[2012] VCAT 1755
Victorian Civil and Administrative Tribunal
2012-11-15
Mr J
Original judgment source is linked above.
Section 77 Planning and Environment Act 1987; Whitehorse Planning Scheme; Residential 1 zone ; 4 storey apartment building; building height; neighbourhood character; visual bulk; interface with neighbouring dwellings; Blackburn Activity Centre and Megamile; Urban Design Framework; Amendment C143;.
Alison Vickers, Keith Creasy, Des Ktenas, Elizabeth Nanayakkara, Paul Wolfram, Donna Goldsmith, Stephen Kalenderian, Glenice McCurdie and Andrew Faska
Dekas One Pty Ltd v Whitehorse CC [2012] VCAT 1755
Mr J Holdsworth, Architect and Urban Design Consultant
A report from Mr R Fairlie, Traffic Engineer, Ratio Consultants was filed. With the agreement of the parties Mr Fairlie's evidence was accepted and he was not called to give evidence.
For Alison Vickers, Keith Creasy, Des Ktenas, Elizabeth Nanayakkara, Paul Wolfram, Anne Bachelard, Donna Goldsmith, Stephen Kalenderian, Glenice McCurdie and Andrew Faska
Construction of a four storey building containing 61 apartment style dwellings over basement car parking
Application under Section 77 of the Planning and Environment Act 1987.
Clause 32.01-4: Construction of more than one dwelling on a lot.
Clause 52.06-1: Reduce the amount of car parking required:
Clause 52.29: Create access onto a road in a Road Zone - category one.
Clauses 11, 15.01, 16.01, 21.06, 22.03, 22.06, 52.06, 52.29, 52.34, 52.36, 55 and 65
The subject land comprises three adjoining residential lots each of which is currently occupied by a single storey dwelling, one of which is used for a massage therapy centre. Combined, these three properties create a development site with a frontage of about 63 metres, depth of about 45 metres and overall area of 2709 square metres. Adjoining properties to the north and west are occupied by single storey dwellings while a three-storey building to be used for office and apartments is under construction on land to the east. Contextually the land is located on the edge of an established residential area adjacent to the Blackburn Activity Centre.
(oral reasons given at the hearing with minor revisions)
Is there policy support for the proposed development?
To identify strategic redevelopment sites for large residential developments in Metropolitan Melbourne.
Is the building acceptable having regard to neighbourhood character considerations
Will the proposed development result in unreasonable impacts on the amenity?
All of the above requirements must be to the satisfaction of the Responsible Authority.
Once approved these plans and documents become the endorsed plans of this permit.
Once submitted and approved to the satisfaction of the Responsible Authority, the ESD Management Plan will form part of the endorsed plans under this permit.
The requirements of the ESD Management Plan must be demonstrated on the plans and elevations submitted for endorsement, and the requirements of this plan must be implemented by the building manager, owners and occupiers of the site when constructing and fitting out the residential building, and for the duration of the building's operation in accordance with this permit, to the satisfaction of the Responsible Authority.
Once submitted and approved to the satisfaction of the Responsible Authority, the Green Travel Plan will form part of the endorsed plans under this permit.
Where appropriate, the requirements of the Green Travel Plan must be demonstrated on the plans and elevations submitted for endorsement, and the requirements of this plan must be implemented by the building manager, owners and occupiers of the site for the duration of the building's operation in accordance with this permit, to the satisfaction of the Responsible Authority.
The requirements of the Waste Management Plan must be demonstrated on the plans and elevations submitted for endorsement.
Once submitted to and approved by the Responsible Authority, the Waste Management Plan must form part of the documents endorsed as part of this planning permit.
The requirements of the Waste Management Plan must be implemented by the building manager, owners and occupiers of the site for the duration of the building's operation in accordance with this permit, to the satisfaction of the Responsible Authority.
The Construction Management Plan must address: any demolition, bulk excavation, management of the construction site, land disturbance, hours of construction, noise, control of dust, public safety, traffic management, construction vehicle road routes, soiling and cleaning of roadways, discharge of any polluted water, security fencing, disposal of site waste and any potentially contaminated materials, location of site offices, redirection of any above or underground services, and site lighting during any night works.
The Construction Management Plan must be prepared in consultation with Council's Transport Team- Engineering and Environmental Services, Engineering Asset Team- Engineering and Environmental Services Building Department and Community Laws Department.
Once submitted to and approved by the Responsible Authority the Construction Management Plan will form part of the documents endorsed as part of this planning permit.
The Construction Management Plan must be implemented to the satisfaction of the Responsible Authority and a contact name and phone numbers for the site manager must be provided to the Responsible Authority.
The requirements of the Arborist Report must be demonstrated on the plans and elevations submitted for endorsement.
Once submitted to and approved by the Responsible Authority, the Arborist Report must form part of the documents endorsed as part of this planning permit.
The requirements of the Arborist Report must be implemented by the owner and site manager for the duration of the demolition, construction and landscaping of the site in accordance with this permit, to the satisfaction of the Responsible Authority. This includes the erection and maintenance of tree protection fencing and implementation of Tree Protection Zone requirements must be erected on the subject site.
Landscaping in accordance with this approved plan and schedule shall be completed before the building is occupied.
Once approved these plans become the endorsed plans of this permit.
Prior to the commencement of any works on the subject land a site development layout plan together with detailed design plans and specifications for outfall drainage external to the site shall be submitted for approval by the Responsible Authority. All outfall drainage works must be completed to the satisfaction of the Responsible Authority prior to the occupation of buildings.
The Responsible Authority may extend the periods referred to if a request is made in writing before the permit expires or within three months afterwards.
[1] We have considered all submissions presented by the parties although we do not recite all of the contents in these reasons.
[2] These conditions were tabled by Mr Freeman on behalf of VicRoads. The conditions require the access point to be designed to take into account the street trees and utility service pits.
[3] One dwelling appears to be also used for massage therapy centre.
[4] Clause 21 of the Whitehorse Planning Scheme
Dekas One Pty Ltd
Whitehorse CC