[2005] VSCA 36
Court of Appeal (Vic)
2005-02-28
WINNEKE, P., CHARLES and PHILLIPS JJ.A.
Original judgment source is linked above.
REFER [2005] VSCA 27
Contract - Equity - Fiduciary duties - Agreement for joint venture and profit sharing - Agreement terminated upon alleged repudiation - Project being still pursued by some of the joint venturers - Whether others free to seize the project for themselves - Whether fiduciary duties still owed - Remedies - Equitable compensation - Proper measure.
Real property - Torrens system - Caveat - Caveat lodged to protect claim to constructive trust - Proceeding commenced to remove caveat - Land sold while litigation pending - Caveator held to have no interest - Whether caveat lodged without reasonable cause - Whether damage suffered upon sale - Measure of compensation - Transfer of Land Act 1958 s.118.
"The parties were agreed on appeal that the amount in question was $800,000 and the question was whether that sum should have been deducted from what otherwise was the profit for division between the appellants and the respondents. The judge said not and the appellants contended that that was error."
That identified the issue, but his Honour continued:-
"During argument even this point of dispute was resolved; for Mr. Scerri announced that his clients now agreed with the appellants that the sum of $800,000 ought to have been deducted from what otherwise was the found profit of $4,990,562 before calculation of the four-sixths which was due to the respondents[1]."
[1] The amount of $4,990,562 is found in paragraph [42] of the trial judge's reasons for judgment, 3 December 2002.
[2] This "basic amount" was an agreed sum, subject to certain disputed items which the trial judge addressed in turn. It was a calculation of both operating profit and capital profit as a single sum: reasons for judgment, 3 December 2002, paragraph [7].
[3] The memorandum was handed up by Mr. Sher on 9 November and it was on 10 November that Mr. Scerri made the concession now called into question.
[4] Reasons for judgment 22 February 2005, paragraphs [66], [67].