Prendergast v Western Murray Irrigation Ltd [2014] NSWCATAP 69 at [13](4)) (Prendergast); FVA v Commissioner for Police, NSW Police Force [2024] NSWCATAP 127 at [83]- [84]).
(2) A constructive failure to exercise jurisdiction, which includes the failure to consider and address a material issue raised by a party in the proceedings that is within the jurisdiction of the Tribunal to determine (Alexandria Landfill Pty Ltd v Transport for NSW (2020) 103 NSWLR 479; [2020] NSWCA 165 at [8]- [12] and [413]). This category of error also includes a failure by the Tribunal to engage with a clearly articulated argument put to it.
(3) The construction of a statute or contract arrived at by the Tribunal at first instance was wrong in some identified way.
(4) Acting on the application of the wrong legal principle which materially affected the outcome (Bimson, Roads & Maritime Services v Damorange Pty Ltd [2014] NSWSC 734 at [38]- [53]).
(5) No evidence to support a factual finding (Kostas v HIA Insurance Services Pty Ltd (2010) 241 CLR 390; [2010] HCA 32 at [91]).
(6) A failure to provide adequate reasons for decision.
An Appeal Panel may grant leave under section 80 (2) (b) of this Act for an internal appeal against a Division decision only if the Appeal Panel is satisfied the appellant may have suffered a substantial miscarriage of justice because:
(a) the decision of the Tribunal under appeal was not fair and equitable, or
(b) the decision of the Tribunal under appeal was against the weight of evidence, or
(c) significant new evidence has arisen (being evidence that was not reasonably available at the time the proceedings under appeal were being dealt with).
(1) the decision of the Tribunal under appeal was not fair and equitable; or
(2) the decision of the Tribunal under appeal was against the weight of evidence; or
(3) significant new evidence has arisen (being evidence that was not reasonably available at the time the proceedings under appeal were being dealt with).
"... there was a 'significant possibility' or a 'chance which was fairly open' that a different and more favourable result would have been achieved for the appellant had the relevant circumstance in para (a) or (b) not occurred or if the fresh evidence under para (c) had been before the Tribunal at first instance."
(1) Issues of principles;
(2) Questions of public importance or matters of administration or policy which might have general application;
(3) An injustice which is reasonably clear, in the sense of going beyond merely what is arguable, or an error that is plain and readily apparent which is central to the Tribunal's decision and not merely peripheral, so that it would be unjust to allow the finding to stand;
(4) A factual error that was unreasonably arrived at and clearly mistaken; or
(5) The Tribunal having gone about the fact finding process in such an unorthodox manner or in such a way that it was likely to produce an unfair result so that it would be in the interests of justice for it to be reviewed.
(1) From the owners:
(a) Original notice of appeal filed 16 May 2025 with attached bundle (not numbered).
(b) Owners bundle of documents (tabbed 1 to 36) filed on 6 June 2025.
(c) Amended notice of appeal filed 27 June 2025 with attachments.
(d) Two folders of documents including submission being-
(i) Volume 1, with 58 Tabs; and
(ii) Volume 2 with 17 Tabs (including a transcript of the hearing below).
(e) Submissions in reply dated 18 July 2025.
(2) From the builder:
(a) Reply to the appeal filed 6 June 2025.
(b) Bundle of documents filed 23 July 2025 tabbed A to F including submissions.
"13 The Homeowners confirmed they sought damages flowing from the Builder's breach of the Contract, to complete the works to practical completion within the agreed contract period of 44 weeks. The Homeowners confirmed they did not seek any work order just a money order."
"Seeking Order: Payment of damages for delays in building work, loss of rental from existing house (...), loss of interest incurred past the 44 week build period (..., clause 6 Build Period HIA Contract). Liquidation damages (sic) amount is unreasonably low at $10 per day, it should be $2400 per week (rental loss). Seeking order for a fixed term completion date by end of October 2024 due to financial hardship and potential loss of current building loan funds. Order for Zac Home to place all available trades on job. Order to include completion inclusive of Colourbond fence at no extra costs, retaining walls as agreed and OC's all submitted and provided..." (our underlining)
Member: ... Now, before we start the evidence study, the claim from the homeowners is for the money order of $405,972. ls that correct?
Applicant Grbevska: Yes. Nothing more, nothing less.
