[2019] WASCA 117
General information, not legal advice.
Court of Appeal (WA)
2019-08-16
Quinlan CJ
Original judgment source is linked above.
Organic Products (including DiCom® Bioconversion Products) and Environmental Credits, and any other material or right created, derived or sorted from Municipal Solid Waste delivered to the Facility, including biogas, other than Non-Specification Material and Residual Material.
For this purpose, 'Organic Products' is defined to mean 'material which is suitable for use as compost or organic fertilizer, including DICOM Compost'.
(1) supply Municipal Solid Waste in accordance with the agreement;
(2) make payments in accordance with the agreement; and
(3) 'remove, transport and dispose of all Residual Material and Non‑Specification Material'.
[I]n respect of Stage 2, the date on which [DiCOM] notifies [the Council] that the Facility is ready to receive, sort, process and treat Municipal Solid Waste for the purpose of commencing the Commission Period.
[T]he DiCOM® System and supporting infrastructure at [the Waste Transfer Station] to be located on the Site incorporating Stage 1 and, as the case may be, Stage 2.
DiCOM® System the integration [sic] of [AnaeCo] developed:
(a) Waste receival, sorting & recovery system.
(b) solid organic waste processing system using DICOM® Bioconversion.
(c) auxiliary systems for DICOM® Bioconversion Products,
for the purposes of processing Waste by:
(a) recovering Recyclables.
(b) converting the organic fraction of Waste into DICOM® Bioconversion Products.
(c) value adding DICOM® Bioconversion Products by producing renewable energy, organic fertiliser/soil conditioner or solid recovered fuel briquettes.
The Commission Period begins on the Commission Date and ends at the end of the Ramp Up Period as notified to [the Council] by [DiCOM].
During the Commission Period, [the Council] must deliver Municipal Solid Waste to the Receival Point in accordance with the Commission Schedule and the Ramp Up Schedule.
On achievement of Practical Completion in respect of Stage 2 (as notified by [DiCOM] to [the Council]), [the Council] must procure the delivery of the following tonnes of Municipal Solid Waste:
(a) 126.45 tonnes of Municipal Solid Waste an Operating Day (Daily Base Capacity);
(b) 634 tonnes of Municipal Solid Waste a week (Weekly Base Capacity);
(c) 2,750 tonnes of Municipal Solid Waste a Month (Monthly Base Capacity); and
(d) 8,250 tonnes of Municipal Solid Waste a Quarter (Quarterly Base Capacity); and
(e) 33,000 tonnes of Municipal Solid Waste in a Financial Year (Annual Base Capacity)
[The Council] must remove, transport and dispose of all Residual Material and Non-Specification Material in accordance with the Collection Procedures, being Residual Material derived and Non‑Specification Material separated or sorted from Waste delivered by [the Council] or any Third Party.
[A]n amount determined by [DiCOM] (on a basis consistent with the Assumptions Book) on or before the Commission Date that is sufficient to provide a rate of return on the capital employed and to cover the expected future operating and finance related cash flows necessary to be incurred to deliver the service requirements for the Term.
It will be convenient to refer to this as the 'return on capital component of the Service Charge'.
[A]n amount equal to the actual costs to [the Council] of the removal, transportation and disposal of the quantity and composition of the Residual Material determined by the Waste Characterisation Study (Residual Material Cost).
(1) the cost to the Council in respect of all Residual Material removed, transported and disposed of by the Council during that month; and
(2) the Overhead Amount (in effect the cost per tonne of the Council operating the Waste Transfer Station) in respect of each tonne of Waste delivered to the Facility by a Third Party during that month.
[I]n respect of each Month, the number of tonnes of Municipal Solid Waste required under this agreement delivered to [DiCOM] at the Facility multiplied by the Service Charge. [sic]
[T]hat the service charge is less than the Service Charge or the same or similar terms contained in the applicable Third Party WSA to those contained in this agreement (having regard to the interaction of all terms) are more favourable such that those terms provide a more favourable apportionment of economic and liability risks than under this agreement.
