[2013] VCAT 608
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2013-04-29
Original judgment source is linked above.
Real Property List; Claim for damages and injunctive relief under Section 16(1) Water Act 1989; Whether moisture damage to residential unit by subdivisional Owners Corporation's failure to upgrade drainage on common driveway to respond to additional water flows caused by landscaping work on more elevated unit in same subdivision; Whether drainage condition in subdivisional development permit requires Owners Corporation to upgrade drainage of common property to accommodate changed circumstances
Cullinane v Owners Corporation 1 Plan No. PS434498R & Anor (Real Property) [2013] VCAT 608
Mr Settle of counsel, instructed by McMahon Fearnley Lawyers Pty Ltd
Mr N. Jones of counsel, instructed by LFS Legal Barristers and Solicitors
Only the members of Owners Corporation No. 2 are entitled to use Common Property No. 1. The members of Owners Corporation No. 1 are responsible for the maintenance and upkeep of the sewerage facilities within Lots 2, 3, 4, 5, 6, 7, 8, 9, 10, 11 and Common Property No. 1.
(a) there is a flow of water from the land of a person onto any other land; and
(ii) damage to the property (whether real or personal) of any other person; or
the person who caused the flow is liable to pay damages to that other person in respect of that injury, damage or loss.
(5) If the causing of, or the interference with, the flow (as the case requires) was given rise to by works constructed or any other act done or omitted to be done on any land at a time before the current occupier became the occupier of the land, the current occupier is liable to pay damages in respect of the injury, damage or loss if the current occupier has failed to take any steps reasonably available to prevent the causing of, or the interference with, the flow (as the case requires) being so given rise to.
(1) In determining whether a flow of water is reasonable or not reasonable, account must be taken of all the circumstances including the following matters -
(a) whether or not the flow, or the act or works that caused the flow, was or were authorised;
(b) the extent to which any conditions or requirements imposed under this Act in relation to an authorisation were complied with;
(c) whether or not the flow conforms with any guidelines or principles published by the Minister with respect to the drainage of the area;
(d) whether or not account was taken at the relevant time of the likely impact of the flow on drainage in the area having regard to the information then reasonably available about the cumulative effects on drainage of works and activities in the area;
(e) the uses to which the lands concerned and any other lands in the vicinity are put;
(ii) collected, stored or concentrated on that land; or
and if so, for what purpose and with what degree of care this was done;
(h) whether or not the flow was affected by any works restricting the flow of water along a waterway;
(i) whether or not the flow is likely to damage any waterway, wetland or aquifer.
(2) In taking account of the matters specified in subsection (1), greater weight must be attached to the matters specified in paragraphs (a), (b), (c) and (d) than to the other specified matters.
caused the flow by omission in failing to [kerb] the driveway and install proper or adequate drainage on its property. Both were 'a' cause of the damage to the Applicant's property.
...the eastern side of the driveway, being the side closest to Unit 3, is generally lower than the western side of the driveway/swale. In one position this is about 140mm lower.
to collect the unreasonable flow of water from the [Owners Corporations] land, and land further uphill, and dispose of that water.
He said she was obliged to carry out drainage only coping with the water falling onto her own unit.
The evidence of Mr Casamento was that that was not feasible as, in effect, this would result in everything being out of square.
If only part of the floor is jacked, to what height should it be jacked? Will the consequential damage be limited to the extent proposed by Mr Merlo?
Unit 3 appears to be affected in general by elevated moist/damp conditions as evidenced by moss/mildew in areas completely unrelated with the flow of surface water run-off from Unit 11 and across the common driveway.
He produced photographs said to illustrate this point in a number of places in the roof and in the wall below the bay window at the front of the house. Mr Pemberton said:
Mrs Cullinane advised the western and southern walls of the main bedroom were affected [by mould and mildew] however inspection failed to identify evidence of said infiltration; Mrs Cullinane alleges to have cleaned the affected areas. Mrs Cullinane informed the floor coverings and window furnishings were removed by the Contents Insurers.
The south-west side elevation ('blind side') depicts an absence of drainage provision; the retaining garden wall of a timber 'sleeper' construction, the brick wall of the unit and the timber 'sleeper' forming the base/threshold of the side/rear gate effectively creates an enclosure capturing the rainfall and surface water accumulating on the gravel path during wet weather conditions.
Drainage is the collection and removal of excess surface water and groundwater from land using surface or subsurface drains. The surface drainage is ineffective due to the lack of a positive culvert at the centre of the driveway at a depth that can cope with the volume of water during heavy rainfall. During the recent drought the ineffective surface drainage may not have been obvious however the increase in rainfall over recent times has resulted in an excessive flow of surface and ground water from the land above the common property driveway and the common property driveway itself towards unit 3.
excellent sub-floor clearance which averages 400mm from the ground to the underside of the bearers and 600mm from the ground to the underside of the particle board flooring in the area beneath bedroom 1 and the ensuite.
The building distress experienced at this site is the result of differential movement of the stumps caused by heave and settlement as a result of moisture variation in the soil.
out of level by up to 49mm, which is considered quite substantial. I concluded that there was enough evidence to suggest that differential movement (heave and settlement) of the stumps is still occurring.
