CITATION : DrillTec v Campbell [2002] NSWSC 1173 CURRENT JURISDICTION: Equity FILE NUMBER(S) : SC 50006/02 HEARING DATE(S) : 05/09/02, 18,19 November 2002 JUDGMENT DATE : 10 December 2002
PARTIES : DrillTec Gut GmbH Grossbohr-und Umwelttechnik v Allan Stuart Campbell JUDGMENT OF : Acting Justice Macready at 1
NC Hutley SC & S Pritchard for plaintiff COUNSEL : MD Young for defendant RG Forster SC for Lucas Group Clayton Utz for plaintiff SOLICITORS : Minter Ellison for defendant Boyd House & Partners for Lucas Group CATCHWORDS : Guarantee and indemnity. Application to strike out paragraphs of defence - construction of agreement - whether common surety agreement was concluded rather than a guarantee on first demand - abuse of process - partial invalidity. - International Law. Forum non conveniens - coincidence of issues - breach of exclusive jurisdiction clause - submission to jurisdiction by commencement of proceedings. Cross claim stayed so matter could be resolved in German court. Lumley General Insurance Ltd v Oceanfast Marine Pty Ltd [2000] NSWSC 1178 Regie National Des Usines Renault SA and Renault Automobiles SA v Zhang (2002) 187 ALR 1 CASES CITED : Henry v Henry (1996) 185 CLR FAI General Insurance Company Ltd v Ocean Marine Mutual Protection & Indemnity Association Ltd (1997) 41 NSWLR National Commercial Bank v Wimborne (1979) 11 NSWLR DECISION : Paragraphs 67 & 68
50006/2002 DRILLTEC GMBH GROSSBOHR-UND-UMWELTTECHNIK v ALLAN STUART CAMPBELL JUDGMENT 1 His Honour: There are before me the hearing of three notices of motion. The first in point of time is a motion filed on 10 July 2002 by the plaintiff. That motion seeks summary judgment against the defendant and dismissal of the first cross-claim to the extent that that cross-claim is brought by the defendant against the plaintiff. The balance of the relief on the motion is not pressed. The second is by the plaintiff on 23 July 2002 which claims a series of relief in respect of the second cross-claim. In essence the claim is for a stay of that cross-claim on the basis of forum non conveniens. Only the relief in paragraph 3 is now pressed. The third motion is one brought by the defendant filed on 30 August 2002 in which the defendant seeks to amend its first cross-claim. 2 At the commencement of the second days hearing the plaintiff abandoned the hearing of the claim for summary judgement and instead it sought dismissal of various defences propounded by the defendant. The amended motion was filed on 18 November. The motions have been heard together with the evidence in one as evidence in the other. Although the defendant's motion to amend it's first cross-claim should logically be the first determined it is necessary to hear all motions together in order to see whether the matters that are raised by the amendment will give rise to a relevant defence that may be propounded at the present time. The nature of the proceedings 3 The plaintiff sues the defendant to recover the sum of Euro 766,937.82. The claim is based upon a guarantee given by the defendant dated 8 June 2001. It was given as part of a settlement of disputes between the plaintiff and a number of companies compendiously described in the pleadings as the Lucas Group. Some of those companies and the plaintiff became involved in a joint venture that carried out construction work drilling tunnels in Hong Kong. 4 The agreement of 8 June 2001 is referred to as a settlement agreement. The agreement is in German and was entered into in Germany as a result of discussions to resolve differences between the parties. The parties were both represented by their German lawyers. There are a number of provisions in the agreement. The one upon which the plaintiff sues in these proceedings is clause 7. That is in the following terms: -- "Mr Allan Campbell hereby accepts for Drilltec's above-mentioned claims against Lucas an irrevocable, absolute guarantee for a maximum amount of being DEM1,500,000 which is effective for an unlimited period of time and becomes payable at first call. Drilltec undertakes not to call Mr Campbell's guarantee before 01.10.2001, should the above-mentioned claims not have been paid by Lucas by that date." 5 Mr Campbell, the defendant, is the chairman of directors of AJ Lucas Group Ltd the public company which heads the various Lucas companies. 6 Another clause in the agreement to which reference will be made is clause 12. That is in the following terms: -- "This agreement is exclusively subject to German law. The place of jurisdiction for all disputes shall be Munich, Germany, for both parties." 7 The agreement provided for the future hire of equipment to complete projects and the hire agreement which applied also contained a jurisdiction clause in the following terms: "14. Place of fulfilment and jurisdiction 14.1 The place of fulfilment is -- at the lessors option -- 07751 Munchen. The place of fulfilment for payments shall always be Munchen, Germany. 14.2 The place of jurisdiction for all disputes, including any dispute concerning the formation and validity of the contractual relationship, and particularly claims arising from bills exchange or cheques, shall be Munchen, Germany for both parties. 14.3 German law will be solely applicable." 8 It appears that clause 12 governs jurisdiction between the companies who are parties to the settlement agreement but does not bind Mr Campbell in his personal capacity. I will return to this aspect later but it is clear that it is for this reason that the plaintiff has sued on the guarantee in New South Wales. 9 In his further amended defence filed on 5 September 2002 the defendant raises the following matters of defence:
(i) That Dr Prell who signed the settlement agreement on behalf of Mr Campbell had no authority to do so.