(1) when 'Practical Completion in respect of Stage 2 (as notified by [DiCOM] to the [Council])' occurs for the purposes of cl 4.2 of the Council Agreement;
(2) the meaning of the term 'process' in certain provisions of the Council Agreement; and
(3) when 'Final Completion' occurs for the purposes of cl 4.2 of the City Agreement.
(1) The plain meaning of cl 4.2 is that it sets up a pre‑condition to the Council's obligation to deliver Waste during the Operational Period. Further, on its face and in the context of the Council Agreement as a whole, cl 4.2 suggests that, to trigger the Council's delivery obligations in the Operational Period, something more is required than simply the completion of the construction of the additional vessels and infrastructure.[7]
(2) There are numerous indicators that the phrase is a reference to an external event. The words 'Practical Completion' are capitalised but not defined. The reference to DiCOM notifying the Council suggests that Practical Completion was something that DiCOM, not the Council, would be told about under the construction contract. The agreement was premised on the fact that another entity would construct the Facility, and did not itself cover that construction. It would be extraordinary if an agreement to construct a facility of this size did not include the usual provisions for certification of practical completion.[8]
(3) A reasonable person would have understood the phrase '[o]n achievement of Practical Completion in respect of Stage 2 (as notified by [DiCOM] to [the Council])' to mean 'on achievement of Practical Completion under the contract under which Stage 2 was completed'. As events transpired, this was the DC Contract. This conclusion is supported by the commercial purposes and objects of the Council Agreement, and was a businesslike construction,[9] in contrast to the construction advanced by DiCOM.[10]
(4) The achievement of Practical Completion under the DC Contract depends upon the terms of the DC Contract. Under that contract, Practical Completion is achieved when, and only when, a certificate of Practical Completion in accordance with the contract is issued.[11]
(2) convert the organic fraction of Waste into DiCOM Bioconversion Products; and
(3) value-add DiCOM Bioconversion Products by producing renewable energy, organic fertiliser/soil conditioner, or solid recovered fuel briquettes.
The trial judge rejected DiCOM's contention that 'process' means only an ability to accept and convey Waste through the Facility for the purposes of recovering Recyclables and Renewables (so that the actual production of the products was merely aspirational).[14]
On the proper construction of the Council Agreement, for the purposes of the definitions of the terms 'Commission Date', 'Services', and 'Residual Material' in the Council Agreement, 'processing' of MSW requires the Facility to:
(a) recover Recyclables;
(b) convert the organic fraction of Municipal Solid Waste into DiCOM® Bioconversion Products, being:
(i) DiCOM® Compost; and
(ii) DiCOM® Biogas; and
(c) value-add DiCOM® Bioconversion Products by producing renewable energy, organic fertiliser/soil conditioner or solid recovered fuel briquettes.
On the proper construction of the Council Agreement, for the purposes of the definitions of the terms 'Commission Date', 'Services', and 'Residual Material' in the Council Agreement, 'processing' of MSW requires the Facility to:
(a) recover Recyclables;
(b) convert the organic fraction of Municipal Solid Waste into Renewable Resources, including but not limited to DiCOM® Bioconversion Products, being:
(i) DiCOM® Compost; and
(ii) DiCOM® Biogas; and
(c) value-add DiCOM® Bioconversion Products by producing renewable energy, organic fertiliser/soil conditioner or solid recovered fuel briquettes.
