[2012] VCAT 752
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2012-06-05
Ms J
Original judgment source is linked above.
Defects - whether settlement agreement between original owner and builder deprives a subsequent owner from taking proceedings for breach of a warranty under section 8 of the Domestic Building Contracts Act 1995.
Evidence - whether sufficient to raise settlement agreement without particulars as defence to claim; burden of proof, sufficiency of evidence.
Delic & Ors v Yahome Pty Ltd (Domestic Building) [2012] VCAT 752
Mr Lim, director and Mr B Gillies of counsel (written submissions only)
In addition to the building owner who was a party to a domestic building contract, any person who is the owner for the time being of the building or land in respect of which the domestic building work was carried out under the contract may take proceedings for a breach of any of the warranties listed in section 8 as if that person was a party to the contract.
(iii) Installation of TV antenna: $150
(iv) Telephone connection wiring: $165
(v) Cleaning and removal of builders rubble: $350
(b) Second Applicant:
- (i) Cost of repairs: $165,973
- (ii) Cost of alternate accommodation in a serviced
(iii) Installation of TV antenna: $150
(iv) Cleaning and removal of builders rubble: $380
(c) Third Applicant:
- (i) Cost of repairs: $211,608
- (ii) Cost of alternate accommodation in a serviced
(iii) Installation of TV antenna: $209
(iv) Rectification of evaporative cooling system: $200
(v) Telephone connection wiring: $165
(1) The Respondent [the Vendor] pay the Applicants [the Builder] the sum of $255,000.00 as follows:
(b) The balance thereof to be paid by three equal instalments within fourteen days of completion of the maintenance items relating to each of the dwellings located at Lots 832, 833 and 834 in accordance with the attached list.
(2) The Applicants complete dwellings at Lots 832, 833 and 834 on or before 5 May 2010.
(3) The Applicants release the Respondent from any further claim in relation to the monies.
(4) The Respondent releases the Applicants from any further claims or monetary compensation thereafter relating to any defects previously identified.
All units with the exception of Lots 832, 833 and 834 were completed by April, 2010. The compensation received by Nguyen was received for the defects which the Respondent did not rectify. Therefore, Nguyen took responsibility for those defects. The defects identified in the list produced to Salvatore Ferraro at the time of making his affidavit dated 4 May, 2012 and identified as 'SF-8' where the items that remained as the responsibility of the Respondent and which he had subsequently rectified.
[1] This amount represents the aggregate of those expenses incurred by the First Applicant which are being claimed and which are listed in a document entitled Loss and Damage filed with the Tribunal on the first day of hearing.
[2] This amount represents the aggregate of those expenses incurred by the Second Applicant which are being claimed and which are listed in a document entitled Loss and Damage filed with the Tribunal on the first day of hearing.
[3] This amount represents the aggregate of those expenses incurred by the Third Applicant which are being claimed and which are listed in a document entitled Loss and Damage filed with the Tribunal on the first day of hearing.
[4] [1981] HCA 3; (1981) 145 CLR 625 per Gibbs CJ at 637
[5] Assuming 8 hours of labour for each working day.
[6] Potter v Minahan [1908] HCA 63; (1908) 7 CLR 277 per O'Conner J at 304.
Delic & Ors
Yahome Pty Ltd
(1981) 145 CLR 625
(1908) 7 CLR 277