The crossfall opposite the west wall is relatively steep (up to 141mm), with a shallow swale roughly centralised and varying in depth. The crossfall is considerably steeper at the driveway entrance to the garage at the rear of Unit 11. Water runs down a slope with a level drop of 1189mm to the surface swale. There is absolutely no chance that the shallow swale would capture this rainfall run-off [from the driveway], and consequently would flow directly into Unit 3.
Water captured on the membrane [viz, the reed mat] would also flow across the driveway and into the subject property. The surface area [viz, covered by riverstones] is quite substantial. The owner [Ms Cullinane] has photographic evidence of this sheet flow from this area during heavy rainfall.
highly recommended that an apron of concrete paving be installed along this path with a fall away from the building. The water should be captured by a spoon drain and discharged into a stormwater drain.
There are acute surface and sub-surface drainage issues in particular along the south side [of Ms Cullinane's unit] as well as the front/east side of the unit. Noting that the original unit site was benched into a hillside, this should have dictated carefully thought out drainage provision to protect the foundations and prevent sub-floor dampness. Unfortunately, such drainage initiatives were never carried out.
the absence of any surface and sub-surface drainage along the south side of the unit combined with the very limited subfloor ventilation
In Mr Merlo's view, run-off from the Owners Corporation's driveway was not a significant issue. In his view, the 'dished profile of the driveway was adequate to contain run-off'. He conceded that on occasions of 'very heavy rain' there could possibly be some overflow run-off in the northern edge of the driveway, that is the street end.
there has been no moisture related damage to the underside and consequently any discolouration to the flooring in the front bedroom ... must have been due to other causes.
He suggested condensation as a possible cause 'particularly if the underlay was rubber'. Mr Merlo also said that, in his view, the Council drainage in Ayers Road was inadequate. He observed 'generally, the open earth drains are too shallow and in particular on the eastern side is overgrown'.
The soil in this area is considered to be Class M - Moderately Reactive, and therefore not prone to substantial movement - swelling and shrinkage due to varying moisture content.
He stood by his opinion that heave was not an issue or a significant one. The rectification of the drainage would rectify any heave.
that the landscaping of Unit 11 has been a significant issue (if any at all) with respect to moisture accumulating on the gravel path along the western side of Unit 3. This water from the landscaping would merely be picked up by what is considered to be rather effective profiling of the large driveway and adequate fall to strategically located drains.
Owners Corporation's allotment at the eastern boundary, he disagreed. First, he said, it would require the destruction of an existing hedge. Secondly:
It would not be possible to achieve the required smooth firm clay floor of the trench using a ditch witch nor would it be possible to achieve a proper grade to achieve fall - essential for the drain to function. The proposed drain, therefore, in the writer's opinion, would be non-functional would arguably actually collect water and generate increased seepage through the walls into the subject Unit 3.
A ditch witch would normally have a maximum width of 150mm. Not only would it be very difficult to lay a pipe at a depth of approximately 1.5m but the installation of a membrane in the trench would be virtually impossible.
[19] It is important at this stage to keep steadily in mind precisely the question that is being addressed. The applicant relies upon a statutory cause of action in the Water Act. Where the necessary facts are made out, the cause of action under Section 16(1) appears to be one of strict liability, that is, it is not necessary to demonstrate any want of reasonable care. The mere proof of causation seems to be enough. Nor are we seeking to answer the question whether the respondents owed a duty of care in accordance with the Common Law tort of negligence to Mr Turner. The issue of "duty" arises only in so far as the establishment of its existence and breach is the only means whereby it can be said that the respondents "caused" the flow of water.
[20] Mr Attiwill referred me to an unreported decision of the Court of Appeal in the matter of Lilley v Alpine Resorts Commission (3 April 1998). In Lilley's case the plaintiff was skiing on the "summit run" at Mt Buller Ski Resort when she collided with a snowboarder, suffering physical and psychological injury. She sued the Alpine Resorts Commission and Buller Ski Lifts Limited (the ski tow operator on the summit run) but not the snowboarder. After a lengthy trial the Judge gave a verdict for the defendant. The Judge found that the defendants had breached their duty to the plaintiff in failing to inspect the run and failing to erect a sign or signs. The trial judge concluded that no causal link had been demonstrated. His conclusion was upheld by the Court of Appeal, specifically by reference to a passage from the judgment of Mason J. (as he then was) in Sutherland Shire Council v Hayman [1985] HCA 41; (1985) 157 CLR 424, 467, where His Honour said:
"When there is a duty to take a precaution against damage occurring to others through the default of third parties or through accident, a breach of the duty may be regarded as materially causal or materially contributing to that damage, should it occur, subject of course to the question whether performance of the duty would have averted the harm."
The trial judge concluded and the Court of Appeal agreed that it was not demonstrated that any of the measures suggested would have protected the plaintiff from her injury.
[21] To ascertain whether in terms of this formulation any causal link can be made between the omissions of the respondents and the flow of water, one must ask what duties if any did the respondents come under in the circumstance.
(2) The responsible authority may include any other condition that it thinks fit including -
(a) a condition that specified things are to be done to the satisfaction of the responsible authority a Minister, public authority, municipal council or referral authority; and
Cullinane
Owners Corporation 1 Plan No. PS434498R & Anor
(1985) 157 CLR 424