[2011] VCAT 311
Victorian Civil and Administrative Tribunal
2011-02-25
Original judgment source is linked above.
"SUPPLY AND INSTALL ITEMS: The following items shall be allowed in the Builder's price for the items listed below, being items requiring further documentation as for Nominated Sub-Contractors:"
A list of items then follows. With one exception, a monetary sum is specified next to each item, which is said to be inclusive of GST for the supply and installation. Next to the item "alarm alterations" there is no figure in the money column. Instead, there are the words: "Owner supplies".
"SUPPLY AND DELIVER ITEMS: The following items shall be allowed in the Builder's price for the items listed below, being items requiring further documentation for supply only as for nominated suppliers; the Builder shall allow for the cost of all fixing of these items:".
There follows a list of items including door and window hardware, hinges, locks and handles and cupboard knobs, lights, towel rails and various toiletry accessories, tiles, certain fixtures and fittings and a pair of new front doors. Next to each item are the words "Owner supplies", except for the new front doors, where a figure of $1,000.00 is specified.
"EXTENT: In accordance with the contract, the Builder is hereby notified that the proprietor will engage separate Contractors as set out in the schedule:
"All prime cost items shall be selected by the owners by the date as specified by the builder. The builder to provide reasonable notice to the owners".
"Please find detailed below a schedule outlining proposed installation date or supply date for prime cost and provisional sum items.
For example with the first item, you are required to supply the Builder with taps/toilet/shower fixtures by 15 April 2009".
There follows a list of 9 items next to each of which is what is described as a "supply/installation date".
"The Builder must give the owner a copy of any invoice, receipt or other document that shows the cost to the Builder of any prime cost item or labour and materials that relates to a provisional sum item as soon as practicable after receiving the same."
The Owners relied upon this clause in support of their claim that they had the right to be consulted as to the appointment of subcontractors and also the right to determine whether a particular sub-contractor should be engaged. The clause does not provide them with any such rights.
You've not provided reasonable notice of these costs. Furthermore, at last week's site meeting you did not mention painting works were to commence Monday 6 July 2006, and this is simply unacceptable.
At this stage we cannot accept your cost on painting works on the following basis:
Without the above we are unable to give you authority to proceed with your chosen or preferred supplier.
"We plan to submit the windows order this Tuesday (17/4/3) in order to avoid a 15% price rise and secure the delivery of the windows by the scheduled installation date. The windows are as specified by your architect except will be made from primed treated pine as previously discussed with Mark. You will recall treated pine has been recommended over cedar to provide you with longer wearing windows.
Please confirm by email that you are happy for us to proceed with the order". (Emphasis added)
"There is nothing in the definition of lock-up in the Act which requires a structure at lock-up stage to be impregnable nor on the face of it does an owner have any particular interest in having an impregnable structure at lock-up stage. The structure may and sometimes is used to store materials and prime cost items; but those materials and items are at that stage at the builder's risk not the owners' risk. The definition of lock-up stage appearing in the Act does not mention the concept of locking-up at all, hence there seems some plausibility in the view expressed by Mr Setford that a structure could have reached lock-up stage if secured by door fixed not by a lock but merely by a bent nail. If I regard the definition of lock-up stage from its very name as necessarily importing some concept that the structure has been locked, this does not in my view carry us the distance of requiring the structure to be impregnable except via access through a locked door."
"I understand that you are in the final stages of finalising your requirements with Ian and that by today, you will be able to confirm your acceptance of job details and final drawings as prepared by Fairmont Cabinets.
Once I receive the final documentation from Fairmont Cabinets, I will be able to finalise documentation for you signature and thus allowing the order to be confirmed and the moneys paid.
I hope that you are able to finalise your joinery/kitchen requirements today allowing us to finally move forward on this overdue item."
"38.00 The Builder may suspend the building works if the owner:
38.1 If the Builder suspends the building works, the Builder must immediately give notice in writing by registered post to the owner. The owner must remedy the breach within 7 days after receiving the notice. The Builder must recommence the building works within 21 days after the owner remedies the breach and gives notice of this to the Builder.
38.2 The date on which the building works are to be completed is changed and extended to cover the period of suspension".
"Pursuant to clause 26 and its relevant parts, "the Builder must not give effect to any variation unless the owner gives the Builder a signed consent to or request for the variation".
Pursuant to clause 37, the building period will be extended for as long as the building works delayed due to your failure to sign and return the variations requested by you as a result of:
(a) selection of larger tiles
(b) selection of a smaller mirror cabinet
(c) selection of a laundry stone bench top and kitchen stone waterfall
(d) your decision to require and supply cabinetry handles.
Pursuant to clause 38, the building works are suspended pending receipt by us of each of the four separate variation documents attached.