Disposition: Achievement of Practical Completion Proper construction of the Council Agreement
The meaning of the terms of a commercial contract is to be determined by what a reasonable businessperson would have understood those terms to mean. That approach is not unfamiliar. As reaffirmed, it will require consideration of the language used by the parties, the surrounding circumstances known to them and the commercial purpose or objects to be secured by the contract. Appreciation of the commercial purpose or objects is facilitated by an understanding "of the genesis of the transaction, the background, the context [and] the market in which the parties are operating". ... [U]nless a contrary intention is indicated, a court is entitled to approach the task of giving a commercial contract a businesslike interpretation on the assumption "that the parties ... intended to produce a commercial result". A commercial contract is to be construed so as to avoid it "making commercial nonsense or working commercial inconvenience". (citations omitted)
(1) An ultimate object of the Council Agreement was that, subject to certain events occurring, the Council would deliver Waste to the Facility and DiCOM would process that Waste under the DiCOM System for a fee. An ultimate object was to recover recyclables and convert some Waste into compost and other renewable resources so as to significantly reduce the amount of Waste going to landfill. That was what the DiCOM System promised to do, and what the Council agreed to pay for.
(2) It was a commercial purpose of the Council Agreement that the Council would not be required to pay unless the DiCOM System worked: ie that its Waste was processed under, and as required by, the DiCOM System.
The trial judge's conclusion as to these commercial purposes of the Council Agreement was not challenged on appeal.
[V]iewed objectively the parties had contracted on the basis that all of the testing would be done during stage 1 and then all that needed to happen was the addition of the extra vessels and once that occurred stage 2 would commence or could commence.
DiCOM's submissions as to errors in the trial judge's reasons
Operation after Practical Completion in respect of Stage 2 - [the Council's] Site Procedures for Steady State.
The reference to 'Desired Outcomes' is to ensuring 'that each party complies with [the] Law, and risk of injury to person, risk of damage to property and risk of contamination of the environment is negated or mitigated'.[38]
Final Completion will occur when the Facility is able to process Waste at a rate of 55,000 tonnes per annum as certified in accordance with the engineering, procurement, construction and management agreement under which the Facility is constructed (Final Completion).
Final Completion means the date on which the Facility is able to accept and process waste at a rate of 55,000 tonnes per annum to the satisfaction of [DiCOM].
The Operational Period begins on the day immediately following the end of the Bank Test Period and ends on the Expiry Date.
(a) The Bank Test Period is the period during which all tests required to be undertaken by [DiCOM] in accordance with the Finance Agreements will be undertaken.
(b) The Bank Test Period will begin on a date notified by [DiCOM] to the [City]. The Bank Test Period will end when the Financiers conclude that the bank tests are satisfied. [DiCOM] will promptly notify the [City] of the date that the Bank Test Period ends.
The 'Financiers' are defined in sch 1 to be the provider(s) of finance to DiCOM for the operation of the Facility.
(1) Clause 4.1 provides for delivery '[u]p to and including the date of Final Completion', in amounts reasonably required by DiCOM to enable ramp up of the Facility and undertake the Initial Waste Characterisation Study.
(2) Clause 4.2 provides for delivery 'during the period from Final Completion to the commencement of the Operational Period' (generally according to a 'Pre-Operational Period Schedule' to be agreed subject to a default position).
(3) Clause 4.3 requires the City to provide notice that it intends to deliver Waste according to one of three options not less than '60 days prior to the commencement of the provision of Services (as contemplated by clause 3.5)'.
Subject to Section 2 and Section 3 of this Schedule 10, the [City] must pay the Service Charge in respect of the number of tonnes of Waste delivered by the [City] during each Month of the Term.
The Term is defined in cl 3.1 as beginning on the date the agreement is executed by both parties and continuing until the Expiry Date.
The Service Charge applicable at the commencement of the Operational Period will be no greater than 110% of the service charge per tonne of municipal solid waste payable by the [City] to Atlas Group Pty Limited (Atlas) under the single bin contract referred to in Recital D of this agreement as at the date of commencement of the Operational Period.
[I]n respect of each Month, the number of tonnes of Waste required under this agreement delivered to [DiCOM] at the Facility multiplied by the Service Charge. [sic]
It was common ground that Final Completion will occur under the City Agreement when the Facility is able to process waste at 55,000 tpa. The dispute is who or what determines when the Facility is able to do that.
As noted earlier, DiCOM asserts that Final Completion occurs when it itself is satisfied the Facility can process waste at 55,000 tpa. The City asserts that Final Completion occurs when the Facility is certified under the DC Contract as being able to process waste at 55,000 tpa.