(ii) That the defendant was a non-merchant who was unfamiliar with the German concept of surety on first demand and that in such circumstances by operation of law only a common surety agreement was concluded.
(iii) That there were no monies due by the Lucas Group to the plaintiff.
(iv) In the event that the agreement is held to be binding as a guarantee on first demand there can be raised the German defence of abuse of process in respect of the liability of the Lucas Group to the plaintiff.
(v) Various matters concerning the jurisdiction clause to suggest that the guarantee under German law is invalid. 10 The defendant admits that there has been an appropriate demand on the guarantee and that it has not made payment. 11 By his first cross-claim which was filed on 7 June 2002 the defendant sued the plaintiff and the various companies in the Lucas Group. This cross-claim in part repeats the defences, or some of them, and as against the Lucas Group seeks indemnity pursuant to a deed of indemnity dated 1 May 2002 between the defendant and the various companies in the Lucas Group. The amendment which is sought to be made to that first cross-claim refers to the second cross-claim for damages by the Lucas Group against the plaintiff and seeks to obtain declaratory relief which has the effect of bringing into the present proceedings an action for recoupment. Under German law an action on a guarantee of first demand is one in which only very few defences are allowed to be raised. The principle underlying that form of guarantee is that payment must be made once a demand is made and any defences, such as a denial of the underlying indebtedness, must be left to later proceedings commenced by the guarantor after he has made payment. The second proceedings are referred to as recoupment proceedings. 12 The second cross-claim was filed pursuant to orders made by Bergin J in a contested application for leave to file that cross-claim out of time brought by two of the companies in the Lucas Group against the plaintiff. The claim refers to the three separate commercial transactions between various parties. One is a joint venture for the purposes of providing horizontal directional drilling equipment and services to Lucas Hong Kong for what is known as the CLP Project. The second is a joint venture sub contract known as Skanska sub contract. The third transaction is what is known as the CLP hire agreements for the provision of drilling equipment and services by the plaintiff to the Lucas Group. This last claim is based upon the settlement agreement of 8 June 2001, which provided for abandonment of the joint venture and its replacement with new provisions for the hire of the relevant equipment at what were probably commercial rates. The first two claims are thus alternative claims in the event that the settlement agreement is found to be invalid. The cross-claim alleges various breaches of each of these three separate commercial arrangements and claims damages totalling HK$31,273,513.52. It is this cross-claim which is the subject of the plaintiff's stay application. 13 In addition to the Australian proceedings there are also proceedings commenced by the plaintiff on 1 October 2001 in the Munich District Court in the Commercial Chamber against the Lucas Group of companies. The defendant is not a party to these proceedings. The claim is for the recovery of various amounts plus interest pursuant to the agreement of 8 June 2001. The Lucas companies filed a challenge to the jurisdiction of the Munich District Court on 24 May 2002. On 2 July 2002 the court dismissed the interlocutory challenge and directed a defence to be filed. In its reasons the court noted that the invalidity of the jurisdiction agreement vis-a-vis Mr Campbell which was based upon the fact that he is not a merchant and did not cause the jurisdiction agreement between the parties (Drilltec and the Lucas Group) to become invalid. It is the clear that the questions of jurisdiction can still be argued at a final hearing because the conclusion was expressed to be "without anticipating a final decision". The application that was before the court was that there should be a special hearing with regard to local jurisdiction. It was this application that they dismissed. The plaintiff's claim to strike out parts of the defence 14 The plaintiff's change of position in respect of the summary judgment application was said to be as a result of the filing of further expert