Applicant Grbevska: I'm sorry, that's just approximate. I mean, I was just being really fair.
Member: Okay. But you've got the breakdown.
Applicant Grbevska: Yes, I have. And I've provided proof.
Member: Yes, I've seen that in your documents. Are you asking for a work order?
Applicant Grbevska: What's the work order?
Member: Work order is for the builder to return to do the work.
Applicant Grbevska: Well, Mr Zaccazan did. He did commend some work. We were overseas and our neighbour did tell us that after I've submitted the documents to NCAT, I believe it was made in the claim to forward.
Member: Are you asking the tribunal to make an order for the builder to do any work or are you only asking for a order? What are you asking for?
Applicant Grbevska: Well, don't know. l I've asked Mr Zaccazan whether he wants to finish this project. He has told us that he does want to complete it. He keeps asking us for money, and that means progress payment six of seven, so we are near the end. But I don't think Mr Zaccazan realises that he actually owes us money because we're way ahead.
Member: Okay. So because one of the problems which I need to highlight to you is that this contract doesn't look like its been terminated by anybody.
Applicant Grbevska: It's not, hasn't been?
Member: You've got a contract.
Applicant Grbevska: Yes.
Member: And it's got in there a whole set of provisions of how you go about doing the contract, and your remedies usually flow from how that contract is terminated. But the contract things, I know I did see something. It's still on foot?
Respondent Zaccazan: It's still on foot.
Applicant Grbevska: Yes, that's correct. We have not ended it. Neither has Mr Zaccazan, even though he has threatened multiple times to terminate the contract. He has also told us multiple times that the contract is null and void, so it doesn't exist.
Member: But in terms of the proceedings today, are both parties saying that the contract is still on foot?
Applicant Grbevska: Yes.
Respondent Zaccazan: Correct.
Member: And you are, okay. But practical completion hasn't been reached?
Applicant Grbevska: No. And we have not been provided
Member: Okay, but as of today it's not reached, And who's got possession of the site?
Respondent Zaccazan: Zac Homes.
Member: Okay, because the costs, you're seeking compensation in terms of funding costs, but you're also seeking completion costs? Okay?
Applicant Grbevska: Sorry, I wasn't sure how, I've got a statement that I was going to read out, like summarising everything so that I remember. I know I've got a statement there, but I was just in the mind frame that I was going to read it all out. We do want Mr Zaccazan to complete it. It was only on the 9th of October a few weeks back that he actually said that we might be at PCI mid-November and completion in January of 2025. I did send several emails prior to that to Mr Zaccazan demanding that they complete the project by the 31st of October because our loan has ended, And as of this month, we're not able to make those loan repayments ...
... Look, there are lots of legal issues. I don't know if either party has had legal advice, but I know you have a practical problem that you've got a house and things have gone... I don't want to use the word wrong, but things have broken down a little bit between the parties. I think it's probably a fair assessment. But the legal remedies that flow from when the contract's still on foot are very limited because the Contract... It's when the contract's terminated and the parties take those steps under the contract to finish it that you can make claims for completion costs and those sorts of things because losses and things haven't crystallised yet because it's ongoing. And things like incomplete works or might still be done by the builder. Any defects, there is a defect liability period after practical completion where small things get attended to. So it might... It could be premature to have these proceedings at this point.
Member: ... . So the orders that are being sought by the homeowners are just the payment of $405,000. You're not seeking a specific work order, or are you?
Applicant Grbevska: Well, if we can agree for them to complete it, because Mr Zaccazan has advised us that the contract is current, that he does want to complete this project. If he says that he doesn't want to, then obviously we need those funds to get someone else to complete it.
Responded Zaccazan: Technically, the job's on hold because there's a breach notice.
Member: Well, you suspended it by notice a while ago but then you've gone back on site. So have you unsuspended it?
Responded Zaccazan: We are continuing the works but there's still money owed.
Member: You've asked ... why have you done a quantity survey? Your $315,000 talks about the value of the work that you say hasn't been completed. Is that right?
Applicant Grbevska: That's correct. What I'm referencing is that according to the expert he stated that there was $315,400 of building works uncompleted. so my question was has that been completed?
Member: Okay so you're not asking for a money order for $315,000?
Applicant Grbevska: No. That's how much work is outstanding. I'm sorry you asked me whether that's in addition to...
