[2025] NSWCATAP 131
General information, not legal advice.
NCAT Appeal Panel
2025-06-11
S Westgarth, Deputy PresidentM Tyson, Senior Member
Original judgment source is linked above.
Allen v TriCare (Hastings) Ltd [2017] NSWCATAP 25
Bellgrove v Eldridge (1954) 90 CLR 613; [1954] HCA 36
Bimson, Roads & Maritime Services v Damorange Pty Ltd [2014] NSWSC 734
Collins v Urban [2014] NSWCATAP 17
DB Homes Australia Pty Ltd v Kes [2019] NSWCATAP 221
Hadley v Baxendale (1854) 9 Exch 341; 156 ER 145
Hyder Consulting (Australia) Pty Limited v Wilh Wilhelmsen Agency Pty Ltd (2002) 18 BCL 122
Gianacopoulos v DJJ Promotions Pty Ltd [2021] VSC 203
Grygiel v Baine [2005] NSWCA 218
McDonald v Dennys Lascelles Ltd (1933) 48 CLR 457; [1933] HCA 25
Maclean v Brylewski [2023] NSWCA 173
Mann v Paterson Constructions Pty Ltd [2019] HCA 32
Midland Expressway Ltd v Carrillion Construction Ltd (2006) 107 Con LR 235
Pavey and Matthews Pty Ltd v Paul [1987] HCA 5; (1987) 162 CLR 221 at 266
Rogers v Head (1610) 79 ER 226
State Rail Authority of New South Wales v Earthline Constructions Pty Ltd (in liq) [1999] HCA 3; (1999) 160 ALR 588
Unique Commercial Group Pty Ltd v Cusumano [2024] NSWCATAP 204
Vella v Mir (No 3) [2020] NSWCATAP 17
Wabbits Pty Limited v Godfrey [2009] NSWSC 1299
Wan v Chief Commissioner of State Revenue [2025] NSWCATAP 54
Warbrook v Griffin [1609] EngR 38; (1609) 123 ER 927
(1) we have decided the threshold question of whether the appeal is on one or more questions of law;
(2) to the extent that the appeal is on one or more questions of law, we have decided whether the Tribunal either answered that question or proceeded on an assumption concerning that answer, whether its answer or assumption was correct or incorrect, and whether that answer or assumption was material to the outcome, in the sense that it could have affected the outcome: Bimson, Roads & Maritime Services v Damorange Pty Ltd [2014] NSWSC 734 (Bimson, Roads & Maritime) at [41] (Beech-Jones J) citing Australian Broadcasting Tribunal v Bond (1990) 170 CLR 321; [1990] HCA 33 at 353 (Mason CJ); cited with approval together with other authorities in Wan v Chief Commissioner of State Revenue [2025] NSWCATAP 54 at [53]- [54];
(3) to the extent necessary, we have decided whether leave to appeal should be granted in accordance with the principles in Collins v Urban [2014] NSWCATAP 17 (Collins) at [76]-[84], and if so whether any relief should be granted in respect of any material error;
(4) we have set out our conclusions;
(5) we have then decided the costs of the appeal;
(6) we have conducted the appeal as a rehearing on the materials before the Tribunal to determine whether the orders that are the subject of the appeal are the result of some legal, factual or discretionary error: Yuen v Thom [2016] NSWCATAP 243 at [14]- [22].
Question of law within s 80(2)(b) of the NCAT Act
"... there was a 'significant possibility' or a 'chance which was fairly open' that a different and more favourable result would have been achieved for the appellant had the relevant circumstance in para (a) or (b) not occurred or if the fresh evidence under para (c) had been before the Tribunal at first instance." (emphasis in original)
"[24] It is not disputed that leave to appeal is necessary. In determining whether leave to appeal should be granted, something more must be demonstrated than that the primary judge's decision was arguably wrong. What is ordinarily required to be demonstrated is that the matter involves a question of principle or of public importance or an injustice which is reasonably clear in the sense of going beyond what is merely arguable. Moreover, where, as here, the decision the subject of the application for leave to appeal involves an exercise of discretion, what is required to be demonstrated is error in the House v The King sense." (citations omitted)
"If the reasonable cost of completion of the work exceeds that which would have otherwise been due under the contract the difference will be a debt payable by the contractor to the owner. Should the reasonable cost of completion be less than otherwise due under the contract the difference will be a debt payable to the contractor."
