[2010] VCAT 1827
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2010-11-15
Original judgment source is linked above.
Negotiations for a building contract, claim for refund of deposit, requiring owner to sign "separate contract", whether really separate, agreement for charge over land entitling the builder to lodge a caveat, ss18 and 31 of the Domestic Building Contracts Act1995, ss8, 9, 161, 163 and 159(1) of the Fair Trading Act 1999, failure to disclose a document to owner before meeting to sign it, misleading conduct, unconscionable conduct, failure to give documents requested, action for damages, refund of sums paid, ability of builder to retain sums representing amounts incurred by it, interest, rent, costs, request for an order that the builder change its practice in future.
Elliott v Simonds Homes Pty Ltd (Domestic Building) [2010] VCAT 1827
The Respondent must pay the Applicant $1,535.38 forthwith.
Simonds Homes Pty Ltd -Mark Sanna (Operations Manager)
NOTE: We hereby authorise Simonds Homes to order a soil test and survey on our behalf.
All prices are estimates only. Simonds Homes is not bound by the estimated price or representations set out in this form.
I remark that to avoid misleading potential customers, if what Simonds Homes intends to provide is a preliminary estimate rather than a quotation which a potential customer can accept, they should re-name this document.
Please Note: Deposit moneys will be applied by the builder towards the cost associated with preparation of your new home quotation and/or contract documents.
Subject to based price being approved @ $164,900 by management. If other wise deposit to be refunded [sic]
This was neither brought to my attention nor discussed during the hearing. I note that in both the Sales Advice Quotation and a similar eight-page document bound into the contract documents, item 1-1 describes the house type - the Stirling - which is priced at $164,900. It is hard to understand what comfort such a statement could give a customer, as this price is so substantially changed by other items. Nevertheless, it is clear that Simonds Homes acknowledged the possibility that there might be circumstances where the whole of the deposit might be refundable.
NOTE: $600 of the deposit is non-refundable once soil and survey information has been ordered.
acknowledge that we are now or may at any time hereafter be or become liable to pay to the Company on any account whatsoever money ("the sum") for services rendered and materials supplied to us, details of which have previously been supplied by the Company.
In consideration of the Company not demanding immediate payment today of the sum owing to it by us we jointly and severally agree as follows:
"An event of default" where referred to above means any failure to pay when due any sum owed to the Company by us or any failure to meet any terms, covenants or conditions contained in any contract or agreement between us and the Company.
I, Dean Simpson Elliott of ... hereby undertake to Simonds Homes that I will not in any manner reproduce the proposed building contract for the above Lot between us as supplied to me by the Builder on 16/6/10 and undertake to return it to Simonds Homes, South Morang office no later than Thursday June 23, 2010 COB.
Mr Elliott's copy of this document has a note on it in his handwriting: "Returned 23.6.10@ 2:12pm" and his initials. I accept Mr Elliott's evidence that he was true to his word and did not copy any part of the contract documents, but got the words of the Caveat agreement by searching the Internet.
I am deeply surprised that ordinarily your company does not release their documentation so proper legal advice can be sought if a customer would like to obtain it. To ask customers to complete seeking such advice within a 5 day cooling off period is wholly unacceptable to me, in view of the large amount of money involved. ... Please note that I will require any future modified contract for a few days as well, in order to properly assess it.
The open-ended, arbitrary and unfair "[Caveat] agreement" allowing Simonds to lodge a caveat over the land ... will not be signed by me under any circumstances ... I was not provided with a copy of this document when I requested a copy of Simonds' contract from the sales person. I was also not provided a copy of this document in the package sent from your office subsequent to my paying a $1500 deposit.
This requirement must remain and is non-negotiable.
Item 11 of schedule 1 notes that the finance approval amount is to be $0.00. This amount should reflect the contract price, or a worded amount sufficient to discharge my obligations under the contract, thereby rendering the entire contract subject to FINAL finance approval of an appropriate amount to pay for it. I am currently the holder of a finance pre-approval only.
Cost Item 2-14 This item is unacceptable, and excessive. The risk of double-handling should be borne by the organisers of the building site, ie the builder. The block is not unusual enough to warrant such a charge.
This item will need to remain as featured in the Contract and is not negotiable.