Member: Normally you would get somebody to value the work that hasn't been completed if you were claiming completion costs against them. That's not what you're claiming. You're claiming...
Applicant Grbevska: I'm claiming my own personal losses.
"90 The loss claimed must be of a type that (1) arises naturally, which is in the usual course of things, from the breach; or (2) is of a type that may have reasonably have been supposed to be in the contemplation of both parties at the time they made the contract as the probable result of the breach. This is often referred to as the 2 [second] limb of the principle of Hadley v Baxendale."
"96 I do not consider that loss of rent for the duplexes arise naturally from the Builder's breach and therefore this claim is not within the first limb of Hadley v Baxendale. The Homeowners must prove on the balance of probabilities that the claim falls within the second limb, by establishing that the Builder knew or reasonably should have known at the time the Contract was entered into on about 27 August 2021 that the dwellings were being constructed for the purpose of rental income".
"97 I have considered the Homeowners' evidence presented in their documents, their own witness statements and their oral evidence given at the hearing and their cross examination of Mr Zaccazan".
"98 In terms of the loss of rental of the 2 duplexes, the Homeowners may have intended for both duplexes to be rented at market rentals once completed. However, in order to be a loss within the second limb of Hadley v Baxendale, the Homeowners must be able to establish on the evidence at the requisite standard of proof that the Builder knew or should have reasonably known that the purpose of the construction was to rent out the properties as an investment".
"99 In rejecting a claim for compensation for loss of rental, the Appeal Panel held in Bui v DB Homes Australia Pty Ltd [2017] NSWCATAP 218 at [28]":
"The appellants did not establish, at first instance, that this type of loss was foreseen by the parties. In the words of Hadley v Baxendale, this damage was not "in the contemplation of both parties" (at 151). It cannot be assumed that the mere fact someone is building a granny flat is for the purposes of rental".
"100 Similarly, just because the Homeowners are building a pair of duplexes it does not necessarily establish that they were was for the purposes of rental properties".
"101 The Tribunal is not satisfied on the balance of probabilities that the Builder knew or should reasonably have known at the time of entering the Contract that the residential premises were being constructed for the purpose of renting".
"102 It follows that I find that there is a lack of evidence before the Tribunal to establish on the balance of probabilities that a loss of rental for the duplexes was reasonably in the contemplation of both parties at the time the Contract was entered into which was on 27 August 2021. Accordingly, the Tribunal dismisses this part of the claim".
104 In terms of the loss of rental of the original house, as the evidence of the Homeowners was that the contract for sale for the purchase of the property was settled with vacant possession, and the tenant had vacated by the time of settlement, the loss of rental of this property could not have been a loss in the contemplation of either party at the time the Contract was signed as no tenant was living at the property at the date of the Contract. Nor was there any evidence that it was proposed to find a new tenant.
105 This claim for compensation is refused on the basis that it does not fall within the second limb of Hadley v Baxendale.
Bank interests and charges incurred during periods of delay
106 This claim is for all interest paid by the Homeowners in the period from 26 August 2023 to the end of January 2025. This loss does not arise naturally from the Builder's breach and would need to fall within the second limb of Hadley v Baxendale to succeed. However, the Tribunal is not satisfied that this is a loss that is attributable to a breach by the Builder.
107 The Homeowners rely on the evidence of the interest figures and calculation in their "Damages Claim" at Tab 4 and a small number of documents in that Tab to demonstrate they have loan facilities with monthly interest payments.
108 In the document titled Damages Claim, they claim all interest paid in the period 26 August 2023 to 21 August 2024 which totals $161,383.44. In the amended claim dated 3 November 2024 they seek additional interest charges at the total monthly rate of $13,698.62 for the period August 2024 - January 2025 which is an additional $82,191.72.
109 The Homeowners have not put into evidence copies of the terms and conditions of the loan facilities. However, it can be safe to assume that the loan obligations were that the Homeowners were liable to pay interest every month for the term of the loan. This is what their monthly obligation would have been irrespective of whether the duplexes were constructed in accordance with the contracted building period or not. There was no evidence that any part of the interest amounts included a default margin interest rate because construction had not taken place in accordance with the building period. Even if there was such an interest charge, it would have needed to be in the reasonable contemplation of the Builder at the time the contract was signed to fall within the second limb of Hadley v Baxendale.
