austlii:cth/FWCA/2025/2008
General information, not legal advice.
FWCA
2025-06-17
Original judgment source is linked above.
The attached document wholly replaces the document previously issued with code [2025] FWC 1675 to correct document referencing.
s.185 - Application for approval of a single-enterprise agreement
Dunmore Sand & Soil Pty Limited Trading AS Dunmore Sand & Soil (DSS)
Application for approval of the Dunmore Sand & Soil Enterprise Agreement 2024
[1] This decision concerns an application for approval of the Dunmore Sand & Soil Enterprise Agreement 2024 (the Agreement). The application has been made under section 185 of the Fair Work Act 2009 (the FW Act) by Dunmore Sand & Soil Pty Limited (the Applicant). The Agreement is a single enterprise agreement. The Fair Work Commission must approve the Agreement if the requirements in sections 186 and 187 of the FW Act.
[2] The Agreement that accompanied the application did not comply with the signature requirements (see section 185(5) of the FW Act, and Regulation 2.06A of the F_air Work Regulations 2009)._ That is because the Agreement that accompanied the application was not signed by the employer covered by the agreement or by at least one representative of the employees covered by the Agreement. An amended signature page was subsequently filed. In accordance with section 586(b) of the FW Act, I waive this irregularity.
[3] The material filed in support of this application was solely from the Applicant. Based upon that material, each of the other requirements of the FW Act that are relevant to this Agreement are satisfied.
[4] The Agreement is approved and, in accordance with section 54 of the FW Act, it will operate from 24 June 2025. The nominal expiry date of the Agreement is 30 June 2028.