[2025] NSWCATCD 98
General information, not legal advice.
NCAT Consumer and Commercial
2025-07-21
Original judgment source is linked above.
(1) Uneven distribution of the aggregate in the concrete slab;
(2) Damage to the surface of the polished concrete slab; and
(3) External bricks not installed and cleaned in accordance with manufacturer's instructions, resulting in mortar smeared across the face.
(1) Costs submissions by the builder dated16 February 2025;
(2) Costs submissions by the owner dated17 February 2025 with supporting documentation;
(3) Submissions in reply by the builder dated 2 March 2025;
(4) Letter from Leeds Lawyers, the builder's representative, dated 3 March 2025 confirming costs incurred;
(5) Submissions in reply by the owner dated 3 March 2025;
(6) Ten invoices filed by the builder on 14 March 2025.
(1) A text message from Mr Kulakovski, CEO of the builder, to the owner on 30 August 2023 was intended to coerce the owner against pursuing legal proceedings and informed the owner of his intentions to 'drain him of funds';
(2) The text message evidences the builder's intention to conduct the proceedings contrary to the Tribunal's guiding principle in s 36 of the NCAT Act;
(3) As a result of the text message, the applicant chose not to engage legal representation and conducted most of the proceedings himself, including drafting pleadings and instructing experts;
(4) Special circumstances therefore exist for the awarding of costs against the builder on an indemnity basis.
(1) Mr Kulakovski's message is not relevant to the issue of costs because punishment is not a proper purpose in an award of costs; the message is intemperate but not intimidatory; and on the owner's submission the message saved him costs;
(2) The Tribunal should not award costs associated with expert Mr Vavrica because, inter alia, the Tribunal rejected substantial portions of his report and the report did not advance the owner's case;
(3) The majority of the owner's claim failed and he is not entitled to any costs associated with the issues upon which he did not succeed.
(1) The proceedings were contained to 3 discreet claims, each comprising a roughly equal portion of the evidence and hearing time;
(2) The owner should pay the builder's costs of the failed claim for the brickwork, a claim that was without any proper foundation and the relief claimed was manifestly unreasonable;
(3) The owner should pay the builder's costs of the failed claim regarding the concrete slab, a claim that was not supported by appropriate evidence and was largely based on speculation by the owner's expert;
(4) The owner should pay no less than two-thirds of the builder's costs;
(5) Each party should pay its own costs referable to the damaged surface of the polished concrete slab because:
(a) The builder did not dispute that the polished concrete floor was defective; the only issue was the builder's liability for that damage;
(b) The builder did not dispute the scope of rectification which the Tribunal ultimately found to be necessary;
(c) The applicant pleaded a breach of the statutory warranties generally and failed to establish the breach which was the focus of evidence and submissions at the hearing;
(d) The owner ultimately failed to establish any fault by the builder.
(1) The builder's expert, Mr Brook, changed his evidence during the hearing, but there 'was no notice of the changed opinion and so the case that the applicant had to respond to was different to the case the applicant prepared for.'
(2) As a result the owner's second expert report by Mr Kenneth Whyte was 'not read' at the hearing;
(3) The builder breached the Tribunal's Expert Code of Conduct;
(4) The builder did not provide evidence of costs by way of invoices or receipts and the owner has thus been prejudiced in responding to the costs application;
(5) The builder's fees for the preparation of its claim against Polycrete Pty Ltd should be distinct from its costs incurred against the owner and the 'the wasted costs' for the revised opinion of Mr Brook should be excluded;
(6) Mr Kulakovski 'exerts unfettered authority' over the conduct of the builder;
(7) The Tribunal accepted Mr Vavrica's calculations regarding remediation costs 'with provisos';
(8) The respondent's submissions on costs should not be given weight.
33 It is not in dispute that the Tribunal has the power to apportion costs. The general approach is to order costs in favour of the successful party based on the outcome of the proceedings as a whole, without differentiating between particular issues on which the party may not have succeeded. However, a different costs order can be made if the losing party succeeds on significant issues: James v Surf Road Nominees Pty Ltd (No 2) [2005] NSWCA 296 at [31]-[36]; Sydney Ferries v Morton (No 2) [2010] NSWCA 238 at [10]-[12];
34 A court will generally only apportion costs where the successful party was unsuccessful in respect of an issue that was clearly dominant or separable: Elite Protective Personnel Pty Ltd v Salmon (No 2) [2007] NSWCA 373 at [6]; Bostik Australia Pty Ltd v Liddiard (No 2) [2009] NSWCA 304 at [38].
35 In Tomanovic v Global Mortgage Equity Corporation Pty Ltd (No 2) [2011] NSWCA 256; (2011) 288 ALR 385, Campbell JA (with Macfarlan JA and Young JA agreeing) held at [107] that an issue or group of issues is "clearly dominant" when it is clearly dominant in the proceedings as a whole. In that case, the approach by counsel to analysing the percentage of costs between the parties - counting the proportion of paragraphs and pages devoted to each factual topic - was held at [84] to be "a highly artificial way of proceeding" which gave "a false air of mathematical precision".
36 In relation to separable issues, a successful party's entitlement to the whole of the costs of the proceedings should not be discounted to allow for another party's success in a separate issue that played a very minor part in the proceedings as a whole: Macourt v Clark (No 2) [2012] NSWCA 411 at [7]. Further, in Hawkesbury District Health Service Ltd v Chaker (No 2) [2011] NSWCA 30 at [14], the Court of Appeal held that the severability of one issue on which the successful party failed is not, without more, sufficient to warrant departure from the general approach. The exercise of discretion will often depend upon matters of impression and evaluation: Elite Protective Personnel Pty Ltd v Salmon (No 2) [2007] NSWCA 373 at [11].
37 Where costs are apportioned, the nature and extent of the apportionment is discretionary. Mathematical precision is illusory: James v Surf Road Nominees Pty Ltd (No 2), citing Dodds Family Investments Pty Ltd v Lane Industries Pty Ltd [1993] FCA 259; (1993) 26 IPR 261 at 272.
38 Finally, where each party has had substantial success, a court or tribunal may make no order as to costs: Hogan v Trustee of the Roman Catholic Church (No 2) [2006] NSWSC 74 at [40].
(1) The issues relating to the uneven distribution of the aggregate in the concrete slab;
(2) The issues relating to damage to the surface of the polished concrete slab; and
(3) The issues regarding the external bricks not installed and cleaned in accordance with manufacturer's instructions, resulting in mortar smeared across the face.
(1) The owner was the successful party in relation to issue (2), the polished concrete. However, the owner was unsuccessful in relation to the other two issues; and
(2) The owner claimed $415,622.00 and received a significantly lower amount, $55,999.19.
(1) A hearing on the issue of costs is dispensed with under s 50 (2) of the Civil and Administrative Tribunal Act 2013 (NSW).
(2) Kyle Fish is to pay two thirds of the costs incurred by Kurmond Homes Pty Ltd in these proceedings, as agreed or as assessed on the ordinary basis.
(3) Kurmond Homes Pty Ltd is to pay one third of the costs incurred by Kyle Fish in these proceedings, as agreed or as assessed on the ordinary basis.
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.
Fish
Kurmond Homes Pty Ltd [2025] NSWCATCD 98;
(2011) 288 ALR 385
(1993) 26 IPR 261
(1998) 193 CLR 72