austlii:vic/VBAB/2019/18
appellant. The decision of the Respondent to refuse to issue an occupancy permit was quashed. The Respondent was ordered to issue an occupancy permit within 3 business days. Consistent orders made in 12...
A building surveyor refused to issue an occupancy permit for a new house because it had a slotted eaves gutter system, which he believed did not comply with plumbing standards. The owners appealed. The Building Appeals Board found that expert evidence showed the gutter system actually performed better than the minimum standards required, even if it wasn't specifically listed in the standard documents. The Board ordered the surveyor to issue the occupancy permit, ruling that the system complied with the performance requirements of the plumbing code. The same decision applied to 12 other similar cases.
AI-generated legal information, not legal advice. Zoe can make mistakes. Check the cited source, and for advice about your situation consult a qualified Australian lawyer.
1 cited instrument linked from this judgment.
APPEAL - Application under s 138 of the Building Act 1993. Whether slotted eaves gutter complies with the National Construction Code 2016; Inconsistency between Volume 2 and Volume 3 of the National Construction Code 2016. Whether slotted eaves gutter satisfies the performance requirements under Volume 3 of the National Construction Code 2016.
RESPONDENT Steve Maloney (Relevant Building Surveyor)
FIRST INTERESTED PARTY Victorian Building Authority
SUBJECT LAND 1-3 Elise Road, Caroline Springs, Vic, 3222
BEFORE Eric Riegler (Chairperson), Sharon Houlihan and Warren Knight (Members)
_______________________________ ________________________________
Vic D1.2 General Requirements
(1) The design, construction, installation, replacement, repair, alteration and maintenance of a roof drainage system must be in accordance with AS/NZS 3500.3.
Deemed to satisfy water overflow per meter from gutter (L/s/m)
Possible water overflow per meter from gutter (L/s/m)
% of provided overflow required for deemed to satisfy solution
The overflow capability of the high fronted slotted Quad Gutter 115 is greater than the deemed to satisfy as referenced in AS3500.3.
It is therefore demonstrated that the NCC Performance Requirements, DP 1.2 Overflow Devices or Measures have been satisfied with the exception of roof sub-catchment 'G'.
Roof sub- catchment 'G' will be provided with the deemed to satisfy overflow provision, namely a 10 mm gap between the gutter and the facia.
Eade
Maloney [2019] VBAB 18;
The decision of the Respondent to refuse to issue an occupancy permit was quashed. The Respondent was ordered to issue an occupancy permit within 3 business days. Consistent orders made in 12 associated proceedings.