[2017] VCAT 1402
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2017-09-15
Original judgment source is linked above.
Building Act 1993 - Section 182A - review of finding made by Building Practitioners Board not to hold an inquiry into the professional conduct of a registered builder practitioner - relevant factors to consider - whether findings in a civil proceeding relevant to the Tribunal's discretion - whether the Victorian Building Authority is able to conduct an inquiry where the Building Practitioners Board had decided not to conduct an inquiry.
Draper v Building Practitioners Board (No 2) (Review and Regulation) [2017] VCAT 1402
178 Inquiries
(1) Subject to section 179A(2), the Building Practitioners Board may conduct an inquiry about the conduct or ability to practise of a registered building practitioner -
...
(d) at the request of any other person.
179 Inquiry to conduct
(1) On an inquiry into the conduct of a registered building practitioner, the Building Practitioners Board may make any one or more of the decisions mentioned in subsection (2) if it finds that the registered building practitioner -
(a) is guilty of unprofessional conduct; or
(b) has failed to comply with this Act or the regulations; or
...
(d) has been guilty of conduct in relation to his or her practice as a building practitioner which -
(i) is constituted by a pattern of conduct or by gross negligence or gross incompetence in a particular matter; and
(ii) shows that he or she is not a fit and proper person to practise as a building practitioner; or
(e) has employed or engaged to do, on his or her behalf, work of a kind that can only be done by a person registered under this Part in a particular category or class, a person who is not so registered; or
...
(fc) has failed to comply with the Domestic Building Contracts Act 1995; or ...
179B Conduct of company or partnership to be conduct of building practitioner director or partner
If a company or partnership of which a registered building practitioner is a director or partner fails to comply with this Act or the regulations in carrying out building work, that failure is taken to have been the conduct of the registered building practitioner and a failure by the registered building practitioner to comply with this Act and the regulations for the purposes of sections 178, 179 and 179A.
177 Preliminary assessment
(1) The Building Practitioners Board may appoint a person to report and make recommendations to it on whether or not it should hold an inquiry into the conduct or ability to practise of a registered building practitioner.
(2) The appointment may be made on the initiative of the Board or after the Authority [Victorian Building Authority] has referred the matter to the Board or a person has requested the Board to hold an inquiry.
(3) The appointed person must investigate the matter referred by the Board, and report and make recommendations to the Board in accordance with the terms of the appointment.
5- I request the Tribunal make an order referring the file to the BPB for a full Inquiry as allowed by s.178 (ca) of the Building Act. I have tried to contact the Board on numerous occasions but they failed to reply so I ask the Tribunal to order that the Inquiry be done. I believe this is the most efficient and effective way of ensuring that the above orders are properly actioned by Simonds Homes and that I have not missed any other problems. After all I am only one man trying to investigate the actions of numerous questionable agents and contract.
...
After considering my options I have now requested that VCAT order an Inquiry under Section 178(ca) of the Building Act. With the case developing into what it is, I am now hoping to avoid wasting more of the tribunals' and our time and ask for the inquiry myself as allowed by Section 178(1d).
I think when you have read my list of claims, it will become clear that this is an issue that should be dealt with by the BPB by way of an inquiry and then given back to VCAT. Once the technical issues have been properly addressed, VCAT will be in a position to rule on how we can then move forward.
I have included the list of claims exactly as it is registered with VCAT...
...
Your request [for an inquiry] will be put to the Board at the next meeting on 11 March 2015.
At the meeting, the Board may decide to appoint a person to further investigate the matters you have raised. This person would be required to investigate your complaint and report to the Board with recommendations as to whether an Inquiry hearing should be held.
Please note that should an Inquiry hearing be held, the Board is not able to order rectification work or financial compensation. The Board would hear evidence regarding the complaint and, upon a finding of guilty, consider a range of possible sanctions for the practitioner.
As the matter you raise is currently slated to go before the VCAT on 18 May 2015, including summonses to VBA employees, the VBA is not in a position to provide any further comment on this matter until the VCAT matter has been determined.