evidence which dealt with the authority of a Dr Prell who executed the settlement agreement on behalf of the defendant. Leaving aside the paragraphs in the defendant's contentions in the further amended defence filed on 6 September 2002 which dealt with the authority of Dr Prell it sought to strike out the balance. The actual paragraphs sought to be struck out were paragraphs 4 (f), 6, 8, 11 except to the extent that it repeats paragraph C, 4 (a) to (e), 12 (b), 13, 14, and 15. I turn to each of these matters. Paragraph 4 (f) 15 The relevant paragraph in the defence is as follows: "Even if, which is denied, there was a valid guarantee or valid agreement dated 8 June 2001, the alleged guarantee only applies to the claims set out in clause 3 of the agreement." 16 It is apparent that that this defence is a matter of the construction of the terms of the settlement agreement. In order to consider the arguments which are advanced it is necessary to set out the relevant parts of the settlement agreement. During the period of the hearing all submissions were based upon a version of the settlement agreement that is exhibit D. There are different translations of the settlement agreement in evidence. Although reference was made to this difference in the defendant's submissions on this aspect I will first deal with it as a matter of construction having regard to the settlement agreement which the parties themselves adopted in argument before me namely ex D. The parties to the agreement were the three Lucas companies described as joint and several debtors and referred to in the agreement as "Lucas", Mr Alan Campbell and the plaintiff "Drilltec". The recitals to the agreement were in the following form: "Preliminary Remarks: There have been disputes between the parties in relation to the establishing and handling of a joint venture project in Hong Kong on behalf of Skanska International Civil Engineering AB. From this project as well as from the so-called Watermains Project Drilltec has claims against Lucas. Lucas was a shareholder in Drilltec, holding 42.5%. By agreement dated 08.06.2001, Lucas sold and assigned these shares to its co-shareholder Max Streicher KG. The parties therefore make the following Agreement in order to settle the disputes between them. 17 The relevant terms of the agreement were as follows: 1. All oral and written agreements on a joint venture for the fulfilment of the order received through the agreement between Lucas and Skanska International Civil Engineering AB made on 08.09.2000, the so-called CLP Project, are hereby cancelled. There are thus no more reciprocal rights and obligations from the joint venture, with the exception of Drilltee claims against Lucas arising from the hiring of staff, drilling equipment and other equipment and services. Drilltec thus has no more claim/no more entitlement to the so-called completion fee in the amount of DEMI,000,000.00 or the partial amount of DEM550,000.00 from the re-invoicing of costs for the double shift of the 400 t rig. 2. For future hiring of staff, drilling equipment and other equipment, the parties make the following separate hire agreement:- 411 Annexure 1: General Conditions of Hire Annexure 2: Special Conditions, Drilitec 260 t rig Annexure 3: Special Conditions, Drilltec 400 t rig. Annexures 1, 2 and 3 form an integral part of this Agreement. Following expiry of the hire agreements, Lucas undertakes to issue without delay all declarations required to export the devices from Hong Kong such as customs declarations, shipping orders, etc. The services already invoiced by Drilltec shall be re-invoiced on the basis of the new charge rates in order to offset the difference to the charge rates agreed on for the joint venture. This means that the resulting difference to the amounts already invoiced will be additionally invoiced.
The Munich proceedings have only been expanded because of unavoidable delays;
The defendant Mr Campbell seeks to agitate the counterclaim and he not being a party to the Munich proceedings must do it in New South Wales;
Section 78 of the Supreme Court Act gives a right to cross-claim and the court can fashion its procedure to deal with such claim as justice requires. This allows the court flexibility in dealing with the alternative claims expressed in the cross claim;
It is the case that the action on the guarantee will have to be heard here in New South Wales. There is thus a need for witnesses from Germany to attend.