"Pursuant to clause 25 of the Building Contract our client is entitled to terminate the Contract on the basis that you are unable or unwilling to complete the work or have abandoned the work. Also, that you have suspended the work before completion without reasonable cause and that you have breached your obligations under the Contract in that you have failed to complete the work or act reasonably or responsibly so as to complete the work."
"You are also notified that you will be liable to pay our clients damages pursuant to your breach of the Building Contract which will include the cost of engaging another builder to complete the Works in accordance with the Building Contract entered into by you together with other heads of damage set out in items 2-7 inclusive of the Notice to Rectify."
The hearing before the Tribunal following the remittal from the Supreme Court
Summary Amounts Claimed by Respondent v Agreed Amounts
"In circumstances where a residential building works contract is repudiated by a builder, the type of damages relevantly involve:
(1) The reasonable cost of rectifying existing defects;
(2) The increased cost of completing incomplete work.
(3) Any other loss caused by breach of contract, provided that loss is caused by the breach and not too remote from the breach, applying principles of remoteness in Hadley v Baxendale (1854) 9 Exch 341 at 354; 156 ER 145 at 151."
"The Tribunal is satisfied that the submissions of the applicant accurately reflect the documentary evidence in respect of what payments were made; when they were made; the amount paid; and what they were paid. The applicant provided supporting evidence, relevantly including the accounts, invoices and records provided by the applicant. The Tribunal accepts that evidence and its factual findings are the findings sought by the applicant. The respondent has failed to provide his own evidence of works done and payments made to him sufficient to cause the Tribunal not to accept the evidence of the applicant."
"(3) The calculation of 'adjustments for provisional sum and prime cost items' of $128,121.40 is not clearly explained and based on the evidence. In essence, the respondent submits that this is the amount that would have been adjusted for provisional sums and prime costs items in favour of the builder had the contract been completed. The evidence does not show that such an adjustment would have bene made in favour of the respondent."
"The Respondents did not engage in this exercise which was essential for determining any loss or damage under the Building Contract as required by clause 25. The Tribunal recognised at [138] and [142(3)] of the Decision that it was required to engage in this task but it failed to do so. The tribunal merely adopted the Respondents methodology and calculation of damages which was flawed ... The failure was an error of law. ... The Tribunal ... criticises the Appellant's calculation of 'adjustments for provisional sum and prime cost items' finding they are not clearly explained and based on the evidence. Even if that was so, it does not excuse the Tribunal from engaging in the exercise."
Plus adjustments for provisional sum and prime costs items
Reasonable cost to complete work under DeMarco Contract
Amount paid to Mr. Swingler under the Swingler Contract (being $471,511.50) less $16,285 (being the cost to fix defective work) less $42,873 (being the betterment value in the Swingler Contract as determined by the Appellant's expert Mr Jamison) see [22.g] above
Amount paid directly to contractors for work outside of the Swingler Contract but within the original contract scope
Contract sum of $770,000 less what had been paid $677,000 (other than amounts paid for agreed variations) see [40] above
The claim in contract - termination under the Contract or at common law?
"Pursuant to clause 25 of the Building Contract our client is entitled to terminate the Contract on the basis that you are unable or unwilling to complete the work or have abandoned the work. Also, that you have suspended the work before completion without reasonable cause and that you have breached your obligations under the Contract in that you have failed to complete the work or act reasonably or responsibly so as to complete the work." (Emphasis added).
"You are also notified that you will be liable to pay our clients damages pursuant to your breach of the Building Contract which will include the cost of engaging another builder to complete the Works in accordance with the Building Contract entered into by you together with other heads of damage set out in items 2-7 inclusive of the Notice to Rectify." (Emphasis added).
The contract - prime cost items and provisional sum items
"The term 'provisional sum' is generally well understood in the construction industry. It is used in pricing construction contracts to refer either to work which is truly provisional, in the sense that it may or may not be carried out at all, or to work whose content is undefined, so that the parties decide not to try and price it accurately when they enter into their contract. A provisional sum is usually included as a round figure guess. It is included mathematically in the original contract price but the parties do not expect the initial round figure to be paid without adjustment. The contract usually provides expressly how it is to be dealt with. ... In this general sense, the term 'provisional sum' is close to a term of art but its precise meaning and effect depends on the terms of the individual contract."