(1) was inconsistent with the plain meaning of cl 3.2;
(2) was inconsistent with what a reasonable person would have understood the terms to mean;
The commercial purpose and objects sought to be secured by the City Agreement were not in dispute. The DiCOM® System was unproven. The City Agreement was objectively intended to ensure the City bore none of the risk that the system wouldn't work. DiCOM accepted that, if it did not work, the City would not have to pay anything.
Against that background, a reasonable person would have understood cl 3.2 to define when Final Completion would be contractually established. A reasonable person would have understood the clauses operated so as to provide for certification that the Facility could process 55,000 tpa from a source who would not benefit from declaring that it could. In this way, the commercial objective would be met. The City would not have to pay merely because DiCOM asserted the Facility could process 55,000 tpa.
To contractually establish Final Completion under the City Agreement, the Facility must be certified in accordance with the [agreement under which the Facility was constructed] to be able to process waste at a rate of 55,000 tpa. Final Completion will not occur before that happens.
Under the DC Contract, the first (and only) certification of the ability of the Facility to process 55,000 tpa is when a certificate of 'Practical Completion' is issued.
On the proper construction of the [City Agreement]:
(a) 'Final Completion' for the purposes of clauses 3.5, 4.2 and 10.2 of the City Agreement will not occur before the Facility has been certified in accordance with the agreement under which the Facility has been constructed to be able to process Waste at a rate of 55,000 tonnes per annum.
...
As from 3 December 2010, 'Final Completion' for the purposes of clauses 3 .5, 4.2 and 10.2 of the City Agreement requires certification of Practical Completion of the Facility in accordance with the DC Contract.
(1) At the time the City Agreement was executed, the EPCM Contract was in place, but did not provide for certification that the Facility was able to process Waste at a rate of 55,000 tonnes per annum. (The EPCM Contract identified the specification for Stage 1, but left the project specification in respect of stage 2 to be settled at a later time).[61]
(2) In that context, the definition of 'Final Completion' in clause 3.2 was only applicable if the contract under which Stage 2 was constructed provided for certification that the Facility was able to process Waste at a rate of 55,000 tonnes per annum.
(3) If the contract under which Stage 2 was constructed did not provide for certification that the Facility was able to process Waste at a rate of 55,000 tonnes per annum, then the definition of 'Final Completion' in sch 1 applied.
(4) The DC Contract (being the contract under which Stage 2 was constructed) did not provide for certification that the Facility was able to process Waste at a rate of 55,000 tonnes per annum. Rather, it provided for a higher standard before Practical Completion would be certified.
(5) Because the DC Contract did not provide for certification of the kind contemplated by cl 3.2, that clause does not apply and the definition in sch 1 operates.
Senior counsel for DiCOM accepted that if the fourth and fifth steps were not established, the appeal could not succeed.[62]
Steps 2 and 3: Reconciling different definitions of 'Final Completion'
If this construction is adopted, there would be complete harmony among cl 3.2 and 3.5 and the Schedule Definition, and each would have work to do. Further, this construction is businesslike. DiCOM would be protected from having to deliver 'Services' before it felt that it could. The City would be protected from having to pay until there had been a certification of the Facility's ability to process 55,000 tpa.
Steps 4 and 5: Did the DC Contract relevant provide for certification
I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.
Research Associate/Orderly to the Honourable Justice Mitchell
[7] Primary Council Decision [76], [79].
[8] Primary Council Decision [81] - [87].
[9] Primary Council Decision [88] - [92].
[10] Primary Council Decision [76] - [77].
[11] Primary Council Decision [95], [109].
[12] Primary Council Decision [37] - [43].
[13] Primary Council Decision [71] - [73].
[14] Primary Council Decision [133] - [136].
[15] Appellant's Submissions, pars 43 - 44; appeal ts 6, 9, 14, 29 - 30.
