austlii:vic/VBAB/2025/124
General information, not legal advice.
VBAB
2025-10-10
Member J
Original judgment source is linked above.
The proposed building work that gives rise to the need for protection work is Alterations and additions to double storey dwelling, including extension to rear.
Note: Clause references refer to the Determination & Orders
of BAB Appeal Case Number 456574 determined on 27/06/2025.
The building of the first-floor boundary wall at 547 Royal Parade Parkville would be built in such a way as to avoid the need to work in the neighbouring property at 549 Royal Parade Parkville.
roof in the zone of works above existing wall height. A ply sheet covering will be installed from within 547
brick wall works, with a shadecloth covering elsewhere. The barrier will be installed from within 547 boundary.
B. Disagree with the proposed protection work for the following reasons:
[68] An order for setting aside or remitter revives the jurisdiction of the original arbitrator to the extent that the order, on its proper construction, so provides: Interbulk Ltd v Aiden Shipping Co Ltd (The "Vimeira" (No 1)) [1985] 2 Lloyd's Rep 410.
[69] There is Australian authority to the effect that if an award is ordered to be wholly set aside, then absent any other indication in the order, the award is deprived of all legal effect, the arbitrator reverts to his status immediately before the award was determined, the arbitrator is no longer functus officio, and the arbitrator thus remains seized of the reference: Re Scibilia & Lejo Holdings Pty Ltd Arbitration [1985] 1 Qd R 94 at 97 and 102.
For clarity, the form 9 being appealed is dated 10.07.25 and was issued after receipt of the form 8 response from the applicant.
(a) amendments made to the protection work set out in the revised Form 7 are 'minor', and the proposed protection work does not adequately protect those accessing the rear entrance, laundry, toilet, or clothesline and back yard from items falling from the building work;
(b) the proposed protection work set out in the revised Form 7 fails to protect against silica dust, falling object and 'hazards arising over the extended construction period';
(c) reliance on access to the Applicant's lean-to roof for the installation of ply sheeting and sandbags should not be permitted as 'safer and more appropriate methods exist';
(d) the Interested Parties and the RBS have ignored alternative proposals submitted by the Applicant 'involving steel props and sliding track to mount the ply sheets with catch trays on the 547 side of the boundary wall, which would provide a genuine physical barrier and better compliance with OH&S and WorkSafe requirements'.
(a) silica dust will be mitigated by cutting and mixing works being done outside the first floor level with appropriate equipment such as a wet saw;
(b) vertical ply sheeting proposed by the Interested Parties will act as sufficient protection against falling debris;
(c) there should be no reduced enjoyment for the Applicant of her property 'outside of what any standard building works may cause for a very limited time'.
[1] Clause 17 of Schedule 3 to the Building Act 1993 provides: 'Unless the Building Appeals Board otherwise determines, a party to a proceeding before the Board must bear his, her or its own costs'.
[2] [2009] WASC 205, [68-69], cited with approval in ABB Service Pty Ltd v Pyrmont Light Rail Company Ltd [2010] NSWSC 831; (2010) 77 NSWLR 321, [96].
�D'Agostino
Merrick [2025] VBAB 124;
(2010) 77 NSWLR 321