[2023] VCAT 1262
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2023-11-15
Senior Member J
Original judgment source is linked above.
Review of refusal of application for registration as Domestic Builder (Unlimited) - whether applicant has the level of practical experience required - Building Act 1993 ss 171, 185-187, Building Regulations 2018, reg 258, cl 31 of Schedule 9.
11 May 2023 (with written submissions received subsequently)
Daggecen v Victorian Building Authority (Review and Regulation) [2023] VCAT 1262
(a) includes compliance with any supervision requirements during the obtaining of that experience; and
(b) must have been obtained in the 7 years before the application for registration was made.
The plan-based exercise tested your ability to apply the National Construction Code and Australian Standards AS 1684.4 and AS 2870. The pass mark for the plan-based exercise is 70%. You received 33 marks out of 77, or 49%.[1]
Broken down by topic, your scores were:
(a) gutters and downpipes - 4 marks out of 4
(b) smoke alarms - 2 marks out of 6
(c) masonry - 8 marks out of 8
(d) general - 6 marks out of 14
(e) roof construction - 1 mark out of 12
(f) timber framing - 6 marks out of 14
(g) conventional raft slab design - 6 marks out of 9
(h) timber wall bracing - 0 marks out of 10.
Obviously, your score was below the 70% pass mark, and by a considerable margin. You scored well in some topics, but there were others where you performed poorly. You appear not to have had time to attempt the questions on timber wall bracing, but you would not have achieved the 70% pass mark even if you had answered all of those questions correctly.
Your score in the plan-based exercise raises concerns about the level of your knowledge and experience. It would form sufficient basis on its own for refusing to grant your application for registration. In your case, it reinforces the conclusion arising from your answers in the discussion of projects.[2]
1. Apply for a building permit for the work (2)
2. Enter into and administer appropriate contracts and insurances (6)
3. Produce cost estimates and apply business financial management skills (2)
4. Coordinate on-site construction works (3)
5. Ensure works are planned and conducted safely (1)
6. Domestic building work that you carried out (41).
• [Area of Experience 2] You did not demonstrate appropriate knowledge and experience in the following aspects of entering into and administering appropriate contracts and insurances:
o Completion of handover including certificates of compliance,
o Managing the building work from start to finish.
• [Area of Experience 3] You failed to demonstrate satisfactory knowledge and experience in the following aspect of producing cost estimates and applying business financial management skills:
o Preparing cost estimates and quotations for project/part of project.
• [Area of Experience 4] You did not demonstrate sufficient knowledge and experience in the following aspects of co-ordinating onsite construction works:
o Developing and monitoring progress schedules for the work,
o Providing on-site day to day supervision of the project,
• [Area of Experience 6] You did not demonstrate sufficient knowledge and experience managing, carrying out or arranging the following critical elements of domestic building work.
Pre-Base Work:
o Interpreting architectural plans, drawings and specifications,
o Interpreting engineering designs, plans, drawings and specifications,
o Establishing the construction site,
o Provided protection works for the adjoining property,
o Arranging services (power /sewer /stormwater/ gas/ telecoms),
o Excavation/site levelling.
Base Work:
o Construction of concrete raft slabs,
o Construction of formwork for concrete slabs,
o Selecting installation of steel reinforcements,
o Installation of damp-proofing.
Framework:
o Construction of sub-floor framing,
o Construction of wall framing - stick build,
o Construction of wall framing - prefabricated,
o Construction of fire rated party walls.
Lock-Up Work:
o Installation of roof tiles,
o Installation of roof sheeting,
o Internal/external services rough-in
Final Work:
o Selecting and installation of waterproofing,
o Installation of tiling - wall and floor,
o Completed fixings - architraves/ skirting/ doors/ hardware.
Please be aware that the above points are examples only, provided to enable you to understand some of the key concerns held by the VBA in relation to your level of knowledge and experience.
Registration as a Domestic Builder (Unlimited)
A person registered in the class of Domestic Builder (Unlimited) is responsible for carrying out, or managing or arranging the carrying out of all components of domestic building work for the construction, renovation, improvement or maintenance of a home (class 1, 2, and 4 buildings, and associated class 10 buildings).
21. Having regard to the applicant's results in the plan-based exercise (even considered alone), the Tribunal ought not be satisfied that the applicant has three years' practical experience to be registered in the unlimited class of registration sought.
