[2009] VCAT 259
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2009-02-23
Original judgment source is linked above.
Planning and Environment; Farming zone; Erosion Management Overlay; Wildfire Management Overlay; Extractive Industry; Basalt quarry; Extractive Industry Interest Area; Noise from blasting, rock breaking, rock drilling, crushing, sifting and earth moving; Flyrock; Dust and air emissions from same sources; Surface and groundwater impacts; aquifers; Buffer distances to sensitive uses; Performance standards; Relationship of buffers to performance standards; Truck transport traffic impacts on surrounding road network; Conflicting land use values; Farming and agriculture; Tourism; Rural residential living.
Virginia Giles and Others and Ken Fraser and Others
Virginia Giles and Others and Ken Fraser and Others
Fraser v Baw Baw SC [2009] VCAT 259
The order of the Tribunal dated 19 January 2009 is corrected under the provisions of Section 119 Victorian Civil and Administrative Tribunal Act 1998 as follows.
Construction works on the site must only occur between 7.00 am and 6.00 pm Monday to Friday and 7.00 am to 1.00 pm Saturday (not including public holidays).
Deleting the words of the groundwater resource from Condition 53 Southern Rural Water - Potential Impact to Groundwater (i).
Fraser
Baw Baw SC [2009] VCAT 259