[2013] VCAT 488
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2013-04-10
For Mr P, Mr P, For Ms J, Ms J
Original judgment source is linked above.
Peter Boekel, J.O. Nixon, Diane Gibson, Jeffrey Travis Phillips, Tina Coventry, Robert and Joanna Rzechowka, Patricia Coyne, Elizabeth A Serpell and Michael James Cohn.
Glenhill Pty Ltd v Stonnington CC & Ors [2013] VCAT 488
Use and development for dwellings, shops and offices, reduction of car parking, new access to a Road Zone Category 1 and removal of easement on certificate of title volume 4535 folio 879.
Mr M Sheppard, Urban Designer, David Lock and Associates
Construction of a 7-storey building for shop, office and 48 apartments over basement car parking.
Application under Section 79 of the Planning and Environment Act 1987.
Clause 31.02: Use of land for a purpose specified in Section 2 of the land use table to clause 34.02 for B2Z.
Clause 34.02- Construction of buildings and works in the B2Z.
Clause 52.29: Create or alter access to a road in a Road Zone Category One [RZ1]
Clauses 10.04, 11.01, 11.02, 11.04, 15.01, 15.02, 16.01, 17.01, 18.02, 21.01, 21.02, 21.03, 21.04, 22.02, 22.05, 22.06, 22.12, 22.13, 52.06, 52.07, 52.29, 52.34 and 65.
Irregular site with an area of about 1050 square metres located on the northwest corner of Burke Road and Malvern Road Glen Iris. Two storey shops occupy land and neighbouring properties to the north, with a 3-4 storey office building to the west, church and residential to the east including medium density housing. Contextually, the land is located within a small Neighbourhood Activity Centre, with a tramline adjacent to both frontages and a train station to the north.
Workshop Architecture v Stonnington CC P1309/2012 28 March 2013
Is the height of the building acceptable having regard to the strategic and physical context of the land?
Encourage higher density housing in and around Neighbourhood Activity Centres that is designed to fit the context and enhances the character of the area while providing a variety of housing options for different types of households.
Will the proposed building detract from the significance of St Andrews Church?
Will the proposal result in unreasonable traffic impacts?
Will the proposal result in unreasonable impacts on the amenity of the area?
Use and development for dwellings, shops and offices, reduction of car parking, new access to a Road Zone Category 1 and removal of easement on certificate of title volume 4535 folio 879.
When approved, the plan will be endorsed and will then form part of the permit. Waste collection from the development must be in accordance with the plan, to the satisfaction of the Responsible Authority.
(a) details of hours of demolition and construction;
(b) methods to contain dust, dirt and mud within land, and the method and frequency of clean up procedures;
(c) protection measures for features of the land to be retained including vegetation, retaining walls, buildings, other structures and pathways;
(d) details of delivery and unloading points and expected frequency;
(e) details of a liaison officer for contact by residents and the Responsible Authority in the event queries or problems are experienced;
(f) details of the movement of construction vehicles to and from the land to avoid traffic hazards in and around the land;
(g) details of parking facilities for construction workers including using the basement for parking of construction vehicles;
(h) measures to minimise the impact of construction vehicles arriving at and departing from the land;
(i) an outline of requests to occupy public footpaths or roads, and anticipated disruptions to local services;
(j) the processes to be adopted for the separation, re-use and recycling of demolition materials;
(k) the measures to minimise noise and other amenity impacts from mechanical equipment and demolition/construction activities, especially outside of daytime hours; and
(l) measures to protect the stormwater drainage system so that no solid waste, sediment, sand, soil, clay or stones from the land enters the stormwater drainage system.
The Responsible Authority may extend the periods referred to if a request is made in writing before the permit expires or within three months afterwards.
[1] We have considered all submissions presented by the parties although we do not recite all of the contents in these reasons.
[2] Application for Review No. P1309/2012
Glenhill Pty Ltd
Stonnington CC & Ors [2013] VCAT 488