[2010] VCAT 439
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2010-03-16
Ms J, Mr J
Original judgment source is linked above.
Section 87A of the Planning & Environment Act 1987; Nillumbik Planning Scheme; Rural Conservation Zone; Amendment to Permit; Hockey Pitch; Additional Floodlighting; Non-School Use of Hockey Pitch; Extended Lighting Hours.
Jenny Seed and others, S A & J A Banks, B Fiit & H Moore, P & D Thomson
Eltham College v Nillumbik SC & Ors [2010] VCAT 439
Mr C Wren SC instructed by Mr M Croft of Gadens lawyers. Expert evidence was called from Mr T Marks, acoustic engineer of Marshall Day; Ms C Heggen, town planner of Fulcrum Town Planners; and Mr I Catt, lighting engineer of Catt Consulting Engineers. Evidence was also called from Dr D R Warner, principal of Eltham College.
Mr M Townsend of counsel for S A & J A Banks, B Fiit & H Moore and P & D Thomson. Evidence was called from Mr S Banks, Ms J Seed, Ms C Thompson & Mr B Fitt (all residents).
Ms J Gregory for Jenny Seed and others. Evidence was called from Mrs D Gregory and Mr J Salman (residents).
Application under Section 82 of the Planning and Environment Act 1987 (PEAct) seeking review of a decision to amend Permit 719/2006/06P.
Application under Section 80 of the PEAct seeking review of conditions included by the Council in its Notice of Decision to amend Permit 719/2006/06P.
Rural Conservation Zone. Environmental Significance Overlay (ESO1) (part).
The College is located on Main Road, just outside the Urban Growth Boundary, in Research. The hockey pitch is on the south side of the School campus, cut into the topography.
3 March 2010 including Nos. 51 & 55 Bells Hills Road. The locality was subsequently re-visited in the evening.
What are the site's physical context and planning contexts?
How has the Tribunal approached the question of existing use rights?
Would the additional light towers, hours of operation and potential non-school use of the hockey pitch create unreasonable amenity impacts?
Would the additional light towers, hours of operation and potential non-school use of the hockey pitch create traffic and parking problems?
Would the additional light towers create unreasonable landscape and environmental impacts?
[1] In reaching a decision we have considered all submissions, expert evidence, lay evidence and other material tendered and filed by the parties. We do not, however, recite all of that material in these reasons.
Eltham College
Nillumbik SC & Ors [2010] VCAT 439