The VBA is continuing its investigation into the conduct of Mr Simonds. The VBA's enquiries into this matter are ongoing and therefore the investigation has not been able to be completed within the timeframe nominated by the BPB. The BPB has been informed of the progress of the investigation and the VBA will continue to report to the BPP as the investigation continues.
...
Further to your recent emails to the BPB and VBA regarding the progress of your complaint, the BPB has determined to undertake a conduct review in relation to Mr Simonds. This review is ongoing and you will be advised of the outcome of the review in due course. This review process is expected to be finalised at the end of March.
As Ms Despot advised in her email to you of 2 March 2016, the BPB has determined to undertake a conduct review in relation to Mr Simonds. A conduct review is different to an inquiry. The BPB's parameters in conducting an inquiry are stipulated in Part 11 of the Building Act 1993 (Building Act). As you note, inquiries are generally held in public unless the BPB determines otherwise.
A conduct review is not an inquiry, rather it is a process that allows the matters to be dealt with by the BPB by inviting the practitioner to attend a meeting with a panel to discuss and review the circumstances that led to a complaint being made against them.
As a conduct review is not an inquiry, the panel is unable to hand down a fine or a penalty that may affect registration, or to impose costs, but may issue a caution and where appropriate, request that the practitioner undertake to do certain things, for example undertake remedial training or alter of business practice.
Conduct reviews are not governed by Part 11 of the Building Act and are not open to the public...
...
B. Future conduct of your matter
The conduct review in this matter has commenced. I am instructed that the BPB has met with Mr Simonds on several occasions. I am instructed that the BPB put concerns to Mr Simonds which relate to Simonds Homes' use of pro forma contracts.
Mr Simonds responded on 24 March 2016. He provided a comprehensive report to the conduct review panel in relation to steps taken to improve compliance within the company. The steps include:
Mr Simonds also agreed to submit six random contracts by 30 April 2016 for review by the BPB.
The panel concluded as follows:
A formal outcome of the review will be provided to you in due course. The conclusion of the Conduct Review will result in a formal decision of the board to either commission an inquiry or not. This decision is subject to review under s 182 of the Act.
violates or falls short of, to a substantial degree, the standard of professional conduct.[22]
246 Offence to make false or misleading statement
A person must not knowingly make any false or misleading statement or provide any false or misleading information to a person or body carrying out any function under this Act or the regulations
The Panel formed the view that there was a total absence of compliance with the regulatory requirements in building transactions conducted by the practitioner.
The Practitioner and his executives acknowledged these compliance failures, and stated that the revelations were a major embarrassment to them.
The Practitioner agreed that there was a need for urgent change to bring a broad compliance with the regulatory requirements including the introduction of a current client building contract. The Practitioner agreed to introduce urgent changes designed to achieve the necessary compliance.
Category 4: Contravention of s 31 of the DBC Act
A builder must not enter into a major domestic building contract unless the contract -
...
(c) has a detailed description of the work to be carried out under the contract; and
(d) includes the plans and specifications for the work and those plans and specifications contain enough information to enable the obtaining of a building permit;
...
General references in the specification such as: "All timber framing embracing to comply with AS1684" ... are not in themselves sufficient and more detailed information should be provided.[26]
Claim 11 - Additional information is required in relation to the loading of trusses by the proposed SHW panels and whether the approved trusses were suitable.[27]
Category 5 & 6: Unlawful variation of building works
(1) A builder who wishes to vary the plans were specifications set out in a major domestic building contract must give the building owner notice that -
(a) describes the variation the builder wishes to make; and
(b) state why the builder wishes to make the variation; and
(c) states what effect the variation will have on the work as a whole being carried out under the contract and whether a variation to any permit will be required; and
...
Category 7: Non-compliance with Australian Standards
A registered building practitioner must -
(a) perform his or her work as a building practitioner in a competent manner and to a professional standard;
... conduct in relation to his or her practice as a building practitioner which is constituted by a pattern of conduct or by gross negligence or gross incompetence in a particular matter.
