[2003] VSC 61
Supreme Court of Victoria
2003-03-11
Mandie J
Original judgment source is linked above.
[2003] VSC 61
INSURANCE--domestic building insurance policy--construction of term in policy and in Ministerial Order--appeal from VCAT--whether error of law by Tribunal in construction of term--"the cost of completing the domestic building work"
"The insurer shall bear no liability for claims arising from non-completion of domestic building work for any reason listed in Item (2) of the definition of Prescribed Cause to the extent that the cost of completing the domestic building work (excluding the cost of rectifying any defective building work) exceeds the contract price specified in the Schedule for the Major Domestic Building Contract by more than 20 %". [emphasis added]
"5. A policy to be issued pursuant to clause 4.1 of this order shall contain terms and conditions, which have the following effect:
5.1 The policy shall indemnify the building owner ("insured") in respect of loss or damage, which results from:
5.1.3 non-completion of the domestic building work due to the:
5.5 ...the policy may exclude or limit claims under the policy:
5.5.6 made under the indemnity for non-completion of domestic building work required by clause 5.1.3 to the extent that the cost of completing the domestic building work (excluding the cost of rectifying any defective building work) exceeds the contract price under the relevant major domestic building contract by more than 20 %;
5.6 Subject to clauses 5.5 and 7, the policy shall not otherwise contain any exclusion or other provision which excludes, limits, avoids or modifies the requirements of this Clause 5 ".
(Clause 7 allowed a policy to limit the liability of the insurer to not less than the aggregate amount of $100,000 for all claims in respect of any one home)
"...does not make much sense because the limitation would probably never come into operation except in cases where the works were at a very early stage of construction. If the object ... was to permit an insurer to limit its liability for completion claims, this interpretation would not seem to achieve that object. Further, it would reward an owner who overpaid the defaulting builder."
"a clear ambiguity or inconsistency in the words "cost of completion", that the second interpretation of the words used would promote the purpose or object of the provision... allowing the insurer to limit its liability for these sorts of claims, whereas the first interpretation would largely defeat the purpose. I therefore think that the second interpretation is the correct one."
Dore
Housing Guarantee Fund Ltd [2003] VSC 61