[16] Appellant's Submissions, par 44, appeal ts 32, 129, 132.
[17] Appellant's Submissions, pars 53 - 56, appeal ts 44 - 47.
[18] See Appellant's Submissions, par 78.
[19] Black Box Control Pty Ltd v Terravision Pty Ltd [2016] WASCA 219 [42].
[20] Primary City Decision [71], incorporated by [3] of the Primary Council Decision.
[21] Electricity Corporation v Woodside Energy Ltd [2014] HCA 7; (2014) 251 CLR 640 [35].
[26] Primary Council Decision [21] - [26].
[27] Appeal ts 7, 9 - 11, 44, 125 - 129.
[30] Life Insurance Company of Australia Ltd v Phillips [1925] HCA 18; (1925) 36 CLR 60, 78 - 79; Minister for Immigration and Border Protection v SZVFW [2018] HCA 30; (2018) 92 ALJR 713 [154]; Sino Iron Pty Ltd v Mineralogy Pty Ltd [2019] WASCA 80 [172].
[31] Appellant's Submissions, par 80(a).
[32] Codelfa Construction Pty Ltd v State Rail Authority of New South Wales (1982) 149 CLR 337, 352. See also Ecosse Property Holdings Pty Ltd v Gee Dee Nominees Pty Ltd [2017] HCA 12; (2017) 261 CLR 544 [16], [24], [45], [73] and Onley v Catlin Syndicate Ltd [2018] FCAFC 119; (2018) 360 ALR 92 [33].
[33] See Agricultural and Rural Finance Pty Ltd v Gardiner [2008] HCA 57; (2008) 238 CLR 570 [35], [163]; KWS Capital Pty Ltd v Love [2015] WASCA 237 [22], [117]. See also the discussion in J D Heydon Heydon on Contract (Law Book Co, 2019) at [9.1600] - [9.1780].
[36] Appellant's Submissions, par 80(a) - (b).
[37] Appellant's Submissions, par 80(c).
[38] Paragraph 1 of s 1 of sch 4 to the Council Agreement.
[39] Appellant's Submissions, pars 62 - 65, 80(d), 81 - 83.
[40] Appellant's Submissions, pars 66 - 72, 84.
[43] Appellant's Submissions, pars 54 - 55.
[44] See Ainsworth v Criminal Justice Commission [1992] HCA 10; (1992) 175 CLR 564, 581 - 582.
[46] Appeal ts 49, 77. A similar typographical error appears in cl 3.5(b), where the context makes it clear that the date of Financial Completion and the date of Final Completion are being treated as the same thing.
[47] Primary City Decision [68] - [69].
[49] Primary City Decision [82] - [88].
[50] Primary City Decision [92] - [128].
[51] Primary City Decision [103] - [104].
[56] Primary City Decision [265]. See trial ts 421.
[59] Another ground was abandoned at the hearing of the appeal: see appeal ts 48.
[61] Clause 2.5(j) of the EPCM Contract.
[63] George 218 Pty Ltd v Bank of Queensland [2016] WASCA 182; (2016) 313 FLR 287 [88]; Tokio Marine & Nichido Fire Insurance Co Ltd v Hans Bo Kristian Holgersson trading as Holgerssons Complete Home Service [2019] WASCA 114 [52] ‑ [58].
[64] Primary City Decision [72] - [75].
[66] Primary City Decision [105] - [106].
[67] Appellant's Submissions, par 53; appeal ts 63.
[68] Clauses 4.13 and 9.2 of the Council Agreement.
[69] Appellant's Submissions, pars 17 - 19, 66 - 74, 80(c), 83.
[71] Appellant's Submissions, pars 22 - 41.
[72] Appellant's Submissions, pars 49 - 52.
(2014) 251 CLR 640
(1925) 36 CLR 60
(2018) 360 ALR 92
(2016) 313 FLR 287
(2018) 92 ALJR 713
(1982) 149 CLR 337
(2017) 261 CLR 544
(2008) 238 CLR 570
(1992) 175 CLR 564