[2000] NSWLEC 130
Land and Environment Court (NSW)
1993-11-22
Lloyd J
Original judgment source is linked above.
CITATION : Environment Protection Authority v New Generation Beverages Pty Limited & Anor [2000] NSWLEC 130 No. 50084 of 1999
PROSECUTOR: Environment Protection Authority DEFENDANT: New Generation Beverages Pty Limited ACN 057 096 036 PARTIES : No. 50085 of 1999
PROSECUTOR: Environment Protection Authority DEFENDANT: Pepsi Seven-Up Bottlers Australia ACN 003 853 736 FILE NUMBER(S) : 50084 of 1999 & 50085 of 1999 CORAM: Lloyd J KEY ISSUES: Environmental Offences :- water pollution - acidic chemical spill - failure to install bunding to contain possible spills - no lasting significant environmental effects - guilty plea - separate defendants carrying on business in partnership - penalty Clean Waters Act 1979 s 16(1) LEGISLATION CITED: Crimes (Sentencing Procedure) Act 1999 s 22 Environmental Offences and Penalties Act 1989 s 8B Pollution Control Act 1970 s 241 CASES CITED: Axer Pty Limited v Environment Protection Authority, Court of Criminal Appeal, 22 November 1993, unreported; Environment Protection Authority v Timber Industries Limited [2000} NSWLEC 39, unreported DATES OF HEARING: 12/05/2000 EX TEMPORE 05/12/2000 JUDGMENT DATE :
PROSECUTOR: S C Simington (solicitor) SOLICITORS: S Garrett
LEGAL REPRESENTATIVES: DEFENDANTS: B J Preston SC SOLICITORS: Mallesons Stephen Jaques
IN THE LAND AND Nos: 50084 & 50085 of 1999 ENVIRONMENT COURT Coram: Lloyd J OF NEW SOUTH WALES Decision date: 12 May 2000
New Generation Beverages Pty Limited ACN 057 096 036 Defendant
Pepsi Seven-Up Bottlers Australia Pty Limited ACN 003 853 736 Defendant EXTEMPORE JUDGMENT
HIS HONOUR:
In the past the partnership had obtained advice from a firm known as "Phoenix" in respect of dangerous goods stored on the premises. Following receipt of the advice from Campbell Brothers Limited the partnership was satisfied that no further advice was required in respect of the storage of ferric chloride on the premises and no such further advice was obtained. Campbell Brothers Limited then delivered approximately 6000 litres of ferric chloride to the tank.
In the first week of November 1998 Mr Avgerinos noticed a slow leak of ferric chloride from the suction side of the ferric chloride pump line to the tank. Mr Avgerinos states that he had a conversation with an employee of the partnership in which it was said that it looked like a faulty fitting. Mr Gordon Clement was a person who at all relevant times was employed by the partnership as an operator and holds a trade qualification in fitting and whose duties include the repair of machinery at the premises. Mr Johnston requested Mr Clement to carry out the necessary repairs to rectify the leak noted by Mr Avgerinos. Mr Clement then removed a brass fitting which he saw was leaking. The fitting that he removed was directly connected to the pipe from the tank to the pump. In carrying out this repair Mr Clement noticed that the brass fitting that he removed had been leaking and was corroded. The partnership did not have a poly-fitting to replace the connector in stock so Mr Clement installed an identical brass connector fitting to replace the leaking fitting as an interim measure. He then advised Mr Johnston that a poly-fitting was required as he, that is Mr Clement, was not sure of the chemical make-up of the substance in the tank and was therefore not satisfied that a brass connector fitting was appropriate.
A stainless steel fitting was also on the pump line when Mr Clement installed the new brass connector. Mr Clement did not see any sign of corrosion on the stainless steel fitting in the same pipe-line. Mr Clement had no concern as to the stainless steel fitting because as he says it was stainless steel. Mr Clement did not make any inquiries as to whether the material in the tank was corrosive. When interviewed he conceded that he saw corrosion in the brass fitting which he had removed. He said that he was concerned about the corrosive prospects of the chemical but when he saw the stainless steel fitting there he thought it must be alright.
On or about 2 November 1998 Mr T Robinson, who was employed by the partnership in the same capacity as Mr Clement, installed a poly-fitting on the pipe-line which, I assume, was in place of the brass fitting that had been placed there by Mr Clement. Mr Robinson did not notice any corrosion of the stainless steel fitting. After installation of the poly-fitting Mr Avgerinos was satisfied that there were no longer any leaks from the system.
At about 5 am on 12 November 1998 an employee of the partnership was checking a clarifier located close to the tank which contained the ferric chloride but he did not notice any liquid leaking from the tank or any odour at that time. Mr Johnston arrived at work just prior to 7 am on 12 November and he immediately went to inspect the clarifier. He had his back to the tank for about fifteen to twenty minutes while he inspected the contents of the clarifier. When he turned round he noticed liquid leaking out of the hose connected to the tank. He immediately attempted to isolate the leaking hose. He closed a valve on the tank but that had no effect and the leak continued.