The building works will commence within 21 days after, pursuant to clause 38.1, the receipt of the last four documents signed by you.
If you do not sign and return the four variations within 7 days pursuant to Clause 26.5, your requests for the variations will be deemed withdrawn and as a consequence:
(a) the larger tiles will not be laid
(b) the bulk head above the smaller mirror cabinet will remain open
(c) the laundry stone bench top nor the kitchen waterfall will be included in the joinery order; and
(d) the Builder will select the cabinetry handles.
You are in breach of Clause 36 because you have refused and continue to refuse to supply prime cost and provisional sum items within 7 days of receiving the written request from the Builder.
The items are available for selection. You have refused to provide written selections - by signing and returning the attached variations you will be making the selections and authorising the variations.
Your continual failure to sign the variations and return them is an indication that you do not intend to be bound by the Contract and is a repudiation of the Contract and that breach of the Contract entitles us to suspend the building works and claim delayed damages until you rectify that breach of Contract.
Please forward the signed variations as a matter of urgency".
The letter concluded by suggesting a meeting to resolve matters.
"46.1 The Builder is in substantial breach of this Contract if the Builder:
................................................................................
46.2 If the Builder is in substantial breach of this Contract the Owner may give the Builder a written notice to remedy the breach;
Specifying the substantial breach;
Requiring the substantial breach to be remedied within 10 days after the notice is received by the Bulder; and
Stating that if the substantial breach is not remedied as required the Owner intends to end the Contract.
46.3 If the Builder does not remedy the substantial breach stated in the notice to remedy breach within 10 days of receiving that notice, the Owner may end this Contract by giving a further notice to that effect.
46.4 The Owner is not entitled to end this Contract under this Clause when the Owner is in substantial breach of this Contract."
"His Honour's analysis refers to a number of interpretations which have been applied to the word substantial over the years in different contexts. In broad terms the two strands of meaning are on the one hand 'of substance as distinct from ephemeral or nominal'. If applied in the present context this would mean that any breach going beyond the de minimis would be a substantial breach. The view which I think was espoused by Mr Gurr, counsel for the Serongs and the view adopted by Viscount Simon in the case referred to by Deane J in the passage quoted above, namely 'considerable, solid or big' in the context of a building contract would mean that only really important breaches would count. In my view, in the context of a building contract, the latter meaning is the one which should be given to the word 'substantial' or the phrase 'substantial breach'."
The photographs show numerous broken tiles. Although Mr Varasdi said that he was not aware of any broken tiles I am satisfied that these are likely to have occurred when the Builder's workmen were walking on the roof. Replacement of broken tiles is required but there appear to have been plenty of additional tiles on site. I accept Mr Croucher's evidence that the lower roof has not been re-tiled because the rendering had not been done. The delay in the rendering was the fault of the Owners for delay in choosing the render colour. Since the Contract is terminated and the completion of the lower roof is not being allowed to the Builder, the Owners are entitled to the cost of replacing the broken tiles with other tiles on site but not for the completion of the roof. Replacement of broken tiles has not been priced as a separate item but I will allow $200.00.
According to the label on one of the boards, these were to be undercoated and painted with two coats of paint within four weeks. They could not be painted until the Owners made up their minds about the colours they wanted. Mr Croucher said that the boards had been pre-primed, which would give short term protection and no deterioration of the boards was evident. I am not satisfied that there has been any breach and there is no proof of any loss or damage in any case.
Mr Kosa said that they should have been installed before the roof was tiled. Mr Croucher disagreed and said that downpipes are usually put on after rendering and brick cleaning, which had not been done. Whenever they should be installed, this is incomplete work, not a defect.
(iv) Dutch gables do not have an overhanging eave.
Mr Kosa said, correctly, that a notation on the plans provided that the new roof should match the existing roof. However a section of the roof in the plans shows quite clearly that there are to be no overhanging eaves. The notation on the plan is ambiguous. It might be intended to refer to general style. There is no specific reference to an eave overhang. However the section in the plan is clear and unambiguous. I accept Mr Croucher's evidence that the plans do not show any overhang and that the Builder has built it according to the plans.
Mr Kosa said there were no flashings to certain windows that he photographed. Mr Croucher agreed that those windows needed to be flashed and that this was incomplete work. He pointed out that, because of the overhanging eaves, no upper flashing was required and Mr Kosa agreed. I accept Mr Croucher's costing of $330.00 to flash the windows.
