Foresight Construction Pty Ltd v MRW Plumbing Group Pty Ltd; MRW Plumbing Group Pty Ltd v Foresight Construction Pty Ltd
[2022] NSWCATCD 6
At a glance
Source factsCourt
NCAT Consumer and Commercial
Decision date
2021-08-24
Source
Original judgment source is linked above.
Judgment (13 paragraphs)
Background
- On or about 11 March 2018 Foresight Construction Pty Ltd engaged MRW Plumbing Group to provide plumbing installations and services to a site at XXX - XXX Botany Road Botany. The contract price was a lump sum of $272,800.00, although a quotation bearing a date 28 March 2019 disclosed a quotation price of $272,800.00 plus GST representing a total cost of $300,080.00.
- Schedule 3 of the contract document noted the construction was to commence from 11 March 2018 and to be completed by 1 December 2019.
- Between August 2018 and 31 October 2019 MRW Plumbing Group Pty Ltd rendered accounts to Foresight Construction Pty Ltd, and under the terms of the contract Foresight was entitled to withhold no more that 5% retention of the total value of the contracted works. The retained amounts were liable to be released to MRW Plumbing Group 13 weeks after practical completion of the works. On 1 November 2019 Foresight Construction Pty Ltd issued a Notice of Termination purporting to terminate the contract between the parties. On 6 November 2019 the solicitors for MRW Plumbing Group Pty Ltd wrote to the applicant's solicitors disputing that the contract was terminated, and claiming that the respondent's conduct amounted to termination of the contract. The repudiation was accepted, and the contract was thereafter regarded as at an end between the parties.
- Foresight Construction Pty Ltd initially commenced proceedings in the Tribunal seeking compensation for defective and incomplete work. A short time later MRW Plumbing Group Pty Ltd commenced proceedings in the Local Court seeking to recover retention payments. In August 2020 the proceedings commenced by MRW Plumbing Group Pty Ltd were transferred to the Tribunal by consent of the parties and both matters continued to be dealt with in the Tribunal.