Mr Johnston found that the leak was coming from the stainless steel fitting, which had a hole in it. At about 7.25 am he closed a red butterfly valve at the outlet to the tank and that stopped further liquid coming out of the stainless steel fitting. He then went back into the premises to obtain a materials safety data sheet in respect of ferric chloride and to contact the plant manager. Mr David Cliff, an effluent technician employed by the partnership was notified by Mr Johnson of the leak. He came and saw that the leaked liquid had spread across concrete beyond a white fence to a gutter and that it was entering a drain. It had started to rain and the flow to the gutter increased. Mr Cliff had employees place "Autodry" bags in the gutter to dam the gutter and prevent flow into the drain.
Between 7.30 and 7.40 am absorbent material was spread to absorb the liquid that had leaked from the tank. Mr Johnston by that time had obtained the materials safety data sheet for ferric chloride which he then printed from the computer system of the partnership. Mr Johnston then went back to the area of the leak and saw that the material had entered a drain at the premises. He was advised that the drain went to storm water. Mr Cliff and Mr Johnston went to the unnamed tributary at Huntingwood Drive and saw that there was some discolouration in the water in the creek. Mr Cliff took a sample of the water to test for alkalinity. The pH was found to be lower than five.
The fire brigade was then contacted between about 7.45 am and 8 am and the prosecutor was contacted at about 8.10 am. The fire brigade arrived at the premises at about 8.25 am and commenced clean up activities. An officer of the prosecutor arrived at about 9.25 am. There was then heavy rain falling at that time. The officer of the prosecutor, Mr Durrington, saw a dark brown coloured liquid exiting out of the drain pipe at the head wall of Huntingwood Drive and into the creek.
An office of the fire brigade, Mr Tapper, took a pH reading of the water in the creek using a piece of litmus paper. The litmus paper was placed in the area of the creek that was coloured and the colour of the litmus paper matched a colour on a colour chart for the litmus paper that corresponded with a pH of two to three. A discussion took place between Mr Durrington and a number of fire brigade officers as a result of which the liquid within the subject premises was mixed with soda ash in an attempt to neutralise the pH of the material before it was released. Approximately 3.5 kilograms of soda ash was used in this mixing process. Mr Durrington noted that the tank was not located within a bunded area and that the metal connector to which I have referred had a corroded hole in it.
Thereafter the defendants arranged for a liquid waste tanker to empty the storage tank of ferric chloride and remove it from the premises. Mr Durrington took samples of water from various locations. The partnership has calculated that the amount of ferric chloride unable to be accounted for was approximately 200 litres. Ferric chloride has not since been stored on the premises.
In August 1998 the partnership had commenced the implementation of a chemical management system for the premises known as Chem Watch. The system consists of a customised data base of material safety data sheets relating to the specific chemicals used on the premises as well as a further data base of some other material safety data sheets. In addition, in order to ensure the effective implementation of the Chem Watch system key employees of the partnership were provided with training with respect to the system. The partnership has also since 12 November 1998 accelerated the full implementation of the Chem Watch system including training of employees in respect to the storage and use of chemicals. In particular, the partnership issued revised hazardous substances and dangerous goods procedures on the premises, it issued revised spills standard operating procedures and it issued revised emergency response procedures. Further employees of the partnership have been trained in the Chem Watch system.
Training has been carried out for the day and afternoon shift production technicians employed at the premises in respect of the revised hazardous substances and dangerous goods procedures. Further training has been carried out for all night shift production technicians, maintenance personnel and the remaining production technicians employed at the premises in accordance with the revised hazardous substances and dangerous goods procedures, and further training has taken place in respect of chemical safety and handling and new product instructions on hazards has been carried out for the plant manager of the premises and others.
Dr F Pablo, an exotoxicologist employed by the prosecutor, has furnished an affidavit which outlines the nature of the substance and the effect of what happened on the local environment. Dr Pablo states that ferric chloride is soluble in water, is used in various industrial processes including use as a coagulant and deodoriser in the treatment of industrial and municipal wastes and sewage. Ferric chloride reacts with water and produces a toxic and corrosive acid in the form of hydrochloric acid. When ferric chloride solution reacts with water in an open system such as in a creek or a river system the hydrochloric acid concentration in the solution will initially increase and be high for a while and will then gradually decrease with time. The acid in the solution does not build up to high concentrations because there are processes that lead to its gradual decrease. These processes are lost by evaporation and/or dilution in water. In effect, the concentration of acid will be high initially and gradually decrease with time as it evaporates or is diluted with the mixing flow.
Dr Pablo inspected the area on 6 July 1999 with Mr Durrington and noted that the bottom of the creek was natural sediment with occasional growth of grass. At the time of the visit the creek was dry. Samples taken upstream in the creek from the creek bed disclosed several species of worms, the larvae of flies, snails, gravid and immature leeches and dragon fly.
The ferric chloride solution which the defendants had on the premises was of a concentration of 41 to 43 per cent weight by weight of water. It is darker in colour than turbid water hence its presence in creek water would have been visible while at high concentration, but would have gradually blended in with the sediment colour with reaction and dilution as it flowed down the stream.