My established budget for this project is $187000.00, which is based on the relevant sales consultant's estimate ($183876.00) plus about $3000.00 for upgrades. Note this EXCLUDES a provision for the discovery of large formations of rock during the excavation process, which I regard as reasonable and standard in building contracts. The current total of the contract offered to me actually and potentially exceeds this total, primarily due to the "provisional" or unacceptable additions to the site cost [cost item 2-14] as detailed above. For me to accept the cost component of our proposed contract, the total cost will have to be reduced to $187000.00 or less. I have identified some upgrade items I can do without ... Note that meeting my cost concerns does not mitigate my other concerns as outlined above.
I hope that our proposed contract can proceed, but note that I will not consider entering into a contract with Simonds until the above concerns, and any others I may find in any subsequent proposed contract have been mitigated.
With great regret, we are not able to reach agreement and the project appears to be dead in the water. The primary cause of this is Simonds' ongoing requirement to sign the [Caveat agreement] ...
The only remaining question is the return of my deposit. Were I shown a copy of the [Caveat agreement] I would be presumed upon to sign prior to making a deposit, I can assure you I would not have made such deposit, therefore regard that money as having been dishonestly obtained. This leads me to expect its return in full by cheque. If the management of Simonds resists this statutory requirement of theirs, I can and will take the time to prepare a very detailed account of your companies' contracting procedures to relevant third parties and construction industry oversight bodies. Please inform me of any procedures I am expected to undertake to facilitate this.
Refusal to provide the contract before the signing date
Refusal to allow Mr Elliott to copy contract documents and the "guarantee" document
To be used for double handling or hand carting of materials, providing access to building area where access is limited due to wet site conditions or restricted access or overhand laying of bricks to wall/s near boundaries.
It is the same provision to which Mr Elliott had objected in his e-mail of 21 June 2010.
Contract does not entitle builder to put caveat on the title of building site land
A domestic building contract does not give a builder an estate or interest in any land for the purpose of section 89 of the Transfer of Land Act 1958.
(1) A builder must not enter into a major domestic building contract unless the contract-
(b) sets out in full all the terms of the contract; and
(j) states the contract price or, in the case of a cost plus contract, how the amount that the builder is to be paid is to be determined; and
(1) A person must not in trade or commerce, in connection with the supply or possible supply of goods or services of a kind ordinarily used for personal, household or domestic purposes to a purchaser, engage in conduct that is, in all the circumstances, unconscionable.
(2) Without in any way limiting the matters to which a court or the Tribunal may have regard for the purpose of determining whether a person has contravened subsection (1), a court or the Tribunal may have regard to-
(b) whether, as a result of conduct engaged in by the supplier, the purchaser was required to comply with conditions that were not reasonably necessary for the protection of the legitimate interests of the supplier; and
(d) whether any undue influence or pressure was exerted on, or any unfair tactics were used against the purchaser ...[Mr Elliott's emphases]
(1) A person must not, in trade or commerce, engage in conduct that is misleading or deceptive or is likely to mislead or deceive.
If a purchaser or a prospective purchaser of goods or services asks the supplier for a document containing particulars of the goods or services, the supplier must give the purchaser or prospective purchaser a document ... which contains-
(c) any particulars or information in relation to the goods or services which have been asked for by the purchaser or prospective purchaser
(1) A person who suffers loss, injury or damage because of a contravention of a provision of this Act may recover the amount of the loss or damage or damages in respect of the injury by proceeding against any person who contravened the provision or was involved in the contravention.
(1) Subject to this Division, each party is to bear their own costs in the proceeding.
(2) At any time, the Tribunal may order that a party pay all or a specified part of the costs of another party in a proceeding.
(3) The Tribunal may make an order under subsection (2) only if satisfied that it is fair to do so, having regard to-
(a) whether a party has conducted the proceeding in a way that unnecessarily disadvantaged another party to the proceeding by conduct such as -
(i) failing to comply with an order or direction of the Tribunal without reasonable excuse;
(ii) failing to comply with this Act, the regulations, the rules or an enabling enactment;
(iii) asking for an adjournment as a result of (i) or (ii);
(iv) causing an adjournment;
(v) attempting to deceive another party or the Tribunal;
(vi) vexatiously conducting the proceeding;
(b) whether a party has been responsible for prolonging unreasonably the time taken to complete the proceeding;
(c) the relative strengths of the claims made by each of the parties, including whether a party has made a claim that has no tenable basis in fact or law;
(e) any other matter the Tribunal considers relevant.
Requested order that Simonds Homes disclose the separate agreement in future
[1] The checklist is a requirement of 31(r) of the Domestic Building Contracts Act 1995.
Elliott
Simonds Homes Pty Ltd