22. The applicant's overall mark of 43% in the plan-based exercise falls well short of the VBA's pass-mark of 70%.
23. Further, the applicant's results for critical aspects of domestic building work (2/6 for smoke alarms, 1/12 for roof construction, 6/14 for timber framing) significant[ly] militate against the conclusion that the Tribunal should be satisfied (as required by s 171(1)(a)(i) of the Act) that the applicant has three years of relevant practical experience. That is, the Tribunal ought not be satisfied that the applicant has obtained the requisite breadth of practical experience to be registered in the class of domestic builder (unlimited). Had she done so, she would have fared better on the plan-based exercise.
24. On the VBA's understanding, the applicant only contends that two errors were made by the VBA's assessor when marking the applicant's plan-based exercise. The applicant's submissions in this respect were made at hearing; her post-hearing submissions do not assert any error in the marking of the plan-based exercise. At hearing, the applicant addressed two elements of the plan-based exercise.
24.1 First, the applicant contended that the assessor ought not to have given her a score of 0/10 for the roof drawing exercise.[7] In the VBA's submission, the mark allocated to the applicant for this exercise was appropriate given the applicant's clear errors with respect to the roof/ drawing exercise. In the alternative, even if the applicant is correct and she should be given some marks for her answer, the overall result would not change. The applicant has not specified the mark she submits that she should be given, although she apparently accepts some errors in her answer. On that basis, and assuming the applicant was given 5/10 marks for her answers here (contrary to the VBA's primary submission), her total score on the plan-based exercise would only improve to be 38 from a possible 77 marks (49%), still well short of the required 70%.
24.2 Second, the applicant apparently contended that the assessor ought to have given her some marks, rather than no marks, for her response on the question requiring her to draw the appropriate location of smoke alarms.[8] The applicant complains that she was given no marks (from a total of three possible marks) when, in her submission, her answer was "not that bad, actually".[9] That submission is misconceived. That the applicant erroneously considers her answer in this regard was "not that bad" might be considered by the Tribunal to be a further indication of a lack of relevant experience. The applicant mis-placed the smoke detectors she did include on drawing 2, and only included two smoke detectors when three were required. Alternatively, in this respect, even if the applicant were given full marks for this question, she would still not have reached the 70% grade required to satisfactorily complete the plan-based exercise.
25. The applicant also apparently impugns the VBA's approach of requiring her to undertake a plan-based exercise at all, and of the breadth of matters assessed. In her VCAT application (TB 309) the applicant apparently complains about the matters assessed, stating: "As I have a diploma in building and construction, I did not focus my study on drawings with the knowledge the diploma bypasses the drawings." Similar contentions were advanced by the applicant in her post-hearing submission. These complaints are misconceived: the unlimited category of registration sought by the applicant requires a broad-range of experience, which can only be tested by canvassing many of the broad-range of matters relevant to domestic building work.
26. Further, the applicant's complaints of general unfairness are misconceived when regard is had to the fact that the audio-recording and plan-based exercise show that the applicant was given additional time to complete the plan-based exercise over and above the specified 5 minutes reading and 55 minutes completion time stipulated on the first page of the plan-based exercise. That is, to the extent that the applicant was treated differently to others, an advantage was conferred upon her, not a disadvantage.
Plan Based Exercise- The applicant's submissions are to identify those questions in the PBE where she contends she was unfairly marked down, and for each, what mark she contends she should have received, and why.
I must also address your claim of discrimination. From the recording and from reviewing the documents relating to your application, I do not detect anything to suggest that you were treated differently to any other applicant, whether male or female. I comment below on the inclusion of the plan-based exercise in your assessment and the fact that your referee was not contacted. In terms of the discussion of your projects, I do not doubt that it was tiring for you. I accept that it is likely to have been stressful, as any assessment process normally is. While it is apparent from the recording that you became upset about 30 minutes before the end of the interview, the assessor did ask you whether you wanted to proceed and you agreed to continue. The number of topics covered by an assessor, the number of questions asked and the precise nature of those questions will vary according to many circumstances. In your case, they did not depart in any significant way from the normal range.
Finally, in relation to your claim that the assessor had prejudged the outcome, I can see no basis for this claim from the material before me. Nor do I question the assessor's ability to undertake assessments of this kind.