(vi) Cova wall panels not installed correctly
Mr Kosa listed a number of criticisms about the installation. One of these relates to a lower section of panelling having been replaced with blue board. There was a lengthy explanation given about this by Mr Varasdi. In essence, the upper floor had to be constructed square and the area of the House on which it was to be constructed was not square. He had to alter the framing to take up the difference. He then had insufficient space to accommodate the thickness of Cova panels in this position and so replaced them with blue board. His explanation appeared to satisfy the experts and the House has been completed by the new builder without interfering with this solution. Accordingly, I find no defect in regard to the blue board. As to the other criticisms, none of them is disputed. However neither expert was able to say that these matters would not have been done by the Builder if it had been allowed to finish the work. As a result, I find that they are items of incomplete work
This was a part of the wall that had to be bricked up. The mortar did not match the existing and has since been coloured by the replacement builder using "Naw Kaw", a product commonly used for the purpose. Mr Croucher says that it is incomplete work. Since the brick work had not even been cleaned down, the time for colour matching had not arrived so I agree that it is more accurately described as incomplete work. I will allow Mr Croucher's assessment of $130.00 to clean the brickwork but the colour must also be matched. There is no evidence as to the cost of that. I will allow $100.00.
(viii) Window in Bedroom 2 is too small and not flashed
The photograph shows a gap between the outer face of the window and the rear face of the outer skin of brickwork which Mr Kosa said was too large to be covered by a wind mould. Mr Varasdi said that he was awaiting specially machined wind moulds so in that respect, it would be incomplete work. However Mr Kosa also pointed out that the window does not match the other windows. Mr Croucher said that Variation 11, which added this window to the scope of works, does not say that the window must match the existing windows. That is true, but the notations on the plan referred to indicate an intention to achieve an appearance to match the existing House. Further, the very fact that the window is too narrow to bridge the brick cavity suggests that this is not what the parties would have intended by the variation. I think it was an implied term of the variation that the window to be supplied pursuant to it would reasonably match the rest of the project. It does not. Mr Kosa said that putting on an oversized flashing will not achieve a satisfactory result and I accept that evidence. According to Mr Croucher, the sill had also not been finished and it was the Builder's intention to flash it at that time. As to head flashing, both experts agreed that it would not be required. I have no evidence as to what it would cost to replace the window that has been supplied with one that would be a reasonable match. The best I can to do is to disallow the amount of this variation (Variation 11) because the Builder did not do what was required by it. The amount of the variation was $1,810.00, including GST.
Mr Kosa points out the absence of trimmers and connections between the framing to the gable end to the brick wall and the frame behind. The brick wall also needed to be built up. This is a part of the job that would require to be scaffolded. There is some partially completed framing to the gable end shown in Mr Kosa's photograph in regard to this item. I accept Mr Crouncher's view that the matters that he refers to are items of incomplete work. I will allow Mr Croucher's figure of $220.00 to build up the brick wall.
Wall panels between the rear doors have not been installed. The experts agreed that it was not within the scope of the Contract. I think that is right..
There is no flashing to the gable end of the chimney. Mr Croucher agreed but said at first that only caulking was required. He then agreed with Mr Kosa that a small flashing should be installed. I will allow Mr Croucher's figure of $95.00 to provide and install the flashing.
This was agreed between the experts. Although Mr Varasdi said that his subcontractor always uses the fibreglass tape that has been used, it seems that paper tape is required. The existing tape will need to be removed and the joins will need to be re-taped. I will allow Mr Croucher's figure of $420.00 to do that.
This was agreed. It is defective rather than incomplete work because the bats are there. They need to be straightened and I will allow Mr Croucher's figure of $55.00 for that.
(xiv) Plaster damage Consequential damage in house from broken tiles
The photographs show clear evidence of water penetration. Mr Varasdi said that there was no such evidence when he was on site and that he would have attended to it if there had been. Although the Owners have wrongly terminated the Contract and cannot now complain that the work is incomplete, I am satisfied on Mr Kosa's evidence that the leakage is due to broken tiles on the roof, caused by the Builder's workmen. I am also satisfied that, although the Builder did not get the opportunity to finish the lower roof, it ought to have replaced any tiles that its workmen broke in the meantime as soon as the breakage occurred. This claim for a defect is therefore made out. The areas concerned will need some minor repair and repainting. Mr Croucher allowed only $280.00 to do that.
The experts disagreed in their reports as to whether the plans show this wall to be moved. It appears that different versions of the drawings show the "existing" wall in different positions. Mr Kosa said that there used to be a reasonable gap to the window architrave and now there isn't. I have dealt with this issue in detail above. The plans are ambiguous but in the end, in order to maintain the dimensions of the en-suite as per the architect's drawings and allow for the passage of the sewer pipe down the wall, the wall had to be moved to its present position. Mr Kosa acknowledged that the only other place in which to run the sewer pipe was down the outside wall, since there was insufficient fall to allow it to run between the floor and the ceiling. I also note that when the Owners took over the project they did not alter the position of this wall. I find no defect.
Less Plastering and Plumbing in variations $ 6,808.80
Cube Building Services Pty Ltd
Fois