Conclusion and calculation comparing contract damages at common law with cl. 25 of the Contract
Add the reasonable cost of the work to make the building conform to the Contract
(The Swingler contract amount of $471,511.50 minus $42,873.00 for work that was done by Swingler outside the scope of the Contract minus $16,285.00 already counted above for Swingler's rectification of existing defects plus $34,531.90 paid by the Homeowners which could not be paid by the Homeowners to Swingler under the Swingler contract but which the Homeowners themselves paid).
("contract price" = $770,000 in the Contract plus $41,124.88 for variations in accordance with the Contract. Subtract total of the amount paid: $714,762.90 for the amount paid by the Homeowners, consisting of a deposit of $77,000 plus seven progress payments totalling $600,000 plus $37,672.90 paid for variations)
Conclusion on the amount of the money order - contract and restitution
60 Costs
(1) Each party to proceedings in the Tribunal is to pay the party's own costs.
(2) The Tribunal may award costs in relation to proceedings before it only if it is satisfied that there are special circumstances warranting an award of costs.
(3) In determining whether there are special circumstances warranting an award of costs, the Tribunal may have regard to the following -
(a) whether a party has conducted the proceedings in a way that unnecessarily disadvantaged another party to the proceedings,
(b) whether a party has been responsible for prolonging unreasonably the time taken to complete the proceedings,
(c) the relative strengths of the claims made by each of the parties, including whether a party has made a claim that has no tenable basis in fact or law,
(d) the nature and complexity of the proceedings,
(e) whether the proceedings were frivolous or vexatious or otherwise misconceived or lacking in substance,
(f) whether a party has refused or failed to comply with the duty imposed by section 36(3),
(g) any other matter that the Tribunal considers relevant.
(4) If costs are to be awarded by the Tribunal, the Tribunal may -
(a) determine by whom and to what extent costs are to be paid, and
(b) order costs to be assessed on the basis set out in the legal costs legislation (as defined in section 3A of the Legal Profession Uniform Law Application Act 2014) or on any other basis.
costs includes -
(a) ...
(b) the costs of, or incidental to, the proceedings giving rise to the application or appeal, as well as the costs of or incidental to the application or appeal.
38 Costs in Consumer and Commercial Division of the Tribunal
(1) This rule applies to proceedings for the exercise of functions of the Tribunal that are allocated to the Consumer and Commercial Division of the Tribunal.
(2) Despite section 60 of the Act, the Tribunal may award costs in proceedings to which this rule applies even in the absence of special circumstances warranting such an award if -
...
(b) the amount claimed or in dispute in the proceedings is more than $30,000.
38A Costs in internal appeals
...
(2) Despite section 60 of the Act, the Appeal Panel for an internal appeal to which this rule applies must apply the first instance costs provisions when deciding whether to award costs in relation to the internal appeal.
"[28] Clause 38 gives the Tribunal a wide discretion to make an order for costs. It does not specify the factors the Tribunal must take into account in exercising the discretion, although the discretion to make such an order must be exercised judicially: see, for example, Ruddock v Vadarlis [2001] FCA 1865 at [9].
[29] Where an application has been heard and determined on the merits and Clause 38 applies, the appropriate starting point for the exercise of the discretion is not that the parties are to pay their own costs. Rather, it is the well-established position at common law; that is, that the purpose of making a costs order is to provide compensation to the party in whose favour the order is made for the expense the party has been put to in prosecuting or defending legal proceedings. In general terms, this means that a party who is successful is entitled to an order for costs in its favour, subject to exceptions generally involving misconduct on the part of that party: Latoudis v Casey [1990] HCA 59; [1990] 170 CLR 534; Oshlak v Richmond River Council [1998] HCA 11.