"Just wanted to get back to you. We are hoping to get pre-approval by possibly the end of the week. We revisited the numbers and they look good so hence heading towards having pre-approval soon".
...
"...We told [the sales representative] that we need to stay within our budget and our preapproved loan".
"111 In terms of the mental health professional fee, there is no evidence that this was a loss in the contemplation of both parties at the time the Contract was signed, nor is there sufficient evidence to establish on the balance of probabilities that this loss was a result of the breach of the Builder."
"Member: Usually you can't claim non-economic loss. I know you've paid for it, but it's a physical, mental injury".
"Member: That's fine, but I just wanted to put it on the record".
"Member: You've got bills?"
"Applicant Grbevska: Yes, I have. I've attached the bills there on that same tab".
"Member: Okay, yes".
"Application Grbevska: And by the way, that is ongoing as well".
"Member: Yep. Have they provided a report or just an invoice"?
"Applicant Grbevska: No, no report. And just to be honest, I don't really want to share something like that: It's very personal".
"Member: Okay".
Leave to appeal the order that the owners pay variation 1
40 The Homeowners have consistently contested liability for BV01 on the basis that no evidence has been provided by the Builder that the spoil was removed to prove the amount claimed, despite their repeated requests for that evidence. The Homeowners contended that they signed BV01 under duress.
41 Additional spoil was located on site by the Builder, but the Homeowners arranged for it to be removed at their cost.
(9) On 17 October 2022 site excavation and benching was completed;
(10) On 4 November 2022 the Builder informed the Homeowners that additional excavation spoil had to be removed from site and a building variation was issued for $5780 - BV01;
(11) The Homeowners did not sign BV01 under duress as they claim;
(12) Further contaminated spoil was also required to be removed from site, which the Builder issued BVO2 on 17 November 2022 for, but the Homeowners arranged for their own contractor to do this work;
(13) The soil the subject of BV02 was different to the spoil removed under BV01;
115 I am satisfied from the evidence presented at the hearing that Building Variation no 1 for $5780 dated 4 November 2022 (at page 161 of PJZ1) was a variation issued by the Builder under clause 18 of the Contract, that the Homeowners signed it and as such it was due and payable by the Homeowners at the time of the next progress payment. The Homeowners have refused to pay the sum of $5780 (or any part of it) on the basis that they signed it under duress and the Builder has never established that the work was done.
116 I am satisfied from the email from the Builder's office to one of the Homeowners dated 4 November 2022 (at page 158 of PJZ 1) that the work was required and the estimated cost from the contractor was $5780. I am satisfied from the oral evidence of the Mr Zaccazan that the work was done and invoiced by the contractor in the sum of $5780.
117 I find that the Homeowners are liable to pay BV 01 and make an order for this amount.
(1) Extend time for the appeal so that the notice of appeal filed on 16 May 2025 and amended on 27 June 2025 was made within time.
(2) Leave to appeal with respect to the appellants' claim for interest payments wasted and related losses is granted. Otherwise, leave to appeal is refused.
(3) The appeal is allowed with respect to application number 2024/00222460.
(4) Order 3 made by the Tribunal on 14 February 2025 is set aside and the application is remitted to the Tribunal for an assessment of damages relating to wasted payments of bank interest and related losses.
(5) The appeal with respect to application number 2024/00391462 is dismissed.
(6) If any party wishes to claim costs of the appeal -
(a) Any application for costs is to be filed and served within 14 days of publication of these reasons supported by submissions on costs
(b) Submissions in response to that application not to exceed 1000 words are to be filed within a further 14 days.
(c) Any submissions in reply from the costs applicant (not exceeding 500 words) are to be filed within a further 7 days.
(d) Bother parties submissions are to address whether the Tribunal can dispense with a hearing of the costs issues and determine them without a hearing on the papers.
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.
File number(s) under appeal corrected to 2024/00391462
Grbevska & Grbevski
Zac Homes Pty Ltd [2025] NSWCATAP 243;
(2020) 103 NSWLR 479
(2000) 102 FCR 578
(1995) 184 CLR 163
(2015) 233 FCR 315
(2010) 241 CLR 390
(2020) 103 NSWLR 36
(1998) 195 CLR 516
(2007) 71 NSWLR 61