Specific findings made in the Internal Review Decision relied on by the VBA
For most steps, the assessor was satisfied that you had sufficient direct experience or had demonstrated an adequate understanding. However, a number of your responses raised concerns about your level of knowledge and experience across the full spectrum of domestic building work. I do not propose to set out all of them, but will provide a few specific examples:
(a) You said that a works protection notice relates to demolition work. You referred (correctly) to Forms 6-9. However, the need for protection of an adjoining property is not limited to demolition work: see the definition of "protection work" in section 3(1) of the Act.
(b) You were not able to accurately describe how power was provided to a kitchen island bench for the Lansdowne Road project.
(c) You could not say what "UB" or "PFC" stood for in engineering drawings. (They stand for "universal beam" and "parallel flange channel" beams.)
(d) When asked where damp-proofing would be installed, you referred (correctly) to the rebate. You did not mention that damp-proofing would also be required above windows and doors.
In addition, many of your answers were vague or incomplete. From the recording of your interview, this seemed to be more than hesitancy in relation to technical terms or expressions. It suggested that you have not had the amount of experience that allows you to generalise about what is involved at certain stages of construction, or the matters to which you should pay particular attention to ensure the building work is compliant.
While some of these issues might be considered minor in isolation, in combination they present a picture of significant gaps in your knowledge and experience. In light of the unlimited nature of the domestic building work authorised by registration in the class of domestic builder (unlimited) (see paragraph 28 above)[11], these gaps are too great to overlook and lead to the conclusion that you do not satisfy the experience component of the prescribed qualification.
In response to some other matters raised in your application for internal review:
(a) It is appropriate that applicants only be allowed to refer to clear copies of drawings. This promotes the objectivity of the assessment process. In any event, it is not clear to me that you would have been assisted in answering any specific questions by referring to the types of highlighting and notes that you mentioned in your grounds for internal review.
(b) In many cases, the assessor did repeat his questions. From the recording, he was clearly concerned to ensure you had fully understood what he had asked. I do not consider this to have disadvantaged you, although it did increase the length of the assessment.
(c) Objectively, the number of plumbing and electrical questions was not high.
Ms Daggecen's post-hearing written submissions about the Interview
It's not helpful at all, I feel it's getting harder and harder
To many relatives get license and it's not that hard, it didn't take 3 hours. I feel like I'm here to fail"
I said "I feel like I'm not here to pass. I feel like because I'm woman it's getting harder"
I said " It's stressfull I got thing mixed up. I miss understand somethings".
Incorrect statements in application documentation
Ms Daggecen's The applicant relied in her application on five building projects, carried out over several years, in support of her claim to have three years' relevant practical experience. The applicant set out, in respect of each project, the duration of each project and her onsite hours each week. Presuming the applicant worked without any breaks on those projects, the total hours worked on each project (as claimed by the applicant) can be calculated as follows:
That is, the applicant's claimed practical experience was for a total of 4,280 hours. This is some 1,480 hours short of three-years full time experience (being 5,760 hours, calculated as 40 hours per week for 48 weeks per year, a total of 1,920 hours per year and 5,760 hours for three years). While the applicant said at hearing that she did additional relevant work , no particulars of that work have been provided.
On this basis alone, the Tribunal may conclude that (even presuming the work claimed was relevant practical work) that it is not satisfied that the applicant has three years' relevant practical experience.
[1] In fact this equates to a mark of 43%. The 49% figure appears to refer to the 33 marks out of 66 marks' worth of questions which Ms Daggecen actually attempted.
[5] Ms Daggecen submitted an application dated 14 October 2021. However, she was required to resubmit her application as she had not provided sufficient identity verification documentation. Her resubmitted application was dated 19 November 2021.
[6] The third option, for "Carried out' was only given for the sub-components for Area of Experience 6 (being the one which relates to actually carrying out the physical building work).
[7] See the applicant's oral submissions, transcript pp 67 - 69. The relevant question in the plan-based exercise is question 18 (on page 7 of 10) which in turn refers to drawing no. 4 of 5.
[8] See the applicant's oral submissions, transcript , p 70. The relevant question in the plan-based exercise is question 3 (on page 3 of 10) which in turn refers to drawing no. 2 of 5.
[11] This is a reference to a DB-U being authorised to carry out all components of domestic building work, and therefore needing to have commensurate proficiency.
[16] At TB 159-164. Mr Balikel also completed an earlier Technical Referee Report, dated 12 October 2021 (TB 25-29), accompanying the original application by Ms Daggecen. But as noted, that application had to be re-done, including the Technical Referee Report.
[20] VBA's Final Submissions, [39]-[41].
Daggecen
Victorian Building Authority