[2016] ACAT 60
ACT Civil and Administrative Tribunal
2016-06-08
Original judgment source is linked above.
I am unable to attend the upcoming specified date, please contact me on the following details or contact myself via post for the changed date and time.
"Both the primary judge and the Court of Appeal should have taken into account that, whatever costs are ordered, there is an irreparable element of unfair prejudice in unnecessarily delaying proceedings. Moreover, the time of the court is a publicly funded resource. Inefficiencies in the use of that resource, arising from the vacation or adjournment of trials, are to be taken into account. So too is the need to maintain public confidence in the judicial system."
"The discretion [to allow amendments] is exercised in the context of the common law adversarial system as qualified by changing practice. But that is not a system which today permits disregard of undue delay. Undue delay can undermine confidence in the rule of law. To that extent its avoidance, based upon a proper regard for the interests of the parties, transcends those interests. Another factor which relates to the interest of the parties but transcends them is the waste of public resources and the inefficiency occasioned by the need to revisit interlocutory processes, vacate trial dates...because of noncompliance with court timetables..."
"97. The objectives of case management are now expressly stated in r21 of the Court Procedure Rules. It cannot be overlooked that later rules, such as r 21, are likely to have been written with the decision in J L Holdings in mind. The purposes stated in r 21 cannot be ignored. The Court Procedures Rules make plain that the Rules are to be applied having regard to the stated objectives of the timely disposal of the proceedings at an affordable cost. There can be no doubt about the importance of those matters in litigation in the courts of the Australian Capital Territory.
98. Of course, a just resolution of proceedings remains the paramount purpose of r 21, but what is a "just resolution" is to be understood in light of the purposes and objectives stated. Speed and efficiency, in the sense of minimum delay and expense, are seen as essential to a just resolution of proceedings. This should not detract from a proper opportunity being given to the parties to plead their case, but it suggests that limits may be placed on re-pleading, when delay and cost are taken into account. The Rule's reference to the need to minimise costs implies that an order for costs may not always provide sufficient compensation and therefore achieve a just resolution."
"Commercial life depends on the timely and just payment of money. Prosperity depends on the velocity of its circulation. Those who claim to be entitled to money should know, as soon as possible, whether they will be paid. Those against whom the entitlement is asserted should know, as soon as possible, whether they will have to pay. In each case that is because it is important that both the claimants and those resisting claims are able to order their affairs. How they order their affairs affects how their creditors, their debtors, their suppliers, their customers, their employees, and, in the case of companies, their actual and potential shareholders, order their affairs. The courts are thus an important aspect of the institutional framework of commerce. The efficiency or inefficiency of the courts has a bearing on the health or sickness of commerce."
In my view, the stage has been reached where costs orders are no longer a panacea for that prejudice. The learned Master fell into error by not properly applying r 21 to those provisions of the Court Procedure Rules which he considered or applied in the course of his decision of 4 February 2011. A just resolution of the appellant's claim requires that the respondent's defence be struck out and that judgment be entered for the appellant in the sum of $248,621.99 together with interest on that amount. The respondent's counterclaim should be severed.
I have given prior notice regarding the issue today being that I am unable to make it as I have work commitments out of state. Due to this I am writing to clarify and assure that the issue does not get dismissed and another date has been selected. If there are any issues regarding this, please don't hesitate to contact myself on the below. (sic)
If you want me to pay you, take me to court. We're not paying you.
All work carried out by you and your sons while you were there and that was inspected by our certifier passed without any ratification (sic) faults.
Krown Living Pty Ltd, Imran Cetinkaya and Ismail Cetinkaya
GORDON LANDO
KROWN LIVING PTY LTD & ORS
Legislation Cited: ACT Civil and Administrative Tribunal Act 2008 ss 6, 18, 19, 22
Subordinate
Legislation cited: Court Procedure Rules 2006 rr 1619, 1620, 2000, 2001, 2002, 2004, schedule 2
Cases Cited: Aon Risk Services Australia Ltd v Australian National University [2009] HCA 27; (2009) 239 CLR 175
Group Konstrukt Pty Ltd v Arrow International Australia Ltd [2012] ACTSC 14
(2009) 239 CLR 175