[30] In BNT Constructions Pty Ltd v Allen [2017] NSWCATAP 186 the Appeal Panel, having set aside a costs order made in the Consumer and Commercial Division, decided to re-exercise the costs discretion. Clause 38 was the applicable costs provision in that case. At [67] the Appeal Panel noted the following principles relevant to the exercise of the discretion:
(1) the starting point is that a successful party should be entitled to an order for costs in his favour;
(2) an award of costs is by way of an indemnity and not as punishment;
(3) there is no absolute rule that, absent disentitling conduct, a successful party is to be compensated by the unsuccessful party;
(4) the factors to be considered are not to be confined as to do so would constrain the general discretion;
(5) the relative success of the parties on different issues and the time taken to determine them may be relevant;
(6) the nature of the proceedings is relevant;
(7) the proper exercise of the discretion requires a decision maker to do justice between the parties and to exercise the discretion having regard to relevant considerations and in a manner which is not arbitrary and capricious.
[31] Generally, costs are awarded in favour of the successful party based on the outcome of the proceedings as a whole, without differentiating between particular issues on which the party may not have been successful. That said, a different costs order may be made if the losing party succeeds on significant issues: James v Surf Road Nominees Pty Ltd (No 2) [2005] NSWCA 296 at [31]- [36]; Sydney Ferries v Morton (No 2) [2010] NSWCA 238 at [10]-[12]. The dollar amount of a particular claim does not determine its dominance in the proceedings. Rather, regard must be had to all of the work involved in prosecuting and defending the parties' various claims, including but not limited to the time taken up at the hearing.
[32] In Tomanovic v Global Mortgage Equity Corporation Pty Ltd (No 2) [2011] NSWCA 256; (2011) 288 ALR 385, Campbell JA (with Macfarlan JA and Young JA agreeing) held at [107] that an issue or group of issues is "clearly dominant" when it is clearly dominant in the proceedings as a whole. In that case, the approach by counsel to analysing the percentage of costs between the parties - counting the proportion of paragraphs and pages devoted to each factual topic - was held at [84] to be "a highly artificial way of proceeding" which gave "a false air of mathematical precision".
[33] In relation to separable issues, a successful party's entitlement to the whole of the costs of the proceedings should not be discounted to allow for another party's success in a separate issue that played a very minor part in the proceedings as a whole: Macourt v Clark (No 2) [2012] NSWCA 411 at [7]. Further, in Hawkesbury District Health Service Ltd v Chaker (No 2) [2011] NSWCA 30 at [14], the Court of Appeal held that the severability of one issue on which the successful party failed is not, without more, sufficient to warrant departure from the general approach. The exercise of discretion will often depend upon matters of impression and evaluation: Elite Protective Personnel Pty Ltd v Salmon (No 2) [2007] NSWCA 373 at [11]."
(1) whether the Tribunal had erred when ascertaining the Homeowner's damages by not applying clause 25 in the Contract;
(2) whether the Tribunal had erred in rejecting the Builder's quantum meruit claim on the basis that there was no evidence in support of said claim when the Homeowners had agreed and accepted parts of the Builder's quantum meruit claim.
(1) The appeal is allowed in part.
(2) The date and amount of order 1 made on 29 August 2024 are varied such that:
The appellant (Godfrey DeMarco) is to pay the respondents (David and Debbie Macey) the sum of $372,579.42 immediately.
(4) The appellant is to pay 90% of the respondents' costs of the appeal, on the ordinary basis, as agreed or assessed.
(5) If any party wishes to make an application to vary order (4) above (the costs application):
(a) the applicant is to lodge and serve the costs application, submissions limited to three pages and any evidence in support within seven days of this decision;
(b) the respondent to the costs application is to lodge and serve any submissions limited to three pages and any evidence in response within 14 days of this decision;
(c) the applicant is to lodge and serve any submissions in reply limited to two pages within 21 days of this decision;
(d) the parties are to indicate in their submissions whether they consent to an order dispensing with an oral hearing of the costs application, and if they do not consent submissions of no more than one page as to why an oral hearing should be conducted rather than the costs application being determined on the papers. If a hearing is not dispensed with, the parties will be advised of a date for the hearing of the costs application.
I hereby certify that this is a true and accurate record of the reasons for decision of the New South Wales Civil and Administrative Tribunal.
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.
DeMarco
Macey [2025] NSWCATAP 131