The board has been given broad powers to inquire into the conduct of registered building practitioners, and to make certain findings and exercise certain powers against them. Having regard to the statutory scheme, I am satisfied that the main purpose of such an inquiry is to ensure that registered builders adhere to the high standards expected of them, primarily for the protection of the public and the reputation of the building industry itself. If the board finds that the builder has failed to comply with a provision of the Act, it may impose one of a number of disciplinary sanctions. That disciplinary regime is separate from the provisions which create offences which are punishable through prosecution in the courts.
Disciplinary proceedings are not intended to be punitive
The purpose of disciplinary proceedings is to protect the public, not to punish a practitioner in the sense in which punishment is administered pursuant to the criminal law. A disciplinary tribunal protects the public by making orders which will prevent persons who are unfit to practise from practising or by making orders which will secure the maintenance of proper professional standards. A disciplinary tribunal will also consider the protection of the public, and of the relevant profession, by making orders which will assure the public that appropriate standards are being maintained within the relevant profession.[32]
The Conduct Review achieved a better outcome.
Mr Simonds cooperation with the Conduct Review
4 Proceedings - Building Practitioners Board
(1) If, before the relevant commencement date, the Building Practitioners Board has commenced an inquiry into the conduct of a building practitioner but the Board has not determined the inquiry, the Board may continue and determine the inquiry in accordance with the old provisions.
(2) A determination of the Building Practitioners Board referred to in subclause (1) is taken -
(a) in the case of a determination under section 179 of the old provisions, to be a decision of the Authority under section 182E of the new provisions; or
(b) in the case of a decision under section 180 of the old provisions, to be a decision of the Authority under section 181 of the new provisions.
(3) An application for a review that has been made under section 182A of the old provisions but not determined before the relevant commencement day may be continued and completed in accordance with the old provisions.
(4) If the time within which an application for review could be made under section 182A of the old provisions had not expired before the relevant commencement day, the application may be made and dealt with in accordance with the old provisions.
6 Decisions and actions of Building Practitioners Board
On the relevant commencement day, all decisions and actions taken by the Building Practitioners Board under this Act before the relevant commencement day are taken to be decisions and actions taken by the Authority in relation to any period on or after the relevant commencement day.
SENIOR MEMBER E RIEGLER
[1] Draper v Simonds Homes Victoria Pty Ltd [2016] VCAT 669.
[2] As defined in s 3 of the Domestic Building Contracts Act 1995.
[4] Paragraphs 3, 14, 16, and 27 of the List of Claims.
[5] Paragraphs 4 and 5 of the List of Claims.
[6] Paragraphs 6 and 7 of the List of Claims.
[8] Paragraph 9 and 27 of the List of Claims.
[9] Paragraphs 10, 11, 21 and 25 of the List of Claims.
[10] Paragraph 13 of the List of Claims.
[11] Paragraphs 21, 22 and 39 of the List of Claims.
[12] Paragraphs 36 and 37 of the List of Claims.
[13] On 1 September 2016, the functions of the Board were transferred to the Victorian Building Authority pursuant to s 18 of the Building Legislation Amendment (Consumer Protection) Act 2016.
[19] Paragraphs 15-17 of the Board's Closing Submissions dated 11 August 2017.
[20] There are 11 discrete headings of complaint, however, some of those categories overlap.
[21] Adamson v Queensland Law Society Incorporated [1990] 1 QdR 498.
[26] Victorian Building Authority, Practice Note 2014-62, Documentation Required for Applications for Building Permits, 3.
[27] Report of Jon Weuers dated 20 July 2015.
[28] Briginshaw v Briginshaw [1938] HCA 34; (1938) 60 CLR 336.
[29] The Board advised that it is anticipated that it will cease to operate after February 2018.
[34] Ibid, although this decision is currently subject of an appeal.
Draper
Building Practitioners Board
(1938) 60 CLR 336
(2009) 21 VR 683