It was suggested that as a result the cross-claim should be allowed to proceed and should be put into an early directions list with a snappy timetable to deal with it as quickly and as expeditiously as possible. 64 The problem with the submissions are that they ignore the true nature of the claim that has been brought by the plaintiff in these proceedings. As I have pointed out several times before it is a claim for summary relief pursuant to a guarantee on first demand which should be dealt with quickly and promptly according to the substantive law. It is interesting to note in Justice Holland's summation of the principles on submission to jurisdiction the plaintiff opens himself to every cross-claim necessary "in order to do justice between the parties in relation to that subject matter". The subject matter of the plaintiff's claim has clearly been limited to a short and concise point. In this regard I note that Holland J in National Commercial Bank v Wimborne at 174-175 went on to say:- "It is not necessary in the present case to decide whether, having regard to the problems of executing a judgment against the property of a foreign Sovereign, the last-mentioned type of counter-claim would lie against a foreign Sovereign; but see Duff Development Co Ltd v Government of Kelantan [1924] AC 797 at 810, 817, 819, 821, 829, 833. As I have earlier indicated, I think that the basis of a correct view of the matter lies in the question: To what has the plaintiff submitted? The answer to that lies, I think, in a consideration of what the plaintiff has brought to the Court for adjudication. He could not, in my opinion, properly be said to have submitted to claims outside of and independent of the subject matter of his own action.
In an endeavour to illustrate the limits upon the kind of counter-claim that would be open to a defendant, counsel for the plaintiff referred to a number of decisions applying statutory provisions or rules entitling defendants to apply in the plaintiff's action for all such relief against the plaintiff or third parties "as related to or was connected with the subject of the cause or matter": eg, Judicature Act 1873 (UK) , s 24(3). These showed that a mere connection with the facts of the action or a party to it was insufficient to satisfy the test if the cause of action was distinct and independent. I will mention the cases but I do not think it necessary to deal with them: S F Edge Ltd v Weigel (1907) 97 LT 447; Barber v Blaiberg (1882) 19 Ch D 473; Harris v Gamble (1877) 6 Ch D 748 and Padwick v Scott (1876) 2 Ch D 736."
65 Accordingly, it seems to me, that given the limited submission in this regard, the plaintiff should not be deprived of the consideration by the Court of the discretionary factors in deciding whether or not to stay the proceedings. Other discretionary reasons 66 The other discretionary reasons did not play a great part in the submissions or evidence before me. The subject matter of the construction contract was construction work in Hong Kong. One party to the dispute and it's relevant officers are in Germany and the other party and it's relevant officers are mainly in Hong Kong and Australia. There is no suggestion that in Germany there would be any different delay in dealing with the matter. Importantly the cross claimant has identified no personal or judicial advantage which it would lose if it was forced to litigate in Germany. Conclusions. 67 Although there is doubt about the jurisdiction submission at this stage the German court has on an interlocutory basis refused to divest itself of jurisdiction. The Court in Munich is, also like this Court, seized of the whole dispute between the parties. When one has regard to the subject matter of the dispute, namely, a construction contract performed in Hong Kong, there is no particular connection which makes it imperative to deal with it in a particular place. The proceedings in Munich were commenced first and are equally advanced as this Court in terms of completion of the proceedings. The hearing of the cross claim will no doubt be long and complex. In this State the cross claim would most likely be referred out to a Referee to deal with a substantial part of the hearing. By virtue of the nature of the issues the length of the hearing would be considerable in contrast to the hearing of the plaintiff's claim which can be brought on promptly. In these circumstances it seems to me that the proceedings should proceed in Germany and, accordingly, the second cross-claim should be stayed. Orders of the court 68 Because of the way in which the pleadings have progressed it may be of assistance to the parties to bring in short minutes to provide for the carrying into effect of this judgment. The parties may wish to have at the same time amended pleadings to reflect the current status of the matter. I will be happy to give directions for the further preparation of the matter for hearing and hear arguments on costs.
Last Modified: 12/11/2002 DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
DrillTec
Campbell
(2002) 187 ALR 1
(1996) 185 CLR 571
(1997) 41 NSWLR 559
(1990) 171 CLR 538
(1950) 81 CLR 502
(1988) 165 CLR 197
(1996) 71 ALJR 156
(1979) 11 NSWLR 156