The concentration of acid in the original ferric chloride solution contained in the holding tank would have corresponded to a pH of 4.2. A pH of seven is considered neutral. Lower values than seven are acidic, higher values are basic. When the ferric chloride solution leaked from the holding tank at the subject premises Dr Pablo states that she would expect the solution would give rise to a distinct acid smell in the immediate vicinity. Initially upon release the pH of the solution would have temporarily decreased and would be likely to be as low as three. This I note is consistent with the measurement of the pH in the creek taken by the fire brigade officer.
In order to neutralise 200 litres of ferric chloride solution 42 per cent by weight of water, an amount of 78.5 kilograms of soda ash or sodium carbonate would have been required. Clearly a large amount of the ferric chloride that was spilt was not neutralised when it reached the creek and flowed downstream. Dr Pablo states that the normal pH of fresh water that supports a healthy aquatic life is 6.5 to nine. The decrease in pH values below 6.5 would certainly cause, in her opinion, adverse effects to any aquatic organisms present in the water column or in the sediment. Assuming that the volume of ferric chloride solution that spilled is 200 litres in order to achieve a pH of 6.1 and assuming no sodium carbonate was added, the dilution required would have been on the order of approximately 29 thousand cubic metres of water, equivalent to fourteen and a half times the volume of an Olympic size pool.
In her conclusion Dr Pablo notes that the pH of water would drop to values close to three initially because of the formation of acid and, as already noted, the increase in acid concentration in water would have acute adverse effects physiologically to aquatic organisms present in the creek. However she would expect that a mixing effect about the discharge point and some evaporation of generated acid as hydrochloric acid would somewhat alleviate the effects to aquatic organisms.
In considering the question of penalty I am required to have regard to the heads of consideration set out in section 241 of the Protection of the Environment Operations Act 1997. The first consideration is the harm caused or likely to be caused to the environment by the commission of the offence. I accept the submission of the defendant that the discharge did not occur for very long and that not all of the 200 litres that was lost was discharged into the drain which led into the creek. I note that the pH at the site of the discharge into the creek had returned to a level of 8.5 at 12.40 pm on the day of the spill which is relatively close to its normal range. Whether this was as a result of the rain which, I note, was described as heavy, or as a result of the soda ash that had been applied I do not know, or it may have been a combination of both.
The evidence shows that this is an industrial area and the particular waterway is a constructed channel. It was dry when inspected by Dr Pablo and is now affected by other earth works. The only evidence of plant life seen by Dr Pablo was grass, although I think it can be assumed that the fauna which she observed above the discharge point may have been present in the creek at the time of the discharge. The harm was temporary and I accept the submission of the defendant that it cannot be said that there is any evidence of serious or lasting environmental harm. I also accept the submission of the defendant that there is no evidence that the creek was valued for its aesthetic quality. That is to say, the effect of this incident on the environment was not one which was significant.
The next consideration is the practical measures that may be taken to prevent, control, abate or mitigate that harm. The defendant submits that it reasonably relied upon an expert external consultant, Mr Avgerinos, of Industrial Solutions Pty Limited. There was nothing in the initial data sheet furnished by Mr Avgerinos to the defendants to indicate that ferric chloride was corrosive. There was no evidence when Mr Clement was replacing the brass fitting of any corrosion on the stainless steel fitting which subsequently did corrode and gave rise to the leak. Mr Avgerinos, who had inspected the area, did not draw attention to the inappropriateness of the steel fitting. The defendant however was aware of some sort of a risk of a spill and gave consideration to the installation of some sort of bunding, either permanent or temporary. The internal memorandum to which I have referred shows clearly that bunding was considered but was rejected as being an expensive option. It is likely that had bunding been in place the spill would have been largely if not totally contained.
In Axer Pty Limited v Environmental Protection Authority , Court of Criminal Appeal, 22 November 1993, unreported, Mahoney JA said: The legislation does not seek merely to prevent deliberate or negligent pollution. It envisages that at least in many cases proper precautions must be taken to ensure that pollution does not occur. Experience has shown that it is not enough merely to take care, accidents will happen. The legislation envisages that in many cases care must be supplemented by positive precautions. Business must be arranged and precaution taken so as to ensure that pollution will not occur. .... I believe legislation of this kind contemplates that in general the costs of preventing pollution will be absorbed into the cost of the relevant industries and in that way will be borne by the community or by that part of it which uses the product which the industry produces. 33. In assessing the quantum of a fine considerations of this kind are to be taken into account. The fine should be such as will make it worthwhile that the cost of precautions be undertaken. I am therefore not prepared to accept that it was reasonable for the defendants to abandon the suggestion of bunding on the ground that it would be an expensive option.
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
43. This means that the formal orders are as follows:
1. The defendant is convicted of the offence as charged.
3. The defendant must pay the prosecutor's costs in the sum of $4475.
1. The defendant is convicted of the offences charged.
2. The defendant must pay a penalty in the sum of $7500.
3. The defendant must pay the prosecutor's costs in the sum of $4475.
Environment Protection Authority
New Generation Beverages Pty Limited & Anor