Review Jurisdiction - Planning Act 1999
The DCA found that two sets of maps existed at the time of the clearing. The EPBC map (submitted by DHA as part of application seeking environmental approval) with stages numbered, commencing at Stage 2 through Stage 6 and Map 2CRU (submitted by DHA as part of application seeking planning approval) with stages numbered commencing at Stage 1 through to Stage 5.
... following that breach of permit, DHA had worked with DAS to reach compliance with the Permit in respect of the subject clearing. DAS officers identified all necessary conditions precedent and, on 23 July 2024, confirmed that all clearances from the relevant authorities to enable clearing of stage 2 had been obtained. The "stage 2" clearing was then compliant with Permit conditions.
... clearing occurred as a result of miscommunication between DHA and the subcontractor, such misunderstanding being exacerbated by the existence of two separate sets of maps with different numbering of the stages involved.
could not be satisfied that the evidence obtained through the investigation established the requisite mental element under section 75B to prove the offence on the part of DHA as required by section 75B(2).[2]
Noting that the same facts and circumstances were relied upon in relation to the alleged breaches of Sections 75B and 75C and that a permit existed allowing the clearing of native vegetation, the DCA resolved to investigate the Complaint as an alleged breach of section 75B of the Planning Act.[4]
(1) A person must not use or develop land in a manner that is only permitted in accordance with a permit:
(b) subject to section 56(c), until all the conditions of the permit that must be complied with before the use is permitted have been complied with.
(a) the person intentionally uses or develops land; and
(b) the use and development is only permitted in accordance with a permit; and
(c) the use or development is not in accordance with the permit and the person is reckless in relation to that result.
(1) Land must not be developed by clearing it of native vegetation except in accordance with any of the following that applies in relation to the land:
(a) the person intentionally engages in conduct; and
(b) the conduct results in clearing of native vegetation on land and the person is reckless in relation to that result; and
(c) the clearing of native vegetation was not in accordance with:
(i) a permit or an interim development control order that applies to the land; or
(ii) if no permit or interim development control order applies to the land - a planning scheme that applies to the land.
(1) A person is reckless in relation to a result if:
(a) the person is aware of a substantial risk that the result will happen; and
(b) having regard to the circumstances known to the person, it is unjustifiable to take the risk.
(3) The question whether taking a risk is unjustifiable is one of fact.
(4) If recklessness is a fault element for a physical element of an offence, proof of intention, knowledge or recklessness satisfies the fault element.
If a physical element of an offence is committed by an employee, agent or officer of a body corporate acting within the actual or apparent scope of his or her employment, or within his or her actual or apparent authority, the physical element must also be attributed to the body corporate.
If intention, knowledge or recklessness is a fault element in relation to a physical element of an offence, that fault element must be attributed to a body corporate that expressly, tacitly or impliedly authorised or permitted the commission of the offence.
The ways in which such authorisation or permission may be established are enumerated in section 43BM(2).
"Preferable" is apt to refer to a decision which involves discretionary considerations. A "correct" decision, in the context of review, might be taken to be one rightly made. It is, inevitably, a decision by the original decision-maker with which the Tribunal agrees.
(4) The Tribunal must, in writing, determine an application for review of a determination of a consent authority by taking one of the following actions:
(a) confirming the determination of the consent authority;
(c) ordering the consent authority to issue or vary a development permit subject to any conditions the Tribunal thinks fit.
... it was reasonably foreseeable to DHA, being a well-resourced, informed, and sophisticated entity, which is experienced in land development and related approval processes, that a breach of the Permit could occur due to the inconsistent numbering in the 2CRU Staging Plan and the EPBC Masterplan when providing the instruction not to proceed to "Stage 3".[11]
In this case, DHA expressly told its contractor not to clear in the 'unpermitted' area. Consequently, it is unlikely that the contractor could be considered to have acted within the actual or apparent authority given to them by DHA.[14]
... proof beyond reasonable doubt is the highest standard of proof known to the law, and therefore requires a much higher state of satisfaction than proof on the balance of probabilities.
2. In proceeding 2025-00298-CT, there shall be no order as to costs.
[1] Letter from DHA to DCA dated 26 June 2024 at [46].
[2] DCA Statement of reasons in relation to decision under section 79A(1)(a)(ii) of the Planning Act regarding Lee Point Master-planned Urban Development, [5].
[3] DCA Statement of reasons in relation to decision under section 79A(1)(a)(ii) of the Planning Act regarding Lee Point Master-planned Urban Development, [7].
[4] DCA Statement of reasons in relation to decision under section 79A(1)(a)(ii) of the Planning Act regarding Lee Point Master-planned Urban Development, [2].
[5] Criminal Code of the Northern Territory, s 43BS(1).
[6] Criminal Code of the Northern Territory, s 43BK(1).
[7] Kasper v Psychology Board of Australia [No 2] [2015] NTCAT 179, [16]; Shi v Migration Agents Registration Authority [2008] HCA 31; (2008) 235 CLR 286, [140]-[142].
[8] Shi v Migration Agents Registration Authority [2008] HCA 31; (2008) 235 CLR 286, [140]-[142].
[10] Outline of Submissions on Behalf of the Respondent dated 6 June 2025, [10].
[11] Outline of Submissions on behalf of Kevin Quall, undated, [33].
[12] Outline of Submissions on behalf of Kevin Quall, undated, [32].
[13] Outline of Submissions on behalf of FOLP, undated, [70].
[14] Outline of Submissions on Behalf of the Respondent dated 6 June 2025, [37]. (Emphasis in original)
Friends of Lee Point Inc & Quall